Market profile

India

nascent * buildout: pending risk: pending outlook: pending

* maturity derived from capacity data; full assessment pending.

0
GW operational
0
GW in construction
0
GW pipeline
5
projects
Proposed · 1.5 GW (2)On Hold · 0.2 GW (1)
Progress to target
0%
0 GW operational of 30 GW by 2030
National Offshore Wind Energy Policy — 30 GW by 2030
Next auction round
India first VGF offshore wind tender (Gujarat / Tamil Nadu)
· tender (VGF-backed seabed allocation) · planned
1.0 GW offered
full auction outlook ↓

Assessment

Assessment pending

This market has a derived snapshot above but no in-depth assessment yet. Authored coverage rolls out market by market; the data here is live in the meantime.

State of the market

as of 2026-09-09
0%
of GW sited through contested rounds
delivered (COD actuals)unweighted dated pipeline (building / contracted / early)Expected Buildout (confidence-weighted)national target (range)superseded targettoday
0102030GW202520302035todayEXPECTED BUILDOUT → 0.0 GW+ building → 0.0 GW+ contracted → 0.0+ early → 0.00.0 GW operational30 GW target · 2030

Teal line = the Hafrok Expected Buildout (confidence-weighted): 0.2 GW of live pipeline weights to 0.0 GW expected to complete, timed by each project's COD distribution (mass beyond 2037 not drawn). Bands are the unweighted dated pipeline — the Expected Buildout also models on-hold and undated projects, so it can sit above them.

How this line is made

The Expected Buildout line answers one question: of the pipeline announced today, how much actually gets built, and when? It is not a scenario and not a target tracker — it is the database's live pipeline, passed through two filters measured from the industry's own delivery record.

Whether a project completes. Every project in development carries a completion weight, banded Delivering / Expected / Prospective / Fragile. A proposal — a site where no authority has yet granted rights — carries none and sits outside this line entirely; it is listed, not counted. The starting point is the historical completion rate of its lifecycle stage — of projects that reached construction, 97% delivered; financed but not yet building, 92%; consented without financing, 75%; early development, 61%; on hold, 15%. That base rate is then adjusted by what the project has actually secured (offtake, grid, consents, investment decision) and decays if a project sits quiet past its stage's normal dwell time.

When it delivers. Each project also carries a completion-date distribution — a shape, not a single year, right-skewed because offshore wind slips late far more often than it runs early. The peak sits on a rule-based expected date chained from the project's latest achieved milestone; the width of the late tail is fitted to how far past their announced dates real projects actually landed: builders slip tight (68% on time, n=158), financed projects tighter still (72%, n=101), consented-only projects carry the fat tail — 25% land three or more years late (n=133). A stated date faster than any comparable project has ever achieved is floored to the achievable window and flagged, never taken at face value.

The line is the sum, across every live project, of capacity × completion weight × the probability it delivers in each year. For projects already under construction, a share of expected capacity is counted at first power — turbines start generating before a wind farm is fully commissioned — so a market's chart can show capacity arriving a year before a project's stated completion date. Delivered history is metered fact; the line inherits every assumption above and nothing else.

Honest limits. The weights are calibrated on a fleet whose failures have so far been overwhelmingly pre-financing — completion rates after FID rest on a record with few failures, so they are ceilings, not guarantees. The slip fitted on consented projects is the loosest (the "three or more years late" bucket spans many years). Policy shocks arrive faster than base rates move — the weights see a stop-work order only as its lifecycle consequences accrue. And the line redistributes as the database learns: it is re-derived on every data refresh, not frozen.

Full per-project workings — each project's weight, band, expected date and distribution — are on its project page. Calibration v2.0-phase0 · generated 2026-09-09; every figure above is read from the generated calibration file, never typed.

Auction outlook

forecast · 1 round tracked
Seabed leaseOfftake awardIntegrated tenderscheduled — bar spans the expected windowplanned (indicative)postponed / suspendedno date yet (off-axis)
202720282029today
NO DATE YETIndia first VGF offshore wind tender (Gujarat / Tam… · planned
Integrated tender India first VGF offshore wind tender (Gujarat / Tamil Nadu) planned
What the date rests on — VGF scheme notified Sep 2024; a 500 MW Gujarat site (NIWE-identified) tender announced Sep 2024; TN 500 MW site being finalised; a separate SECI 4 GW Tamil Nadu seabed-lease-rights tender floated Feb 2024.

India's first competitive offshore allocation. MNRE notified the INR 7,453 cr Viability Gap Funding scheme (Sep 2024) for 1,000 MW off Gujarat + Tamil Nadu (incl. INR 600 cr for two ports); SECI implements. Timelines soft and the projects are not yet awarded. National policy aim is to tender 30 GW of offshore by 2030 (see the India national target). No OSW operational in India yet.

Origination ladder

settled rounds → projects
Seabed leaseOfftake awardIntegrated tenderbirth award (colour = round type)no auction award on record (the chapter names how the site originated)offtake / tender winterminated award / cancelledFIDCOD achievedCOD expected (dashed = still to run)on hold
202520252030203020352035UNCLASSIFIED — ORIGINATION NOT YET ESTABLISHEDFOWIND Pipavav demonstration · 1 GW · Proposed · No auction award on record · origination unclassifiedFOWIND Pipavav demonstration1 GWFOWPI (First Offshore Wind Project of India) · 200 MW · On Hold · outlook: Fragile · No auction award on record · origination unclassifiedFOWPI (First Offshore Wind P…200 MWMNRE VGF Scheme - Tamil Nadu 500 MW · 500 MW · Proposed · No auction award on record · origination unclassifiedMNRE VGF Scheme - Tamil Nadu…500 MWSECI Gujarat Offshore Wind Tranche I · 500 MW · Cancelled · No auction award on record · origination unclassifiedSECI Gujarat Offshore Wind T…500 MWSECI Tamil Nadu Offshore Wind Tranche I · 4 GW · Cancelled · No auction award on record · origination unclassifiedSECI Tamil Nadu Offshore Win…4 GW