Tamra Offshore Wind Farm
Nearshore project off Jeju Island. Public utility-led development.
Technology
Capacity
30 MW ◇
Turbines
10 × 3 MW ◇
Model
Doosan Winds3000 ◇
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Water depth
30–54 m ≈
Wind speed
7.7 m/s @ 100 m ≈
Revenue & grid
Offtake
Other ◇
Grid
Not recorded ◇
Connection
Grid connection secured ◇
Schedule
FID
Mar 2016 ◆
COD
2017-Q4 ◇
Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026).
Revenue & offtake the regime the project was built under
Offtake regime: Korean RPS (Renewable Portfolio Standard)
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2017-Q4
Sources & verification
1/14 fields verified · rests on 7 sources
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press6
[2]
[3]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionCommercial operationSite rightsTurbinesModel+3 more
[4]
[5]
[6]
Korea Electric Association Journal (전기저널)2016-11
“2006.08월 발전사업허가 및 개발사업시행 승인((주)삼무) ... 2016.03월 선순위(950억원) 대출약정 체결 → 총사업비 재원조달 완료”
supportsConsentFinal investment decisionConsent granted
[7]
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsFirst powerTurbinesModelUnit capacityTotal capacity+2 more