Bandibuli Floating Wind Farm (Equinor Firefly)

Also known as Firefly. Equinor leads; Jeonnam province context but Ulsan-area project. Co-located with Ulsan floating wind cluster.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2035
expected year of commercial operation
The developer says 2030; Hafrok expects 2035 — 5 years later.
Chance of delivery
≈59% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits below that: a market with a thinner delivery record, its size and technical complexity. A secured offtake contract helps only slightly.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2034: 14.1% (conditional on completion) 2035: 28.0% (conditional on completion) 2036: 22.7% (conditional on completion) 2037: 14.6% (conditional on completion) 2038: 8.7% (conditional on completion) 2039: 5.1% (conditional on completion) 2040: 3.1% (conditional on completion) 2041: 1.8% (conditional on completion) 2042: 1.1% (conditional on completion) 2043: 0.7% (conditional on completion)2026now2028203020322034203528%EXPECTED2036203820402042 Developer-announced COD: 2030 ANNOUNCED 2030
COD probability by year, conditional on completion
YearProbability
203414.1%
2035 (expected)28.0%
203622.7%
203714.6%
20388.7%
20395.1%
20403.1%
20411.8%
20421.1%
20430.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (floating, in developing offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2035 is not credible.
3
Result
Expected commercial operation 2035, likely range 2035–2041 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈59%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33’34’35Developer-announced COD: 2030 announced COD 2030Commercial operation 2035 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake contract duration and price levels · money of the day

750 MW contracted — utility PPA
Utility PPA · South Korea 2024 Wind Fixed-Price Auction — fixed-bottom + floating offshore
Priceprice undisclosed ·Capacity750 MWAwardedDec 2024
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2030

Sources & verification

0/12 fields verified · rests on 9 sources · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[4]
Equinor Korea2024-10◆ Five Ulsan Floating Offshore Wind Power …
“Five developers have signed a contract with Korea Electric Power Corporation (hereinafter referred to as KEPCO) for the use of the world's largest 6GW floating offshore wind power transmission electri…”
supportsStatusConnection point
Auction results1
[11]
Shin and Kim2026-06-22◆ kr-rps-wind-2024-kr-rps-terms
Korea RPS fixed-price offshore: completion-period bands 60/72/78 months; REC-price cut / cancellation on miss
supportsUtility PPA · South Korea 2024 Wind Fixed-Price Auction — fixed-bottom + floating offshore
Trade press6
[2]
Offshore Wind (Navingo)2024-12◆ South Korea Awards Nearly 1.9 GW of Offs…
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityMechanismDetail
[5]
Tethys (PNNL)2026-06◆ Firefly/Bandibuli Floating Wind Farm | T…
“EBL Status: Approved in December 2021. EIA Status: Approved July 2024. The Ministry of Environment completed its review following a two-year evaluation process. Permitting/Consent Status: Planning.”
supportsConsentSite rights
[7]
reNEWS2025-09
Press report — cited, not quoted; read it at the source link.
supportsoperator
[8]
GEM2026
supportsTotal capacityFoundationCoordinates
[9]
GEBCO Compilation Group2020
supportsWater depth
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsCommercial operationTotal capacityFoundationWater depthCoordinates