SECI Gujarat Offshore Wind Tranche I
Gulf of Khambhat, Gujarat. India's first offshore wind tender attempt. NIWE estimates 36 GW potential off Gujarat. NTPC-ONGC JV formed Nov 2024.
Status
Cancelledlifecycle stage
Ownership
—
Location
Arabian Sea
Technology
Capacity
500 MW ◇
Turbines
—
Foundation
—
Site & conditions
Site rights
State-designated State designation · Ministry of New and Renewable Energy (MNRE), tendered by SECI · 2024-09 ◆
Water depth
4–14 m ≈
Wind speed
6.6 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
COD
—
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
1/10 fields verified · rests on 7 sources (2 primary) · ◆ 1 document held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[7]
Solar Energy Corporation of India (SECI)2024-09-13◆ RfS for setting up of 500 MW Offshore Wi…
“Pursuant to the Letter of Award, all Stage-II approvals, permits and clearances required for setting up of the Project and/or transmission network up to the offshore Interconnection/ Delivery Point (a…”
supportsConsentSite rights
Trade press5
[2]
offshoreWIND.biz2025-08-13
Press report — cited, not quoted; read it at the source link.
supportsBackground
[3]
offshoreWIND.biz2024-09
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[4]
[5]
[6]
Unverified import1