Dogger Bank South West

Part of Dogger Bank South 3GW complex. Combined DBS capacity could power ~3 million homes.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

LikelyHafrok's delivery likelihood for Dogger Bank South West
The developer says 2031. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

2 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 17 sources (12 primary) · ◆ 12 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator6
[3]
DESNZ2026-01◆ Contracts for Difference Allocation Roun…
“Dogger Bank South West CfD Unit A TA044349 England RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITED Offshore Wind 1500.00 65.45 91.20 2030/31 3 3”
supportsTotal capacityMechanismStrike / priceDetail
[5]
DESNZ2026-05-14◆ Dogger Bank South Offshore Wind Farms de…
“The Dogger Bank South Offshore Wind Farms DCO application has today been granted development consent by the Department for Energy Security and Net Zero.”
supportsConsentConsent granted
[11]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 20217: Site Name "Dogger Bank South West", Development Status "Application Submitted", Installed Capacity 1500 MWelec, Operator "RWE Renewables UK Limited / Mas…”
supportsRegister entry
[15]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 20217: Site Name "Dogger Bank South West", Development Status "Planning Permission Granted", Installed Capacity 1500 MWelec, Operator "RWE Renewables UK Limited…”
supportsRegister entry
[17]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010125: "Dogger Bank South Offshore Wind Farms"; applicant "RWE Renewables UK Dogger Bank South (West) Ltd and RWE Renewables UK Dogger Bank South (East) Ltd"; Stage "Post-decision…”
supportsConsentConsent appliedConsent granted
[18]
legislation.gov.uk (The National Archives)2026-05-14◆ The Dogger Bank South East and West Offs…
“DBS West Project Offshore works Work No. 1B (a) an offshore wind turbine generating station with a gross electrical output of over 100 megawatts comprising up to 100 wind turbine generators each fixed…”
supportsFoundation
Operator5
[4]
RWE AG2026-01-14◆ RWE secures CfDs for 6.9 GW of offshore …
“In December 2023, Masdar (49%) and RWE (51%) joined forces to deliver DBS. On behalf of the partners, RWE is leading the development, construction and operation. Commissioning of the projects is expec…”
supportsCommercial operationCOD history
[8]
RWE/Masdar2026
supportsTurbinesDistance from shore
[12]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-001386-1: "Dogger Bank South West", Status "Scoping", MW Connected 0, Effective From 2030-10-30, Customer "RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMI…”
supportsStatusConnection point
[14]
RWE2025-03-20◆ RWE — 2025 03 20 rwe annual report 2024
“We have formed a partnership with Abu Dhabi-based clean energy firm Masdar to realise two offshore wind projects, which are planned for the southern section of Dogger Bank in the British North Sea. Th…”
supportsoperatorco-investor
[16]
RWE2026-05-14◆ Rwe and masdar receive planning permissi…
“RWE and Masdar will now conduct detailed final design work and progress procurement decisions with the aim of taking a final investment decision (FID) in 2027.”
supportsFinal investment decision
Auction results1
[20]
DESNZ (gov.uk)2026-01◆ cfd-ar7-results-2026
Offshore Wind (Pot 3) cleared GBP 65.45 (2012) / 91.20 (2024): Awel y Môr A 775.00 MW; Dogger Bank South East/West Unit A 1,500.00 MW each; Norfolk Vanguard East A 1,380 / B 90 / C 75 MW; Norfolk Vang…
supportsCfD · AR7
Trade press4
[7]
GEM2026
supportsTotal capacityCoordinates
[9]
GEBCO Compilation Group2020
supportsWater depth
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[19]
Bloomberg (via Energy Connects)2026-07-06◆ Dogger Bank Wind Farm Challenges UK Appr…
Press report — cited, not quoted; read it at the source link.
supportsStatus note
Unverified import1
[1]
unknown
supportsTurbinesTotal capacityWater depthDistance from shoreCoordinates
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.