Baltyk 3
Twin project with Baltyk 2, combined 1,440 MW. Located off Ustka coast, approximately 22 km from shore. Landfall near Ustka.
Status
Under Constructionlifecycle stage
Near certainHafrok delivery likelihood
Ownership
Equinor — 50% ◆
Polenergia — 50% ◆Location
Baltic Sea
Technology
Capacity
720 MW ◆
Turbines
50 × 14.4 MW ◆
Model
Siemens Gamesa SG 14-236 DD ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
Poland offshore CfD Phase 1 (administrative) · 2021 ·
Water depth
25–39 m ◆
Distance from shore
22 km ◆
Wind speed
9.8 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · 319.6 PLN/MWh ◆
Grid
Secured ◆
Connection
PSE Slupsk Wierzbiecino substation via onshore substations at … ◆
Schedule
FID
19 May 2025 ◆
COD · announced
2028 ◆
COD · Hafrok
for registered readers
Delivery outlook modelled by Hafrok · calibrated on delivered projects
Near certainHafrok's delivery likelihood for Baltyk 3
The developer says 2028. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
4 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 20 sources (19 primary) · ◆ 17 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[10]
European Commission2021-05-01◆ State aid: Commission approves EUR 22.5 …
“The aid will be granted in the form of a two-way contract-for-difference premium, during 25 years. The reference price for projects in the first phase will be administratively fixed based on their cos…”
supportsMechanismDetail
[23]
Pomorski Urząd Wojewódzki w Gdańsku2024-07-11◆ Decyzja nr 88/2024/SJ - pozwolenie na bu…
“po rozpatrzeniu wniosku o pozwolenie na budowę z dnia 10.04.2024 r.”
supportsConsentConsent appliedConsent granted
Operator12
[1]
Equinor2025-05-22◆ Financial close for Bałtyk 2 and Bałtyk …
“Final investment decisions were taken on May 19, 2025, with financial close achieved by May 23, 2025. The projects total 1,440 MW (720 MW each), jointly owned by Equinor (50%) and Polenergia (50%). Tw…”
supportsoperatorco-developerFinal investment decisionCommercial operationTotal capacity
[2]
Polenergia2025-06-26◆ The construction of the Bałtyk 2 and Bał…
“Two onshore substations, cable routes connecting the coast with the energy infrastructure, an O&M base in Łeba – the construction of onshore infrastructure for the Bałtyk 2 and Bałtyk 3 offshore wind …”
supportsOffshore constructionFirst powerStatusConnection pointoperations and maintenance
[6]
Polenergia2025-01-01
“The President of URE granted the right to cover the negative balance of the so-called differential contract at a price of PLN 319.6 per 1 MWh, and Baltyk 3 is included in the first phase of developmen…”
supportsWater depthDistance from shoreCoordinates
[8]
Equinor2022-02-22◆ Turbine supplier selected for Baltyk II …
“Equinor and Polenergia have selected the Siemens Gamesa SG 14-236 DD offshore wind turbine for both MFW Bałtyk II and MFW Bałtyk III. The combined capacity of both projects totals 1440 MW.”
supportsModel
[9]
Sif Group2024-02-16◆ Sif and Equinor Polenergia JV agree on f…
“Sif and Equinor Polenergia JV agreed on final terms for Bałtyk II + Bałtyk III. Firm contracts for 100 monopile foundations for wind turbines, 50 units for each project, in the Polish exclusive econom…”
supportsTurbinesFoundation
[12]
Polenergia2025-05-19◆ Equinor and Polenergia take Final Invest…
“The project joint venture partners – the international Norwegian-based energy company Equinor and Polenergia, Poland's largest private energy group – have taken the final investment decisions for the …”
supportsStatusConnection point
[13]
Polenergia2026-04-29◆ The Bałtyk 2 and Bałtyk 3 offshore wind …
“This reflects the project status at the end of Q1 2026 for Bałtyk 2 and Bałtyk 3, jointly developed by Equinor and Polenergia. ... In January 2026 began the first phase of the offshore installation ca…”
supportsOffshore construction
[14]
Polenergia2026-07-14◆ Landfall hdd completed for the baltyk 2 …
“Landfall HDD has been completed at the construction site of the Bałtyk 2 and Bałtyk 3 offshore wind farms, a joint venture between Equinor and Polenergia.”
supportsStatus note
[15]
Polenergia2026-07-01◆ Baltyk 2 3 turbine foundations halfway c…
“Foundation installation began at Bałtyk 2, located 37 kilometres offshore, where monopiles and transition pieces were installed first. At the same time, work continued on Bałtyk 3, situated 22 kilomet…”
supportsOffshore constructionCOD history
[16]
Polenergia S.A.2024-02-16◆ Siemens Gamesa to supply Baltyk II and B…
“The two energy companies have signed final contracts for the production, delivery and service of 100 modern offshore wind turbines. ... The SG 14-236 DD turbines ordered for the Bałtyk II and Bałtyk I…”
supportsModelUnit capacity
[17]
Heerema Marine Contractors2026-09-02◆ Heerema Marine Contractors Installs 100 …
“Heerema Marine Contractors has successfully completed the offshore foundation installation campaign for the Bałtyk 2 and Bałtyk 3 offshore wind farms in the Baltic Sea, safely delivering the work well…”
supportsThialf — foundation installation
[24]
Polenergia2026-10-01◆ Polenergia notuje zyski za półrocze, zbl…
“farmy offshore o mocy 1 440 MW, Bałtyk 2 i 3, których fundamenty stoją już na morzu ... pierwszy prąd z ich turbin popłynie w 2027 roku ... zakończono wszystkie cztery przewierty na styku lądu i morza…”
supportsStatus note
Financier1
[7]
European Investment Bank2025-05-20◆ Poland: EIB extends €700 million for dev…
“The European Investment Bank provided EUR 700 million total (EUR 350 million for each wind farm), signed on May 20, 2025. The twin projects consist of fixed-bottom installations featuring approximatel…”
supportsTurbinesUnit capacityTotal capacityFoundation
Auction results1
[25]
Norton Rose Fulbright2026-06-22◆ pl-phase1-admin-cfd-2021-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 1 (administrative)
Trade press4
[3]
Offshore Wind Biz2026-02-18◆ Offshore Construction Starts on Polish B…
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionTurbinesModelFoundation
[4]
Offshore Wind Biz2024-08-22◆ All Construction Permits Granted for Bał…
Press report — cited, not quoted; read it at the source link.
supportsConsentConsent appliedConsent granted
[5]
Offshore Wind Biz2021-05-05
Press report — cited, not quoted; read it at the source link.
supportsMechanismStrike / priceDetail
[11]