Haesong 3 Offshore Wind Farm (CIP)

Co-located with Haesong 1 off Shinan, Jeonnam.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2030
expected year of commercial operation
Chance of delivery
≈76% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a market with a thinner delivery record, its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2029: 3.9% (conditional on completion) 2030: 50.2% (conditional on completion) 2031: 29.5% (conditional on completion) 2032: 10.6% (conditional on completion) 2033: 3.8% (conditional on completion) 2034: 1.4% (conditional on completion) 2035: 0.6% (conditional on completion)2026now202720282029203050%20312032203320342035 Developer-announced COD: 2030 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2030
COD probability by year, conditional on completion
YearProbability
20293.9%
2030 (expected)50.2%
203129.5%
203210.6%
20333.8%
20341.4%
20350.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
Result
Expected commercial operation 2030, likely range 2029–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈76%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30Developer-announced COD: 2030 announced COD 2030Commercial operation 2030 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake contract duration and price levels · money of the day

504 MW contracted — utility PPA
Utility PPA · South Korea 2026 H1 Offshore Wind Auction (fixed-bottom general + public-led + floating)
Priceprice undisclosed ·Capacity504 MWAwardedJun 2026
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2030

Sources & verification

2/12 fields verified · rests on 10 sources · ◆ 5 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[10]
기후에너지환경부 (MCEE)2026-06-30◆ '26년 상반기 해상풍력 입찰 결과 5개 사업 1,786MW 선정
“「2026년 상반기 해상풍력 고정가격계약 경쟁입찰 결과, 총 3,656MW, 9개 사업이 응찰해 5개 사업, 1,786MW가 최종 선정되었다. 기후에너지환경부(장관 김성환)는 6월 30일 한국에너지공단이 … 결과를 확정하고, 입찰 사업자에게 개별 통보했다고 밝혔다.」 (2026 H1 offshore wind fixed-price competitive auc…”
supportsMechanismDetail
Auction results1
[13]
기후에너지환경부 (MCEE), via 대한민국 정책브리핑 (korea.kr)2026-06-30◆ kr-2026h1-mcee-result
"2026년 상반기 해상풍력 고정가격계약 경쟁입찰 결과, 총 3,656MW, 9개 사업이 응찰해 5개 사업, 1,786MW가 최종 선정되었다. 기후에너지환경부(장관 김성환)는 6월 30일 한국에너지공단이 2026년 상반기 해상풍력 고정가격계약 경쟁입찰 결과를 확정하고, 입찰 사업자에게 개별 통보했다고 밝혔다. … 고정식 해상풍력은 총 1,254MW가 선정되…
supportsUtility PPA · South Korea 2026 H1 Offshore Wind Auction (fixed-bottom general + public-led + floating)
Trade press7
[2]
offshoreWIND.biz2025-06-12◆ CIP Plans New 1 GW Offshore Wind Farm in…
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[3]
offshoreWIND.biz2025-07-08◆ Grid Interconnection Deal Sealed for 1 G…
Press report — cited, not quoted; read it at the source link.
supportsConsentSite rightsStatusConnection point
[5]
offshoreWIND.biz2025-06◆ CIP Plans New 1 GW Offshore Wind Farm in…
Press report — cited, not quoted; read it at the source link.
supportsoperator
[6]
GEM2026
supportsTotal capacity
[7]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[8]
GEBCO Compilation Group2020
supportsWater depth
[9]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsCommercial operationTotal capacityWater depthCoordinates