Horns Rev 1

Located ~14-20 km west of Esbjerg, Jutland. Originally built by Elsam/DONG (now Ørsted); Vattenfall acquired 60% in 2005 and is operator.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2001’02’03’04’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted 29 Mar 2001 View the source for Onshore constructionOnshore construction 2002 View the source for Offshore constructionOffshore construction 2002 View the source for First powerFirst power 2002-Q3 View the source for Commercial operationCommercial operation 2002-Q4 No origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDØrsted → Vattenfall — 60.0% · €268m · closed 2006-07 2005-05 ACQUISITIONTODAYØrsted — 40% today Ørsted Ørsted 40%Vattenfall — 60% today · operator Vattenfall Vattenfall 60%Ørsted → Vattenfall — 60.0% · €268m · closed 2006-07 60%
Dashed tick marks today (9 Sep 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing8080 turbines + 1 platform expected · 1 fewer than expected — a position the survey missed
Surveyed2026-09-01from 119 satellite passes
Built2002 → 2002-Q4offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed80 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Esbjerg ·operations base · quay 10000 m · crane 300 t · draft 15 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (80)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Horns Rev 1, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationHorns Rev 1 transformer platform·owner Vattenfall (60%) / Ørsted (40%) — the ENS established-parks page states that split for the WIND FARM; no held document apportions the platform itself.

Sources & verification

17/18 fields verified · rests on 10 sources (6 primary) · ◆ 9 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Energistyrelsen (Danish Energy Agency)2001-03◆ Energistyrelsens godkendelse og sammenfa…
"Den 29. marts 2001 Miljø- og energiministeren gav med brev af 13. februar 1998 ... pålæg til Elsam og Eltra om i fællesskab at opføre op til 300 MW havbaseret vindkraft." "havvindmølleparken vil få e…
supportsConsentTotal capacityFoundationWater depthDistance from shore+1 more
[2]
Energistyrelsen (Danish Energy Agency)2002◆ Elproduktionsbevilling for Horns Rev 1
“Elproduktionsbevilling for Horns Rev 1. Scanned document — no machine-readable text layer. Per secondary sources dated 2002-07-25. Backs lifecycle.offtake_secured (production licence issued by Energis…”
supportsMechanismDetail
[3]
Energistyrelsen (Danish Energy Agency)◆ Eksisterende havvindmølleparker
"Vindmølleparken blev etableret i 2002 og består af i alt 80 møller på i alt 160 MW." "Vattenfall besidder 60 procent af ejerskabet for Horns Rev Vindmøllepark, mens Ørsted besidder de sidste 40 proce…
supportsTurbines
Operator3
[4]
Ørsted A/S (DONG Energy)2015-05◆ Horns Rev 1 wind turbine has reached the…
"Horns Rev 1 consists of 80 Vestas 2.0MW wind turbines and has a total capacity of 160MW. The wind farm is located approximately 20km west off Blåvandshuk on the west coast of Jutland. Vattenfall oper…
supportsownerTurbinesModelUnit capacityTotal capacity+1 more
[6]
Vattenfall◆ Power plants: Horns Rev 1 - Vattenfall
“Horns Rev 1 "20 kilometres off the west coast of Jutland." "158 megawatts of electricity using 80 turbines supplied by Vestas." "In Operation (inaugurated in 2002)." "Vattenfall Ownership: 60%." Water…”
supportsTurbinesModelStatusConnection pointWater depth+1 more
[10]
Vattenfall2025◆ Vattenfall — vattenfall corporate factbo…
“Horns Rev 1 60% 95 158”
supportsTotal capacity
Financier1
[7]
European Investment Bank2002-07-05◆ ELSAM OFFSHORE WINDFARM
"ELSAM OFFSHORE WINDFARM." Promoter: "Elsam A/S, Fredericia, Denmark." "80 wind turbines with 2 MWe capacity each, generating approximately 600 GWh annually." "Approved: 5 July 2002. Signed: 19 May 20…
supportsTurbinesUnit capacity
Trade press3
[5]
offshoreWIND.biz2025-02-10◆ GWS, Swire Secure O&M Contract for Horns…
Press report — cited, not quoted; read it at the source link.
supportsoperatorTotal capacityoperations base
[8]
Tethys (PNNL / US DOE)◆ Horns Rev 1 | Tethys
"Construction Start: March 1, 2002." "First Turbine: July 29, 2002." "Full Commission: December 11, 2002." "Foundation Type: Monopile." "Water Depth: 6-14 m." "Distance from Shore: 20 km." "Capacity p…
supportsFinal investment decisionOnshore constructionOffshore constructionFirst powerCommercial operation+4 more
[9]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed