Market profile

Belgium

established * buildout: pending risk: pending outlook: pending

* maturity derived from capacity data; full assessment pending.

2.3
GW operational
0
GW in construction
3.5
GW pipeline
11
projects
Operational · 2.3 GW (8)Early Development · 3.5 GW (3)
Progress to target
38%
2.3 GW operational of 6 GW by 2030
Belgian offshore wind capacity
Next auction round
Princess Elisabeth Zone — Lot 1 (PE I, Noordhinder Noord)
2027 · tender · planned
0.7 GW offered
full auction outlook ↓

Assessment

Assessment pending

This market has a derived snapshot above but no in-depth assessment yet. Authored coverage rolls out market by market; the data here is live in the meantime.

State of the market

as of 2026-09-09
0%
of GW sited through contested rounds
11 yr
median award → power
delivered (COD actuals)unweighted dated pipeline (building / contracted / early)Expected Buildout (confidence-weighted)national target (range)superseded targettoday
0246GW201020152020202520302035today+ early → 5.8EXPECTED BUILDOUT → 3.8 GW+ building → 2.3 GW+ contracted → 2.32.3 GW operational5.4–5.8 GW target · 2030

Teal line = the Hafrok Expected Buildout (confidence-weighted): 3.5 GW of live pipeline weights to 1.7 GW expected to complete, timed by each project's COD distribution (mass beyond 2037 not drawn). Bands are the unweighted dated pipeline — the Expected Buildout also models on-hold and undated projects, so it can sit above them.

How this line is made

The Expected Buildout line answers one question: of the pipeline announced today, how much actually gets built, and when? It is not a scenario and not a target tracker — it is the database's live pipeline, passed through two filters measured from the industry's own delivery record.

Whether a project completes. Every project in development carries a completion weight, banded Delivering / Expected / Prospective / Fragile. A proposal — a site where no authority has yet granted rights — carries none and sits outside this line entirely; it is listed, not counted. The starting point is the historical completion rate of its lifecycle stage — of projects that reached construction, 97% delivered; financed but not yet building, 92%; consented without financing, 75%; early development, 61%; on hold, 15%. That base rate is then adjusted by what the project has actually secured (offtake, grid, consents, investment decision) and decays if a project sits quiet past its stage's normal dwell time.

When it delivers. Each project also carries a completion-date distribution — a shape, not a single year, right-skewed because offshore wind slips late far more often than it runs early. The peak sits on a rule-based expected date chained from the project's latest achieved milestone; the width of the late tail is fitted to how far past their announced dates real projects actually landed: builders slip tight (68% on time, n=158), financed projects tighter still (72%, n=101), consented-only projects carry the fat tail — 25% land three or more years late (n=133). A stated date faster than any comparable project has ever achieved is floored to the achievable window and flagged, never taken at face value.

The line is the sum, across every live project, of capacity × completion weight × the probability it delivers in each year. For projects already under construction, a share of expected capacity is counted at first power — turbines start generating before a wind farm is fully commissioned — so a market's chart can show capacity arriving a year before a project's stated completion date. Delivered history is metered fact; the line inherits every assumption above and nothing else.

Honest limits. The weights are calibrated on a fleet whose failures have so far been overwhelmingly pre-financing — completion rates after FID rest on a record with few failures, so they are ceilings, not guarantees. The slip fitted on consented projects is the loosest (the "three or more years late" bucket spans many years). Policy shocks arrive faster than base rates move — the weights see a stop-work order only as its lifecycle consequences accrue. And the line redistributes as the database learns: it is re-derived on every data refresh, not frozen.

Full per-project workings — each project's weight, band, expected date and distribution — are on its project page. Calibration v2.0-phase0 · generated 2026-09-09; every figure above is read from the generated calibration file, never typed.

Auction outlook

forecast · 3 rounds tracked
Seabed leaseOfftake awardIntegrated tenderscheduled — bar spans the expected windowplanned (indicative)postponed / suspendedno date yet (off-axis)
202720282029todayPLANNED — INDICATIVEPrincess Elisabeth Zone — Lot 1 (PE I, Noordhinder Noord) · 2027 · planned · 700 MW offeredPrincess Elisabeth Zone — Lot 1 (PE I, Noor… · 700 MW
NO DATE YETPrincess Elisabeth Zone — Lot 2 (PE II, Noordhinder… · plannedPrincess Elisabeth Zone — Lot 3 (PE III, Fairybank) · planned
Integrated tender Princess Elisabeth Zone — Lot 1 (PE I, Noordhinder Noord) planned
What the date rests on — indicative

20-year two-sided CfD. The first Princess Elisabeth tender was launched November 2024 and cancelled 2 July 2025; FPS Economy is preparing a relaunch of the tender under amended conditions.

Integrated tender Princess Elisabeth Zone — Lot 2 (PE II, Noordhinder Zuid) planned
What the date rests on — indicative

~1,225-1,400 MW. No tender date announced by FPS Economy.

Integrated tender Princess Elisabeth Zone — Lot 3 (PE III, Fairybank) planned
What the date rests on — indicative

~1,225-1,400 MW. No tender date announced.

Origination ladder

settled rounds → projects
Seabed leaseOfftake awardIntegrated tenderbirth award (colour = round type)no auction award on record (the chapter names how the site originated)offtake / tender winterminated award / cancelledFIDCOD achievedCOD expected (dashed = still to run)on hold
20052005201020102015201520202020202520252030203020352035BELGIAN OFFSHORE WIND ZONE — DOMAIN CONCESSIONS (TH… · 2004Belwind · 165 MW · Operational · COD 2010 · Rounds: be-domain-concessionsBelwind2010165 MWC-Power · 325 MW · Operational · COD 2013 · Rounds: be-domain-concessionsC-Power2013325 MWNorthwind · 216 MW · Operational · COD 2014 · Rounds: be-domain-concessionsNorthwind2014216 MWNobelwind · 165 MW · Operational · COD 2017 · Rounds: be-domain-concessionsNobelwind2017165 MWRentel · 309 MW · Operational · COD 2018 · Rounds: be-domain-concessionsRentel2018309 MWNorthwester 2 · 219 MW · Operational · COD 2020 · Rounds: be-domain-concessionsNorthwester 22020219 MWSeaMade · 487 MW · Operational · COD 2020 · Rounds: be-domain-concessionsSeaMade2020487 MWNorther · 370 MW · Operational · COD 2020 · Rounds: be-domain-concessionsNorther2020370 MW

3 sites designated for forecast rounds (3.5 GW) are not in the history ladder — pre-tender zones are the auction outlook's rounds-in-waiting: Princess Elisabeth Zone Lot 1 (Noordhinder Noord) · Princess Elisabeth Zone Lot 2 (Noordhinder Zuid) · Princess Elisabeth Zone Lot 3 (Fairybank).