Jeonnam 2 Offshore Wind Farm (CIP/SK)
Located off Shinan County, Jeonnam. Adjacent to Jeonnam 1.
Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Location
Yellow Sea
Technology
Capacity
399 MW ◇
Turbines
—
Foundation
—
Site & conditions
Site rights
Application filed ○
Water depth
6–25 m ≈
Wind speed
7.9 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Not taken
COD · announced
2031 ◇
COD · Hafrok
2034 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2034
expected year of commercial operation
The developer says 2031; Hafrok expects 2034 — 3 years later.
Chance of delivery
≈60%
estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a market with a thinner delivery record and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2033 | 14.1% |
| 2034 (expected) | 28.0% |
| 2035 | 22.7% |
| 2036 | 14.6% |
| 2037 | 8.7% |
| 2038 | 5.1% |
| 2039 | 3.1% |
| 2040 | 1.8% |
| 2041 | 1.1% |
| 2042 | 0.7% |
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (
2026), adds the time similar projects (in developing offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before
2034 is not credible.3
Still needs an offtake award: KR-OFFSHORE-2026H2
The project has no offtake contract yet. The next visible auction is around
2026 Q4; winners typically reach final investment decision about 2 years after an award (2028 Q4), then build time on top gives 2031 Q4. The milestone timing is already later than that, so it stands.4
Result
Expected commercial operation
2034, likely range 2034–2039 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈60%, which rates it
Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
JV formation · 2020-Q1
SK E&S · Copenhagen Infrastructure Partners stake not disclosed
- Stake
- not disclosed
- Consideration
- not disclosed
- Announced
- 2020-Q1
- Closed
- 2020-Q4
- Project stage
- early development
Jeonnam Offshore Wind Power Co. was established in 2020 as a 51/49 joint venture between SK E&S (majority, 51%) and Copenhagen Infrastructure Partners (CIP, 49%), acting through its fund Copenhagen Infrastructure III ("CI III"). CIP's development and technical partner is Copenhagen Offshore Partners (COP). The JV develops a portfolio of offshore wind projects in Shinan County, Jeonnam Province (South Jeolla), including Jeonnam 1 (99 MW, now operational), Jeonnam 2 (~400 MW), and Jeonnam 3 (~400 MW). Haesong 1 and Haesong 3 (each ~500 MW) are also part of the broader CIP/SK E&S Korea platform, likely under the same or a sister entity. Jeonnam 1 reached financial close on 11 October 2023 (KRW 1.07 trillion / ~EUR 715m project financing). Jeonnam 1 achieved first power in November 2024 and commenced commercial operations in May 2025. Exact announcement date within 2020 not found in public sources. This record is anchored to Jeonnam 2 as representative; companion record for Jeonnam 3 not created to avoid duplication of the same JV formation event.
Evidence
- globenewswire.com — SK E&S and Copenhagen Infrastructure Partners reach ↗ ◆ held
- offshoreWIND.biz — CIP, SK E&S Achieve Financial Close on South Korean Offshore Wind Project ↗ 2020-Q1 ◆ held
- cop.dk — Copenhagen Offshore Partners | Jeonnam 1 Offshore Wind Project in Korea Reaches Financial Close and Begins Onshore and Offshore Construction ↗ 2020-Q1 ◆ held
- offshorewind.biz — Largest Privately Led Offshore Wind Farm in South Korea Enters Commercial Operation ↗ ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake route to market — open
No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
South Korea 2026 H2 Offshore Wind Auction ◇
MCEE's ten-year roadmap (2026-06-30) schedules 1.7-3.0 GW for 2026 H2 — fixed 1.3-2.0 GW, floating 0.4-1.0 GW. No 공고 date published as of 2026-08-26; the ministry began collecting military-operability consultation requests for H2 bidders from April 2026.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2031
Sources & verification
0/9 fields verified · rests on 8 sources · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Auction pipeline1
[9]
기후에너지환경부 (MCEE), via 대한민국 정책브리핑 (korea.kr)2026-06-30◆ kr-mcee-roadmap-2026
Roadmap table, 2026 H2 column: 경쟁입찰 물량 1.7~3.0 GW (고정식 1.3~2.0, 부유식 0.4~1.0). "RPS 제도 일몰('27.1.1.)에 따라 '27년 이후 입찰에 대한 세부 운영 방식 및 선정 프로세스 구체화 필요 ('26년 하반기 중)."
supportsSouth Korea 2026 H2 Offshore Wind Auction
Trade press6
[2]
SK Innovation News (SK Innovation E&S)2025-05
“SK Innovation E&S, in collaboration with CIP, plans to construct Jeonnam Offshore Wind Farm 2 (399MW) and Jeonnam Offshore Wind Farm 3 (399MW), with completion targeted for 2031.”
supportsCommercial operationTotal capacity
[4]
[5]
[6]
4C Offshore2026
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[7]
[8]
Unverified import1
[1]
unknown◆ Copenhagen Offshore Partners | Jeonnam 1…
supportsConsentSite rightsTotal capacityWater depthCoordinates