BC-Wind

Located off Krokowa/Choczewo municipalities. First project in Poland to be fully delivered from Polish ports.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

Near certainHafrok's delivery likelihood for BC-Wind
The developer has stated no date. Hafrok's year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

3 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 17 sources (12 primary) · ◆ 11 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[8]
European Commission2021-05◆ State aid: Commission approves EUR 22.5 …
“The aid will be granted in the form of a two-way contract-for-difference premium, during 25 years … During the first phase of the scheme, offshore projects will be granted aid using the exception to t…”
supportsMechanismDetail
Operator10
[1]
Ocean Winds2021-06-30◆ Ocean Winds, the 50/50 JV owned by EDPR …
“Ocean Winds, the 50-50 JV owned by EDPR and ENGIE, has been awarded a CfD for the 'B&C-Wind' offshore wind farm in Poland … awarded by the Polish Energy Regulatory Office … capacity 369.5 MW … referen…”
supportsMechanismStrike / priceDetail
[2]
BC-Wind (Ocean Winds project site)2026
“Contract for Difference (CfD) awarded: June 2021 by the Energy Regulatory Office … Grid connection agreement signed: March 2021 … Water depth: 35-60 m … Distance from shore: approximately 23 km … Numb…”
supportsTurbinesUnit capacityTotal capacityFoundationStatus+3 more
[3]
Ocean Winds2025-12-01◆ Ocean Winds has reached Financial Close …
“Ocean Winds has reached Financial Close for its BC-Wind project in Poland … BC-Wind is an offshore wind project developed by Ocean Winds in the Polish Exclusive Economic Zone of the Baltic Sea … 26 tu…”
supportsFinal investment decisionTurbinesUnit capacityTotal capacityFoundation marshalling+2 more
[6]
Ocean Winds2022-10-24◆ Ocean Winds was awarded a positive envir…
“Ocean Winds was awarded a positive environmental decision for the BC-Wind offshore wind farm … The decision was taken by the Regional Directorate for Environmental Protection (RDOŚ) in Gdańsk … an imp…”
supportsConsentConsent granted
[10]
Ocean Winds2025
“Ocean Winds is the exclusive owner of the BC-Wind Project, holding sole rights to develop offshore wind farms across two adjacent sites.”
supportsowner
[13]
BC-Wind (Ocean Winds project site)2026-08-27◆ Zakończyliśmy przewierty HDD na trasie l…
“W ramach prac związanych z budową lądowej infrastruktury przyłączeniowej generalny wykonawca P&Q zakończył przygotowanie dróg serwisowych na potrzeby linii kablowej 275 kV oraz wykonał trzy przewierty…”
supportsOnshore construction
[15]
BC-Wind (Ocean Winds project site)2026-08-06◆ Ocean Winds wybrał Hydrobudowę Gdańsk na…
“Hydrobudowa Gdańsk wybrana na wykonawcę modernizacji nabrzeży i infrastruktury cumowniczej we Władysławowie [...] w trakcie budowy z portu korzystać będą dwie jednostki serwisowe Ocean Winds, a w fazi…”
supportsFoundation marshallingTurbine marshallingO&M / service base (2 service vessels during construction; 1 CTV based there in operations); quay and mooring-infrastructure modernisation by Hydrobudowa Gdańsk, port crane due Q1 2027
[16]
Ocean Winds2025-07-29◆ Ocean winds selects siemens gamesa as th…
“Ocean Winds has entered into a key agreement with Siemens Gamesa for the supply of SG 14-236 wind turbines and service maintenance ... The agreement covers the delivery of 26 wind turbines, each with …”
supportsTurbinesModelUnit capacity
[17]
Ocean Winds2024-09-03◆ Ocean winds receives positive environmen…
“The BC-Wind transmission infrastructure will connect to the National Power System at the 400 kV Choczewo Substation operated by Polskie Sieci Elektroenergetyczne (PSE S.A.).”
supportsStatusConnection point
[18]
DEME Group2025-12-10◆ Deme secures foundation and cable instal…
“DEME will deploy its offshore installation vessel Orion to install 27 monopile foundations: 26 monopiles for the wind turbines and 1 foundation for the offshore substation (OSS).”
supportsFoundation
Auction results1
[19]
Norton Rose Fulbright2026-06-22◆ pl-phase1-admin-cfd-2021-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 1 (administrative)
Trade press5
[5]
Offshore Wind Biz2025-12-01
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityFoundationFoundation marshallingTurbine marshalling+1 more
[7]
Offshore Wind Biz2025-06-10
Press report — cited, not quoted; read it at the source link.
supportsFoundation marshallingTurbine marshallingO&M / service base (2 service vessels during construction; 1 CTV based there in operations); quay and mooring-infrastructure modernisation by Hydrobudowa Gdańsk, port crane due Q1 2027
[11]
Global Energy Monitor2026-07-02
supportsCoordinates
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[14]
offshoreWIND.biz2026-08-14◆ Ocean Winds Selects Bilfinger for Offsho…
Press report — cited, not quoted; read it at the source link.
supportsOnshore construction
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say