Market profile

Brazil

nascent * buildout: pending risk: pending outlook: pending

* maturity derived from capacity data; full assessment pending.

0
GW operational
0
GW in construction
0
GW pipeline
73
projects
Early Development · 0 GW (1)Proposed · 137.5 GW (56)On Hold · 35.1 GW (15)
Progress to target
No published national target.
Next auction round
Brazil first offshore wind auction (Lei 15.097/2025 planned-offer model)
2027 · lease auction · planned
full auction outlook ↓

Assessment

Assessment pending

This market has a derived snapshot above but no in-depth assessment yet. Authored coverage rolls out market by market; the data here is live in the meantime.

State of the market

as of 2026-09-09
0%
of GW sited through contested rounds
delivered (COD actuals)unweighted dated pipeline (building / contracted / early)Expected Buildout (confidence-weighted)national target (range)superseded targettoday
01234GW202520302035todayEXPECTED BUILDOUT → 3.3 GW+ building → 0.0 GW+ contracted → 0.0+ early → 0.00.0 GW operational

Teal line = the Hafrok Expected Buildout (confidence-weighted): 35 GW of live pipeline weights to 3.3 GW expected to complete, timed by each project's COD distribution (mass beyond 2037 not drawn). Bands are the unweighted dated pipeline — the Expected Buildout also models on-hold and undated projects, so it can sit above them. 0.0 GW of pipeline has no dated COD and is not in the bands.

How this line is made

The Expected Buildout line answers one question: of the pipeline announced today, how much actually gets built, and when? It is not a scenario and not a target tracker — it is the database's live pipeline, passed through two filters measured from the industry's own delivery record.

Whether a project completes. Every project in development carries a completion weight, banded Delivering / Expected / Prospective / Fragile. A proposal — a site where no authority has yet granted rights — carries none and sits outside this line entirely; it is listed, not counted. The starting point is the historical completion rate of its lifecycle stage — of projects that reached construction, 97% delivered; financed but not yet building, 92%; consented without financing, 75%; early development, 61%; on hold, 15%. That base rate is then adjusted by what the project has actually secured (offtake, grid, consents, investment decision) and decays if a project sits quiet past its stage's normal dwell time.

When it delivers. Each project also carries a completion-date distribution — a shape, not a single year, right-skewed because offshore wind slips late far more often than it runs early. The peak sits on a rule-based expected date chained from the project's latest achieved milestone; the width of the late tail is fitted to how far past their announced dates real projects actually landed: builders slip tight (68% on time, n=158), financed projects tighter still (72%, n=101), consented-only projects carry the fat tail — 25% land three or more years late (n=133). A stated date faster than any comparable project has ever achieved is floored to the achievable window and flagged, never taken at face value.

The line is the sum, across every live project, of capacity × completion weight × the probability it delivers in each year. For projects already under construction, a share of expected capacity is counted at first power — turbines start generating before a wind farm is fully commissioned — so a market's chart can show capacity arriving a year before a project's stated completion date. Delivered history is metered fact; the line inherits every assumption above and nothing else.

Honest limits. The weights are calibrated on a fleet whose failures have so far been overwhelmingly pre-financing — completion rates after FID rest on a record with few failures, so they are ceilings, not guarantees. The slip fitted on consented projects is the loosest (the "three or more years late" bucket spans many years). Policy shocks arrive faster than base rates move — the weights see a stop-work order only as its lifecycle consequences accrue. And the line redistributes as the database learns: it is re-derived on every data refresh, not frozen.

Full per-project workings — each project's weight, band, expected date and distribution — are on its project page. Calibration v2.0-phase0 · generated 2026-09-09; every figure above is read from the generated calibration file, never typed.

Auction outlook

forecast · 1 round tracked
Seabed leaseOfftake awardIntegrated tenderscheduled — bar spans the expected windowplanned (indicative)postponed / suspendedno date yet (off-axis)
202720282029todayPLANNED — INDICATIVEBrazil first offshore wind auction (Lei 15.097/2025 planned-offer model) · 2027 · plannedBrazil first offshore wind auction (Lei 15.…
Seabed lease Brazil first offshore wind auction (Lei 15.097/2025 planned-offer model) planned
What the date rests on — enabling law sanctioned Jan 2025; implementing decree pending (expected H1 2026); first leilão not scheduled

Brazil has NO binding national OSW target — its pipeline is licensing-led (~50+ projects in IBAMA environmental licensing, none built). Lei nº 15.097/2025 (sanctioned 10 Jan 2025, confirmed on Planalto) governs offshore generation on federal maritime assets via cessão de uso of "prismas energéticos", under a Permanent Offer (self-nominated, no tender) and a Planned Offer (competitive tender) model. The implementing decree was expected H1 2026, pushing any first auction toward ~2027, with postponement risk (2026 is a Brazilian election year). Recorded as planned, not scheduled.

Origination ladder

settled rounds → projects
Seabed leaseOfftake awardIntegrated tenderbirth award (colour = round type)no auction award on record (the chapter names how the site originated)offtake / tender winterminated award / cancelledFIDCOD achievedCOD expected (dashed = still to run)on hold
202520252030203020352035UNCLASSIFIED — ORIGINATION NOT YET ESTABLISHEDMaral · 2.01 GW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedMaral2031e2.01 GWTramandaí Offshore · 700 MW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedTramandaí Offshore2031e700 MWVento Tupi · 999 MW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedVento Tupi2031e999 MWVentos do Atlântico · 5 GW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedVentos do Atlântico2031e5 GWVentos do Sul · 6.51 GW · Proposed · developer's date 2031 · not forecast · No auction award on record · origination unclassifiedVentos do Sul2031e6.51 GWAlísios Potiguares · 1.84 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedAlísios Potiguares2032e1.84 GWAracatu I · 1.92 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedAracatu I2032e1.92 GWAracatu II · 1.92 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedAracatu II2032e1.92 GWAtoba · 2.49 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedAtoba2032e2.49 GWBI Energia Offshore RN · 624 MW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedBI Energia Offshore RN2032e624 MWCamocim Offshore Wind · 1.2 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedCamocim Offshore Wind2032e1.2 GWColibri · 2.01 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedColibri2032e2.01 GWDragão do Mar · 1.22 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedDragão do Mar2032e1.22 GWIbituassu · 2.01 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedIbituassu2032e2.01 GWIbitucatu · 2.01 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedIbitucatu2032e2.01 GWJangadas Offshore · 3 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedJangadas Offshore2032e3 GWMangara · 2.01 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedMangara2032e2.01 GWMaravilha Wind Complex · 3 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedMaravilha Wind Complex2032e3 GWPalmas do Mar · 1.4 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedPalmas do Mar2032e1.4 GWVentos do Açu Offshore Wind Complex · 2.16 GW · On Hold · outlook: Fragile · COD expected 2032 · No auction award on record · origination unclassifiedVentos do Açu Offshore Wind …2.16 GWÁguas Claras Offshore · 3 GW · Proposed · developer's date 2032 · not forecast · No auction award on record · origination unclassifiedÁguas Claras Offshore2032e3 GWAraioses · 2.81 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedAraioses2033e2.81 GWCassino Offshore · 1.92 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedCassino Offshore1.92 GWComplexo Offshore do Piauí · 2.02 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedComplexo Offshore do Piauí2033e2.02 GWComplexo Offshore do Sul I · 1.66 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedComplexo Offshore do Sul I2033e1.66 GWComplexo Offshore do Sul II · 1.6 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedComplexo Offshore do Sul II2033e1.6 GWComplexo Offshore do Sul III · 3.02 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedComplexo Offshore do Sul III2033e3.02 GWCosta Branca I · 1.46 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedCosta Branca I2033e1.46 GWCosta Branca II · 2.11 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedCosta Branca II2033e2.11 GWCosta Nordeste Offshore · 3.84 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedCosta Nordeste Offshore3.84 GWEspírito Santo I · 1.98 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedEspírito Santo I2033e1.98 GWFortaleza · 2.16 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedFortaleza2033e2.16 GWGinga · 1.06 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedGinga2033e1.06 GWGuarita Offshore · 1.68 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedGuarita Offshore1.68 GWMostardas · 3.51 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedMostardas2033e3.51 GWPiedade · 2.27 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedPiedade2033e2.27 GWPrazeres · 2.39 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedPrazeres2033e2.39 GWRio Grande Offshore · 1.2 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedRio Grande Offshore1.2 GWShell Açu Offshore Wind · 3 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell Açu Offshore Wind2033e3 GWShell Galinhos Offshore Wind · 3 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell Galinhos Offshore Wind2033e3 GWShell Offshore Wind Piauí · 2.52 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell Offshore Wind Piauí2033e2.52 GWShell Pecém Offshore Wind · 3 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell Pecém Offshore Wind2033e3 GWShell Ubu Offshore Wind · 2.52 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell Ubu Offshore Wind2033e2.52 GWShell White Shark Offshore Wind · 3 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedShell White Shark Offshore W…2033e3 GWSopros do Ceará · 3 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedSopros do Ceará3 GWSopros do RJ · 3 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedSopros do RJ3 GWSopros do RS · 3 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedSopros do RS3 GWVentos Offshore do Pecém · 2.02 GW · Proposed · developer's date 2033 · not forecast · No auction award on record · origination unclassifiedVentos Offshore do Pecém2033e2.02 GWVitoria Offshore · 1.2 GW · On Hold · outlook: Fragile · COD expected 2033 · No auction award on record · origination unclassifiedVitoria Offshore1.2 GWAlpha (Morro Branco) · 6 GW · Proposed · No auction award on record · origination unclassifiedAlpha (Morro Branco)6 GWAraras · 3 GW · Proposed · No auction award on record · origination unclassifiedAraras3 GWAsa Branca I · 1.08 GW · Proposed · No auction award on record · origination unclassifiedAsa Branca I1.08 GWAsa Branca II · 1.08 GW · Proposed · No auction award on record · origination unclassifiedAsa Branca II1.08 GWAsa Branca III · 4.32 GW · Proposed · No auction award on record · origination unclassifiedAsa Branca III4.32 GWAsa Branca IV · 4.32 GW · Proposed · No auction award on record · origination unclassifiedAsa Branca IV4.32 GWBeta · 3 GW · Proposed · No auction award on record · origination unclassifiedBeta3 GWCattleya · 1.18 GW · Proposed · No auction award on record · origination unclassifiedCattleya1.18 GWCaucaia Offshore Wind · 576 MW · Cancelled · No auction award on record · origination unclassifiedCaucaia Offshore Wind576 MWH2GPCEA · 3 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedH2GPCEA3 GWMar de Minas I · 1.5 GW · Proposed · No auction award on record · origination unclassifiedMar de Minas I1.5 GWMar de Minas II · 3 GW · Proposed · No auction award on record · origination unclassifiedMar de Minas II3 GWMares do Norte · 1.52 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedMares do Norte1.52 GWPlanta Piloto Petrobras · 18 MW · Early Development · outlook: Prospective · No auction award on record · origination unclassifiedPlanta Piloto Petrobras18 MWSopros do Piauí 1 · 3.13 GW · Proposed · No auction award on record · origination unclassifiedSopros do Piauí 13.13 GWSopros do Rio Grande do Norte · 3 GW · Proposed · No auction award on record · origination unclassifiedSopros do Rio Grande do Norte3 GWTatajuba · 3 GW · Proposed · No auction award on record · origination unclassifiedTatajuba3 GWVentos Potiguar · 2.48 GW · Proposed · No auction award on record · origination unclassifiedVentos Potiguar2.48 GWVentos de São Francisco · 2.96 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedVentos de São Francisco2.96 GWVentos do Atalaia · 2.96 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedVentos do Atalaia2.96 GWVentos do Caiçara · 1.97 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedVentos do Caiçara1.97 GWVentos do Delta · 2.64 GW · Proposed · No auction award on record · origination unclassifiedVentos do Delta2.64 GWVentos dos Bandeirantes · 2.75 GW · Proposed · No auction award on record · origination unclassifiedVentos dos Bandeirantes2.75 GWÁgua Marinha · 1.7 GW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedÁgua Marinha1.7 GW