Aberdeen EOWDC

European Offshore Wind Deployment Centre. Test facility for next-generation turbines in Aberdeen Bay.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

7 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 14 sources (11 primary) · ◆ 11 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator4
[1]
Marine Scotland2013-03-26◆ EOWDC Aberdeen Bay - Section 36 Decision…
“the Scottish Ministers GRANT CONSENT under section 36 of the Electricity Act for the construction and operation of the Development, consisting of up to 11 turbines with a permitted capacity of up to 1…”
supportsConsentTurbinesDistance from shoreConsent appliedConsent granted
[11]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2505: Site Name "European Offshore Wind Deployment Centre (EOWDC) (Aberdeen Bay - Demonstration site)", Development Status "Operational", Installed Capacity 96.…”
supportsRegister entry
[14]
Scottish Government Marine Directorate (MD-LOT)2026-08-23◆ Scottish MD-LOT marine projects register…
“Register row "European Offshore Wind Deployment Centre" (key ml/european-offshore-wind-deployment-centre): Application stage "Post-consent", type "Renewables - Wind".”
supportsRegister entry
[15]
Companies House2026-06-17◆ Aberdeen Offshore Wind Farm Limited — ac…
"Registered number: SC278869 ABERDEEN OFFSHORE WIND FARM LIMITED ANNUAL REPORT FOR THE YEAR ENDED 31 DECEMBER 2024 ... The Company's (Aberdeen Offshore Wind Farm Limited) principal activity consists o…
supportsMechanismDetail
Operator7
[2]
Vattenfall AB2016-07-21◆ Vattenfall to build a wind farm off Aber…
“Vattenfall has decided to invest more than SEK 3 billion in a combined wind farm and technology development centre off the Scottish coast … The wind farm, known as the European Offshore Wind Deploymen…”
supportsoperatorFinal investment decisionOnshore constructionOffshore constructionSite rights
[3]
Vattenfall AB2018-05-28◆ Final turbine successfully installed for…
“The ground-breaking 93.2MW EOWDC, which is scheduled to generate first power in the summer, will produce the equivalent of more than 70% of Aberdeen's domestic electricity demand … It features nine 8.…”
supportsOnshore constructionOffshore constructionSite rightsTurbinesModel+3 more
[4]
Vattenfall AB2018-07-01◆ Vattenfall commissions wind turbines wit…
“On 1 July 2018, wind turbines with the world's largest capacity were taken into operation … Installed capacity: 93.2 MW … Capacity turbines: 8.8 MW (2), 8.4 MW (9)”
supportsFirst powerModelUnit capacityTotal capacity
[5]
Vattenfall AB2018-09-07◆ Vattenfall inaugurates Scottish offshore…
“Today, on 7 September 2018, the European Offshore Wind Deployment Centre, with the world's largest turbine capacity, is inaugurated … Installed capacity: 93.2 MW … The eleven wind turbines, two 8.8 MW…”
supportsCommercial operationCOD history
[6]
Vattenfall AB2026-06-12◆ European Offshore Wind Deployment Centre…
“96.8 Megawatts … 11 x 8.8 megawatt Vestas wind turbines … Energy produced is transported from the turbines to the onshore substation at Blackdog”
supportsStatusConnection point
[7]
Vattenfall AB2017◆ Peterhead Port awarded major offshore wi…
“Peterhead Port Authority … will harbour the game-changing suction bucket jacket foundations for the 11-turbine scheme … The port will also moor one of the world's largest floating cranes … a project s…”
supportsoffshore installation
[12]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000002: "Aberdeen Offshore Wind Farm", Status "Built", MW Connected 95.5, Effective From n/a, Customer "ABERDEEN OFFSHORE WIND FARM LIMITED"”
supportsRegister entry
Trade press3
[8]
unknown
supportsCoordinates
[9]
GEBCO Compilation Group2020
supportsWater depth
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.