Planta Piloto Petrobras
Brazil's first licensed offshore wind project. Deep water (>100m) floating. Off São João da Barra, northern RJ coast. Pre-FID + floating = min 2029.
Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
Petrobras — 100% ◆Location
Southwest Atlantic
Technology
Capacity
18 MW ◇
Turbines
1 × 18 MW ◇
Foundation
—
Site & conditions
Site rights
Application filed 2024 ◇
Water depth
17–17 m ≈
Wind speed
8.7 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Not taken
COD · Hafrok
2033 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2033
expected year of commercial operation
Chance of delivery
≈50%
estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: a market with no delivery record yet, technical complexity and no offtake contract yet.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2032 | 14.1% |
| 2033 (expected) | 28.0% |
| 2034 | 22.7% |
| 2035 | 14.6% |
| 2036 | 8.7% |
| 2037 | 5.1% |
| 2038 | 3.1% |
| 2039 | 1.8% |
| 2040 | 1.1% |
| 2041 | 0.7% |
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (
2026), adds the time similar projects (in new offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before
2033 is not credible.3
Merchant project — financing counted from today
The project has no offtake contract yet. This project's route offers no support scheme: it has to sign a power contract and take a financing decision on its own, and Hafrok counts that from today (
2026 Q3) rather than from a tender it cannot enter. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2028 Q3), then build time on top gives 2031 Q3. The milestone timing is already later than that, so it stands.4
Result
Expected commercial operation
2033, likely range 2033–2038 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈50%, which rates it
Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026).
Revenue & offtake route to market — open
No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
1/11 fields verified · rests on 7 sources · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[6]
Trade press5
[2]
Offshore Wind Biz2026-04-01◆ Fugro Secures Offshore Wind Work in Braz…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacity
[4]
Offshore Wind Biz2024-06-19◆ Petrobras to Explore Potential Wind Pilo…
Press report — cited, not quoted; read it at the source link.
supportsConsentSite rightsConsent applied
[7]
offshoreWIND.biz2026-04◆ Fugro Secures Offshore Wind Work in Braz…
Press report — cited, not quoted; read it at the source link.
supportsoperator
[8]
[9]
Unverified import1
[1]
unknown◆ Work Starts on Brazil's First Offshore W…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacityWater depthCoordinates