Dogger Bank C

Final phase of the 3.6 GW Dogger Bank Wind Farm complex.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

Near certainHafrok's delivery likelihood for Dogger Bank C
The developer says 2028. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

4 dated milestones on the spine, each with its source · 4 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 21 sources (17 primary) · ◆ 18 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator4
[1]
legislation.gov.uk2015-08-04◆ The Dogger Bank Teesside A and B Offshor…
"Work No. 1A — (a) an offshore wind turbine generating station with a gross electrical output capacity of up to 1.2 gigawatts comprising up to 200 wind turbine generators each fixed to the seabed by m…
supportsConsentTotal capacityCoordinatesConsent appliedConsent granted
[3]
DESNZ (gov.uk)2019-09-20◆ Contracts for Difference (CfD) Allocatio…
“Doggerbank Teeside A P1 | Doggerbank Offshore WindFarm Project3ProjcoLimited | Offshore Wind | 1200.00 MW | £41.611/MWh | 2024/25”
supportsTotal capacityMechanismStrike / priceDetailCfD · AR3
[15]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2517: Site Name "Dogger Bank C (was Teesside A)", Development Status "Under Construction", Installed Capacity 1200 MWelec, Operator "SSE/Equinor (formerly Stato…”
supportsRegister entry
[22]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010051: "Dogger Bank Teesside A / Sofia Offshore Wind Farm (formerly Dogger Bank Teesside B) - Project previously known as Dogger Bank Teesside A&B"; applicant "Forewind Limited"; …”
supportsConsentConsent appliedConsent granted
Operator10
[4]
Dogger Bank Wind Farm (SSE Renewables / Equinor)2021-12-02◆ DOGGER BANK C REACHES FINANCIAL CLOSE - …
“SSE Renewables, together with its joint venture partner Equinor, has reached financial close on Dogger Bank C … first power is anticipated in Q3, 2025 and full power in Q1, 2026. Onshore cable install…”
supportsFinal investment decisionOnshore construction
[5]
Equinor2021-12-02◆ Equinor and partner reach financial clos…
“Reaching financial close on the third phase of Dogger Bank is a significant milestone as it demonstrates that we are on track with developing what will become the world's largest offshore wind farm.”
supportsFinal investment decision
[6]
Dogger Bank Wind Farm2022-10-17◆ Vargronn acquires Plenitude's 20% intere…
“Vårgrønn acquires Plenitude's 20% interest in the world's largest offshore wind farm … SSE Renewables (40 per cent), Equinor (40 per cent) and Vårgrønn (20 per cent).”
supportsoperatorowner
[7]
SSE Renewables2024-12◆ Dogger Bank Wind Farm signs vessel reser…
“When fully complete in 2027, Dogger Bank will be the world's largest offshore wind farm.”
supportsSeaway Ventus — turbine installation
[11]
SSE Renewables2025-05-23◆ Dogger Bank Wind Farm and delivery partn…
"Dogger Bank Wind Farm and its delivery partners have completed the installation of the HVDC offshore substation platform for Dogger Bank C, the third and final offshore substation platform across all…
supportsStatusConnection point
[16]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000409: "Dogger Bank Project C", Status "Consents Approved", MW Connected 0, Effective From 2025-04-01, Customer "DOGGERBANK OFFSHORE WIND FARM PROJECT 3 …”
supportsStatusConnection point
[17]
Equinor2026-05-06◆ Equinor Q1 2026 results call transcript …
"When it comes to Dogger Bank C, the transition pieces those things are ongoing. And we actually, well, no, let me say -- those were actually completed. Those are actually done half a year ago. And we…
supportsCommercial operationCOD history
[19]
GE Renewable Energy2021-05-18◆ GE Renewable Energy finalizes contracts …
“London, May 18, 2021 - GE Renewable Energy announced today it has finalized the Turbine Supply and Service and Warranty contracts for the third and final phase of the Dogger Bank offshore wind farm, D…”
supportsTurbinesModelUnit capacity
[21]
Dogger Bank Wind Farm (SSE Renewables)2026-08-12◆ Up to 180 new offshore wind jobs created…
"Turbine installation is ongoing at Dogger Bank B following the completion of the phase A turbine campaign earlier this year." ... "Offshore installation works at Dogger Bank C will begin next year." …
supportsCommercial operationturbine marshalling
[23]
SSE Renewables2022-09-26◆ Convertor station works begin for third …
“September 2022: Work has started on the convertor station for the third phase of the world's largest offshore wind farm”
supportsOnshore construction
Record source2
[24]
offshore-energy.biz / offshoreWIND.biz2025-09-03◆ oe-dbc-iac-strashnov-2025-09
Press report — cited, not quoted; read it at the source link.
supportsSeaway Strashnov — foundation installation
[25]
Dogger Bank Wind Farm (SSE Renewables / Equinor / Vargronn)2025-05-23◆ doggerbank-dbc-hvdc-platform-2025-05
Manufactured and supplied by Aibel and installed by Heerema Marine Contractors' Sleipnir vessel, the Dogger Bank C platform measures approximately 75 x 50 metres across and 36 metres high and sits on …
supportsSleipnir — substation installation
Trade press5
[8]
reNEWS2025-11-15◆ Seaway7 installs final monopile at Dogge…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[10]
offshoreWIND.biz2026-05-12
Press report — cited, not quoted; read it at the source link.
supportsturbine marshalling
[12]
GEBCO Compilation Group2020
supportsWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[20]
Dogger Bank Wind Farm2026-09-05◆ Dogger Bank C Weekly Notice of Operation…
“All Monopile / Transition Pieces (MP/TP) in the DB C construction site have now been installed”
supportsFoundation
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.