Dunkirk (Dunkerque)

AO3 Round 3 project. Located in the North Sea near the Belgian border, covering 50 km2. Turbines up to 240-300m high.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
EDF Renewables — 40% 
Enbridge — 30% 
RWE — 30% 
Location
France
North Sea
Technology
Capacity 600 MW  Turbines 46  Foundation Monopile 
Site & conditions
Site rights Seabed rights held 
Origination France Offshore Wind Dunkerque (AO3) · 2019 ·
Water depth 19–30 m  Distance from shore 10 km  Wind speed 9.4 m/s @ 150 m 
Revenue & grid
Offtake CfD · €44/MWh  Grid Offered · 2024-12  Connection RTE grid connection: offshore substation + dual 225 kV … 
Schedule
FID Not taken
COD · announced 2027 
COD · Hafrok 2030 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2030
expected year of commercial operation
The developer says 2027; Hafrok expects 2030 — 3 years later.
Chance of delivery
≈82% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record, its size and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2029: 14.1% (conditional on completion) 2030: 28.0% (conditional on completion) 2031: 22.7% (conditional on completion) 2032: 14.6% (conditional on completion) 2033: 8.7% (conditional on completion) 2034: 5.1% (conditional on completion) 2035: 3.1% (conditional on completion) 2036: 1.8% (conditional on completion) 2037: 1.1% (conditional on completion) 2038: 0.7% (conditional on completion)2026now20272028203028%EXPECTED2032203420362038 Developer-announced COD: 2027 ANNOUNCED 2027
COD probability by year, conditional on completion
YearProbability
202914.1%
2030 (expected)28.0%
203122.7%
203214.6%
20338.7%
20345.1%
20353.1%
20361.8%
20371.1%
20380.7%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2025. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2030; the faster quarter of similar projects would be done by 2028, the slower quarter not until 2030.
3
Result
Expected commercial operation 2030, likely range 2028–2030 (the middle half of outcomes for similar projects). The developer's announced date (2027) is earlier than similar projects have managed — Hafrok's own date is used and the difference is flagged above.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈82%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2020’21’22’23’24’25’26’27’28’29’30Developer-announced COD: 2027 announced COD 2027France Offshore Wind Dunkerque (AO3) — awarded to EDF Renouvelables + Innogy (RWE) + EnbridgeFrance Offshore Wind Dunkerque (AO3) Jun 2019 · auction recordView the source for Consent grantedConsent granted Feb 2025 Commercial operation 2030 ·Hafrok expectedFrance Offshore Wind Dunkerque (AO3) — awarded to EDF Renouvelables + Innogy (RWE) + Enbridge 2019-06 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYEDF Renewables — 40% today EDF Renewables EDF Renewables 40%Enbridge — 30% today Enbridge Enbridge 30%innogy innogy innogy exited 2019-06RWE — 30% today RWE RWE 30%France Offshore Wind Dunkerque (AO3) — awarded to EDF Renouvelables + Innogy (RWE) + Enbridge Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

600 MW contracted — tender award
Tender award · France Offshore Wind Dunkerque (AO3)
Price€44/MWh ·Capacity600 MWAwardedJun 2019
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2027

Sources & verification

6/15 fields verified · rests on 16 sources (7 primary) · ◆ 9 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator7
[3]
Eoliennes en mer de Dunkerque (EMD)2025-02-18◆ Obtention des autorisations pour le deve…
“la préfecture du Nord a délivré le 14 février 2025 un arrêté préfectoral d'autorisation environnementale pour la construction et l'exploitation du Parc éolien en mer de Dunkerque.”
supportsConsentConsent granted
[4]
RTE (Réseau de Transport d'Electricité)2026-02◆ Bilan annuel de la concertation continue…
“A EMD, un arrêté préfectoral d'autorisation environnementale pour la construction et l'exploitation du parc éolien en mer au large de Dunkerque, le 14 février 2025. [...] il s'agira de définir les com…”
supportsStatusConnection point
[5]
Europe en France / Direction Générale des Affaires Européennes2022◆ SA.51061 - France - Parc éolien en mer d…
“Le parc éolien en mer de Dunkerque, d'une puissance de 600 MW maximum, dont la mise en service est prévue en 2027, est soutenu par un complément de rémunération de l'électricité produite. [...] Entrée…”
supportsCommercial operationTotal capacityMechanismDetail
[6]
Offshore Wind Biz2019-06-20◆ Dunkirk Strike Price Is EUR 44/MWh
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityStrike / price
[7]
EDF Group2019-06-14◆ EDF Dunkirk consortium selected
“France's Ministry for the Ecological and Inclusive Transition has selected the EDF Group, via its EDF Renewables subsidiary, in partnership with Innogy and Enbridge, to design, build, operate and main…”
supportsTotal capacity
[8]
CRE (Commission de régulation de l'énergie)2023-03◆ AO4 Centre Manche 1 - CRE deliberation 2…
“Procédure dite « AO3 » - 2016 : Dunkerque (600 MW d'éolien posé) : le projet a été attribué en 2019 ; [...] le tarif de référence du lauréat de Dunkerque, proposé initialement à un niveau de 44 €2019/…”
supportsTotal capacity
[17]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 853 (node--type-project) at /facades-maritimes-en-france/facade-manche-mer-du-nord/dunkerque — title 'Dunkerque'; page text 2718 chars, hash 88f5194638d5fb86…. Identifying text: Le parc …”
supportsRegister entry
Auction results1
[18]
CRE (Commission de regulation de l'energie) / DGEC2018◆ fr-ao3-cahier-des-charges
AO3 Dunkerque cahier des charges ("DUNKERQUE - CAHIER DES CHARGES - 15 novembre 2018"); the dialogue concurrentiel that produced the record-low ~44 EUR/MWh strike via complement de remuneration.
supportsTender award · France Offshore Wind Dunkerque (AO3)
Trade press7
[10]
reNEWS2024◆ EDF, Innogy, Enbridge take 600MW Dunkirk…
Press report — cited, not quoted; read it at the source link.
supportsowner
[11]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacityFoundation
[12]
Global Energy Monitor2026
supportsTotal capacity
[13]
Eoliennes en Mer de Dunkerque (official project site)2025
supportsDistance from shore
[14]
Global Energy Monitor2026-07-02
supportsCoordinates
[15]
GEBCO Compilation Group2020
supportsWater depth
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTurbinesTotal capacityFoundationWater depthDistance from shore+1 more