Baltic Power

Located off Choczewo/Leba coast. Onshore substation at Choczewo municipality complete and ready for commissioning tests.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

Near certainHafrok's delivery likelihood for Baltic Power
The developer says 2026. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

5 dated milestones on the spine, each with its source · 3 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 29 sources (28 primary) · ◆ 18 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[33]
Wojewoda Pomorski (Pomorski Urząd Wojewódzki w Gdańsku)2025-11-27◆ Decyzja nr 138/2025/LH zmieniająca pozwo…
“zmieniam decyzję o pozwoleniu na budowę nr 137/2023/SJ z dnia 16.08.2023r. (sygn. Sprawy WI-II.7840.4.4.2023.SJ) wydaną przez Wojewodę Pomorskiego na rzecz Baltic Power Sp. z o. o., ul. Bielańska 12, …”
supportsConsentConsent granted
Operator17
[1]
Baltic Power (ORLEN Group / Northland Power)
“Baltic Power's offshore wind farm area of approximately 130 square kilometres will feature 76 wind turbines, each with a generating capacity of 15 MW. ... 23 km to the north of the Polish coastline, o…”
supportsCommercial operationTurbinesUnit capacityTotal capacityDistance from shore
[3]
Baltic Power (ORLEN Group / Northland Power)2024-10-18
“In the Baltic Power offshore wind farm area, the depth of the seabed reaches 30-45 metres ... monopiles ... driven more than 40 metres into the seabed.”
supportsFoundationWater depth
[6]
Baltic Power (ORLEN Group)2021-01-14
“Baltic Power, a member of the ORLEN Group, has signed a grid connection agreement with Polskie Sieci Elektroenergetyczne for its offshore wind farm in the Baltic Sea. ... A PSE-operated onshore power …”
supportsStatusConnection point
[7]
Northland Power2023-09-19◆ Northland Power Announces Signing of Cre…
“Northland Power Inc. ... 49% ... Orlen S.A. (51%). ... The project's 25-year Euro-pegged and inflation-indexed Contract for Difference ... Full commercial operations are expected in the latter half of…”
supportsCommercial operationMechanismStrike / priceDetail
[8]
ORLEN (Grupa ORLEN)2023-10-12
Press report — cited, not quoted; read it at the source link.
supportsConsentFinal investment decisionConsent granted
[9]
ORLEN (Grupa ORLEN)2026-02-18◆ All foundations installed as Baltic Powe…
“The installation of all 78 foundations, called monopiles, has been completed at Poland's first offshore wind farm. ... Transition pieces: 60/78 ... Wind turbines: 30/76 ... Baltic Power is scheduled t…”
supportsCommercial operation
[10]
Baltic Power (ORLEN Group / Northland Power)2025-11-01◆ Baltic Power
“Baltic Power opened Poland's first dedicated offshore wind operations and maintenance service base ... in Łeba ... supporting installation work in a marine area covering over 130 km².”
supportsO&M / installation service base
[11]
Baltic Power (ORLEN Group)2025-02-05
“Manufactured at shipyards in Gdynia and Gdańsk, the steel structures of two offshore substations ... The completed structures were moved onto a barge ... and are now sailing to Aalborg for outfitting.”
supportsComponent fabrication / marshalling (offshore substation structures)
[12]
ORLEN2026-06
supportsoperatorowner
[14]
Baltic Power (ORLEN Group / Northland Power)2025-02-06
“As scheduled, the offshore construction of the first Polish offshore wind farm Baltic Power, a joint venture between Orlen Group and Northland Power, has commenced in January. The first monopiles, the…”
supportsOnshore constructionOffshore construction
[16]
Northland Power2026-07-10◆ Northland's Baltic Power Reaches First P…
“TORONTO, July 10, 2026 (GLOBE NEWSWIRE) — Northland Power Inc. (“Northland” or the “Company”) (TSX: NPI) today announced that Baltic Power – its 1.1-gigawatt offshore wind project, owned 49% by Northl…”
supportsFirst powerCOD history
[23]
Baltic Power2026-07-10◆ Morska farma wiatrowa baltic power po ra…
“na farmie Baltic Power – wspólnym projekcie ORLEN i Northland Power – pierwsze turbiny przeszły wymagane testy i dostarczyły energię z morskiego wiatru do krajowej sieci energetycznej. Odbiór energii …”
supportsFirst powerStatusConnection point
[25]
Baltic Power2026-06-22◆ Już 50 turbin zainstalowanych na morskie…
“Projekt znajduje się w końcowej fazie realizacji (postęp prac: ponad 80%). Aktualny status: Fundamenty i elementy przejściowe: 78/78 – prace zakończone Turbiny: 50/76 – w trakcie instalacji Morskie ka…”
supportsStatusConnection point
[28]
Northland Power2026-08-12◆ Northland Power Reports Second Quarter 2…
“The project has 61 of 76 turbines installed and 15 generating power. The project continued its wind turbine installation and commissioning campaign and is on track for commercial operations in the sec…”
supportsCommercial operation
[30]
Northland Power2026-10-07◆ Northlands baltic power offshore wind pr…
“All 76 turbines are now installed, with over one-third currently generating power. The project is advancing through commissioning and is on track for commercial operations in 2026, with costs aligned …”
supportsCommercial operation
[32]
Cadeler2026-10-07◆ Cadeler completes its turbine installati…
“Copenhagen, 7. October 2026 – Cadeler has completed its turbine installation campaign for all the 76 wind turbines at the 1.2 GW Baltic Power offshore wind farm in the Baltic Sea. This milestone marks…”
supportsFirst power
[34]
Baltic Power (ORLEN Group / Northland Power)2023-05-21◆ The construction of transmission infrast…
“The ORLEN Group and Northland Power have commenced the construction of an onshore substation in the Choczewo municipality.”
supportsOnshore constructionOffshore construction
OEM2
[2]
Vestas / windfair2023-09-28
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacity
[27]
Vestas Wind Systems A/S2023-09-28◆ Vestas wins 1,140 MW offshore order for …
“Vestas has secured a 1,140 MW firm order from Baltic Power Sp. z o.o, a joint venture between ORLEN S.A. and Northland Power Inc, for the Baltic Power Offshore Wind Project in Poland. Vestas will supp…”
supportsTurbinesModelUnit capacityTotal capacity
Auction results1
[35]
Norton Rose Fulbright2026-06-22◆ pl-phase1-admin-cfd-2021-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 1 (administrative)
Record source4
[36]
Van Oord2025-02◆ vanoord-svanen-first-monopile-2025-02
Heavy lift installation vessel Svanen installs first monopile at Baltic Power wind farm | Van Oord
supportsSvanen — foundation installation
[37]
offshore-energy.biz / offshoreWIND.biz2026-03-20◆ oe-baltic-power-all-tps-2026-03
Press report — cited, not quoted; read it at the source link.
supportsMV Lone — foundation installation
[38]
Cadeler A/S2025-07-07◆ cadeler-baltic-power-first-wtg-2025-07
This weekend, Cadeler successfully completed the installation of the very first Vestas 15MW turbine at the Baltic Power Offshore Wind Farm in the Baltic Sea... Over the coming months, Cadeler's Wind O…
supportsWind Osprey — turbine installation
[39]
Cadeler A/S2026-04-10◆ cadeler-wind-mover-first-project-2026-04
Cadeler's newbuild wind installation vessel Wind Mover is installing the very first turbine on her first transportation and installation campaign following her delivery last year. From Port of Ronne i…
supportsWind Mover — turbine installation
Trade press4
[4]
The Wind Power (industry database)
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[5]
Energy Regulatory Office (URE) / offshoreWIND.biz2021-06-16◆ 1.2 GW Baltic Power Offshore Wind Farm S…
Press report — cited, not quoted; read it at the source link.
supportsMechanismStrike / priceDetail
[13]
offshoreWIND.biz2023-05-23
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[15]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.