SECI Tamil Nadu Offshore Wind Tranche I

Bay of Bengal, SE Tamil Nadu coast. NIWE estimates 35 GW potential off Tamil Nadu. India's 30 GW by 2030 target widely seen as unachievable.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

1/8 fields verified · rests on 5 sources (2 primary) · ◆ 1 document held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[3]
PIB (Government of India / MNRE)2024
supportsUnit capacityTotal capacity
Operator1
[5]
Solar Energy Corporation of India (SECI)2024-02-02◆ RfS for allocation of Seabed Lease Right…
“Under this RfS, the OWPD shall set up the Project at its own cost . All approvals, permits and clearances required for setting up of the Project, including those required from State Government and loc…”
supportsConsentSite rights
Trade press2
[2]
offshoreWIND.biz2025-08-13
Press report — cited, not quoted; read it at the source link.
supportsBackground
[4]
GEBCO Compilation Group2020
supportsWater depth
Unverified import1
[1]
unknown
supportsUnit capacityTotal capacityWater depth