Market profile

South Korea

emerging * buildout: pending risk: pending outlook: pending

* maturity derived from capacity data; full assessment pending.

0.3
GW operational
0.8
GW in construction
12.0
GW pipeline
37
projects
Operational · 0.3 GW (4)Under Construction · 0.8 GW (2)Advanced Development · 2.9 GW (9)Early Development · 9.1 GW (15)Proposed · 7.1 GW (6)On Hold · 0.5 GW (1)
Progress to target
2%
0.3 GW operational of 14 GW by 2030
11th Basic Plan — 14.3 GW offshore wind by 2030
Next auction round
South Korea 2026 H2 Offshore Wind Auction
2026-H2 · fixed-price offtake auction (power contract; general + public-led + floating pots) · planned
2.4 GW offered
full auction outlook ↓

Assessment

Assessment pending

This market has a derived snapshot above but no in-depth assessment yet. Authored coverage rolls out market by market; the data here is live in the meantime.

State of the market

as of 2026-09-09
0%
of GW sited through contested rounds
delivered (COD actuals)unweighted dated pipeline (building / contracted / early)Expected Buildout (confidence-weighted)national target (range)superseded targettoday
0510152025GW2020202520302035today+ early → 11EXPECTED BUILDOUT → 6.9 GW+ contracted → 3.4+ building → 0.7 GW0.3 GW operational11 GW target · 203025 GW target · 203511th Basic Plan — 14.3 GW offshore wind by 2030 — superseded14 · superseded

Teal line = the Hafrok Expected Buildout (confidence-weighted): 13 GW of live pipeline weights to 7.4 GW expected to complete, timed by each project's COD distribution (mass beyond 2037 not drawn). Bands are the unweighted dated pipeline — the Expected Buildout also models on-hold and undated projects, so it can sit above them. 2.0 GW of pipeline has no dated COD and is not in the bands.

How this line is made

The Expected Buildout line answers one question: of the pipeline announced today, how much actually gets built, and when? It is not a scenario and not a target tracker — it is the database's live pipeline, passed through two filters measured from the industry's own delivery record.

Whether a project completes. Every project in development carries a completion weight, banded Delivering / Expected / Prospective / Fragile. A proposal — a site where no authority has yet granted rights — carries none and sits outside this line entirely; it is listed, not counted. The starting point is the historical completion rate of its lifecycle stage — of projects that reached construction, 97% delivered; financed but not yet building, 92%; consented without financing, 75%; early development, 61%; on hold, 15%. That base rate is then adjusted by what the project has actually secured (offtake, grid, consents, investment decision) and decays if a project sits quiet past its stage's normal dwell time.

When it delivers. Each project also carries a completion-date distribution — a shape, not a single year, right-skewed because offshore wind slips late far more often than it runs early. The peak sits on a rule-based expected date chained from the project's latest achieved milestone; the width of the late tail is fitted to how far past their announced dates real projects actually landed: builders slip tight (68% on time, n=158), financed projects tighter still (72%, n=101), consented-only projects carry the fat tail — 25% land three or more years late (n=133). A stated date faster than any comparable project has ever achieved is floored to the achievable window and flagged, never taken at face value.

The line is the sum, across every live project, of capacity × completion weight × the probability it delivers in each year. For projects already under construction, a share of expected capacity is counted at first power — turbines start generating before a wind farm is fully commissioned — so a market's chart can show capacity arriving a year before a project's stated completion date. Delivered history is metered fact; the line inherits every assumption above and nothing else.

Honest limits. The weights are calibrated on a fleet whose failures have so far been overwhelmingly pre-financing — completion rates after FID rest on a record with few failures, so they are ceilings, not guarantees. The slip fitted on consented projects is the loosest (the "three or more years late" bucket spans many years). Policy shocks arrive faster than base rates move — the weights see a stop-work order only as its lifecycle consequences accrue. And the line redistributes as the database learns: it is re-derived on every data refresh, not frozen.

Full per-project workings — each project's weight, band, expected date and distribution — are on its project page. Calibration v2.0-phase0 · generated 2026-09-09; every figure above is read from the generated calibration file, never typed.

Auction outlook

forecast · 1 round tracked
Seabed leaseOfftake awardIntegrated tenderscheduled — bar spans the expected windowplanned (indicative)postponed / suspendedno date yet (off-axis)
202720282029todayPLANNED — INDICATIVESouth Korea 2026 H2 Offshore Wind Auction · 2026-H2 · planned · 2.35 GW offeredSouth Korea 2026 H2 Offshore Wind Auction · 2.35 GW
Offtake award South Korea 2026 H2 Offshore Wind Auction planned
What the date rests on — MCEE's ten-year roadmap (2026-06-30) schedules 1.7-3.0 GW for 2026 H2 — fixed 1.3-2.0 GW, floating 0.4-1.0 GW. No 공고 date published as of 2026-08-26; the ministry began collecting military-operability consultation requests for H2 bidders from April 2026.

LAST round under RPS — the scheme sunsets 2027-01-01 and the post-RPS auction design is due to be specified in 2026 H2. Known intending bidders: CIP has said it will bring Haesong 1 (kr-haesong-1-offshore-wind-farm-cip) and Haewoori 3 back, both of which sat out or lost in H1; Jangbogo (kr-wando-jangbogo) was rejected in the H1 public-led pot and is a natural re-bidder. Watch the Hanbit precedent — a Vensys/Goldwind-licensed turbine cleared for the first time, and trade press expects more bidders to follow that route in H2.

Origination ladder

settled rounds → projects
Seabed leaseOfftake awardIntegrated tenderbirth award (colour = round type)no auction award on record (the chapter names how the site originated)offtake / tender winterminated award / cancelledFIDCOD achievedCOD expected (dashed = still to run)on hold
2015201520202020202520252030203020352035OPEN DOOR — DEVELOPER-INITIATED SITESTamra Offshore Wind Farm · 30 MW · Operational · COD 2017 · No auction award on record · open doorTamra Offshore Wind Farm201730 MWHanlim Offshore Wind Farm · 100 MW · Operational · COD 2025 · No auction award on record · open doorHanlim Offshore Wind Farm2025100 MWJeonnam 1 Offshore Wind Farm · 96 MW · Operational · COD 2025 · No auction award on record · open doorJeonnam 1 Offshore Wind Farm202596 MWEast Blue Power (Mainstream / Ocean Winds Phase 1) · 375 MW · Early Development · outlook: Prospective · COD expected 2030 · No auction award on record · open doorEast Blue Power (Mainstream …2030e375 MWGray Whale Phase 1 (BadaEnergy) · 510 MW · Early Development · outlook: Prospective · COD expected 2030 · No auction award on record · open doorGray Whale Phase 1 (BadaEner…2030e510 MWGray Whale Phase 2 (BadaEnergy) · 495 MW · Early Development · outlook: Prospective · COD expected 2030 · No auction award on record · open doorGray Whale Phase 2 (BadaEner…2030e495 MWHanbando Offshore Wind Farm (Ocean Winds) · 1.13 GW · Early Development · outlook: Prospective · COD expected 2031 · No auction award on record · open doorHanbando Offshore Wind Farm …2031e1.13 GWKF Wind (Mainstream / Ocean Winds) · 750 MW · Early Development · outlook: Prospective · COD expected 2031 · No auction award on record · open doorKF Wind (Mainstream / Ocean …2031e750 MWAbalone Offshore Wind Farm (Deep Wind / KHNP) · 1.5 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · open doorAbalone Offshore Wind Farm (…2032e1.5 GWAdmiral Lee Offshore Wind Farm (Deep Wind / KHNP / bp) · 1.5 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · open doorAdmiral Lee Offshore Wind Fa…2032e1.5 GWIncheon Offshore Wind Farm (Ørsted/KOEN) · 1.4 GW · Early Development · outlook: Prospective · No auction award on record · open doorIncheon Offshore Wind Farm (…1.4 GWMunmubaram · 750 MW · Proposed · No auction award on record · open doorMunmubaram750 MWDEMONSTRATIONS & PILOTSSouthwest Offshore Demonstration Wind Farm · 60 MW · Operational · COD 2019 · No auction award on record · demonstrationSouthwest Offshore Demonstra…201960 MWUNCLASSIFIED — ORIGINATION NOT YET ESTABLISHEDDonghae 1 Floating Wind Farm · 200 MW · Early Development · outlook: Prospective · COD expected 2028 · No auction award on record · origination unclassifiedDonghae 1 Floating Wind Farm2028e200 MWGray Whale Phase 3 (BadaEnergy) · 495 MW · Early Development · outlook: Prospective · COD expected 2029 · No auction award on record · origination unclassifiedGray Whale Phase 3 (BadaEner…2029e495 MWWando Jangbogo Offshore Wind Farm · 400 MW · Early Development · outlook: Prospective · COD expected 2029 · No auction award on record · origination unclassifiedWando Jangbogo Offshore Wind…2029e400 MWHaesong 1 Offshore Wind Farm (CIP) · 504 MW · Early Development · outlook: Prospective · COD expected 2030 · No auction award on record · origination unclassifiedHaesong 1 Offshore Wind Farm…2030e504 MWJeonnam 2 Offshore Wind Farm (CIP/SK) · 399 MW · Early Development · outlook: Prospective · COD expected 2031 · No auction award on record · origination unclassifiedJeonnam 2 Offshore Wind Farm…2031e399 MWJeonnam 3 Offshore Wind Farm (CIP/SK) · 399 MW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedJeonnam 3 Offshore Wind Farm…2031e399 MWWestern Wind Offshore Wind Farm · 1.5 GW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedWestern Wind Offshore Wind F…2031e1.5 GWRising Sun Offshore Wind Farm (Deep Wind) · 1.5 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedRising Sun Offshore Wind Far…2033e1.5 GWSOUTH KOREA 2023 WIND FIXED-PRICE AUCTION — OFFSHOR… · 2023Shinan-Ui Offshore Wind Farm · 390 MW · Under Construction · outlook: Delivering · COD expected 2029 · Rounds: kr-rps-wind-2023Shinan-Ui Offshore Wind Farm2029e390 MWWando Geumil Offshore Wind Farm · 600 MW · Advanced Development · outlook: Expected · COD expected 2029 · Rounds: kr-rps-wind-2023Wando Geumil Offshore Wind F…2029e600 MWNakwol · 365 MW · Under Construction · outlook: Delivering · Rounds: kr-rps-wind-2023Nakwol365 MWSOUTH KOREA 2024 WIND FIXED-PRICE AUCTION — FIXED-B… · 2024Anma Offshore Wind Farm · 532 MW · On Hold · outlook: Fragile · COD expected 2029 · Rounds: kr-rps-wind-2024Anma Offshore Wind Farm532 MWYeonggwang Yawol Offshore Wind Farm · 104 MW · Early Development · outlook: Prospective · COD expected 2029 · Rounds: kr-rps-wind-2024Yeonggwang Yawol Offshore Wi…2029e104 MWBandibuli Floating Wind Farm (Equinor Firefly) · 750 MW · Early Development · outlook: Prospective · COD expected 2030 · Rounds: kr-rps-wind-2024Bandibuli Floating Wind Farm…2030e750 MWTaean Wind Power · 504 MW · Advanced Development · outlook: Expected · COD expected 2030 · Rounds: kr-rps-wind-2024Taean Wind Power2030e504 MWSOUTH KOREA 2025 H1 OFFSHORE WIND AUCTION (PUBLIC-L… · 2025Aphae Offshore Wind Farm · 80 MW · Advanced Development · outlook: Expected · COD expected 2028 · Rounds: kr-rps-wind-2025h1-offshoreAphae Offshore Wind Farm2028e80 MWDadaepo Offshore Wind Farm · 99 MW · Early Development · outlook: Prospective · COD expected 2028 · Rounds: kr-rps-wind-2025h1-offshoreDadaepo Offshore Wind Farm2028e99 MWHandong-Pyeongdae Offshore Wind Farm · 100 MW · Advanced Development · outlook: Expected · COD expected 2028 · Rounds: kr-rps-wind-2025h1-offshoreHandong-Pyeongdae Offshore W…2028e100 MWSouthwest Offshore Wind Phase 2 · 400 MW · Advanced Development · outlook: Expected · COD expected 2028 · Rounds: kr-rps-wind-2025h1-offshoreSouthwest Offshore Wind Phas…2028e400 MWSOUTH KOREA 2026 H1 OFFSHORE WIND AUCTION (FIXED-BO… · 2026Haewoori Floating Wind Farm (CIP) · 1.5 GW · Early Development · outlook: Prospective · COD expected 2028 · Rounds: kr-offshore-2026h1Haewoori Floating Wind Farm …2028e1.5 GWGeumodo Offshore Wind Farm · 160 MW · Advanced Development · outlook: Expected · COD expected 2030 · Rounds: kr-offshore-2026h1Geumodo Offshore Wind Farm2030e160 MWHaesong 3 Offshore Wind Farm (CIP) · 504 MW · Advanced Development · outlook: Expected · COD expected 2030 · Rounds: kr-offshore-2026h1Haesong 3 Offshore Wind Farm…2030e504 MWHanbit Offshore Wind Farm · 340 MW · Advanced Development · outlook: Expected · COD expected 2030 · Rounds: kr-offshore-2026h1Hanbit Offshore Wind Farm2030e340 MWGulupdo Phase 1 Offshore Wind Farm · 250 MW · Advanced Development · outlook: Expected · Rounds: kr-offshore-2026h1Gulupdo Phase 1 Offshore Win…250 MW