MNRE VGF Scheme - Tamil Nadu 500 MW

TN half of the June 2024 Rs 7,453 cr VGF scheme; tender planned 2026, distinct from the 4 GW seabed lease.

Status
Proposedlifecycle stage
Ownership
SNSECI (no developer awarded) — 100% 
Location
India
Technology
Capacity 500 MW 
Turbines
Foundation
Site & conditions
Site rights Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · developer

Delivery outlook not forecast

We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take.
Next visible round · from the auction calendar
India first VGF offshore wind tender (Gujarat / Tamil Nadu)
expected — · planned · the round’s published documents do not name this project
VGF scheme notified Sep 2024; a 500 MW Gujarat site (NIWE-identified) tender announced Sep 2024; TN 500 MW site being finalised; a separate SECI 4 GW Tamil Nadu seabed-lease-rights tender floated Feb 2024.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

0/4 fields verified · rests on 2 sources
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[1]
PIB2024
supportsownerTotal capacity
Auction pipeline1
[2]
MNRE (India)2026
MNRE offshore wind programme — VGF scheme for 1,000 MW off Gujarat/Tamil Nadu; SECI implementation; 30 GW by 2030 aim.
supportsIndia first VGF offshore wind tender (Gujarat / Tamil Nadu)