Avedore Holme
Located immediately off the coast of Avedøre Holme industrial area, south of Copenhagen, Oresund strait.
Status
Operationallifecycle stage
Ownership
Ørsted — 66.67% ◆HVHvidovre Vindmøllelaug — 33.33% ◇
Location
Øresund
Technology
Capacity
10.8 MW ◆
Turbines
3 × 3.6 MW ◆
Model
Siemens Swt 3-6-120 ◆
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Water depth
2–4 m ◇
Distance from shore
0.5 km ◆
Wind speed
8.4 m/s @ 100 m ≈
Revenue & grid
Offtake
Other ◆
Grid
Not recorded ∅
Connection
Avedore power station local grid ∅
Schedule
FID
Taken · date not recorded ∴
COD
2011 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
5 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 10 sources (5 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Energistyrelsen2008-11◆ Download
“(Scanned image PDF - no machine-readable text layer; held for document existence and date evidence only. The consent sentence is carried verbatim by the ens.dk established-parks page source on this re…”
supportsConsentTurbinesConsent granted
[2]
Energistyrelsen◆ Elproduktionstilladelse - Avedoere Holme
“Elproduktionstilladelse for Avedøre Holme havvindmøllepark udstedt af Energistyrelsen. (Scanned document — text not extractable; cited for existence and regulatory authority.)”
supportsMechanismDetail
[3]
Energistyrelsen2024◆ Eksisterende havvindmølleparker
“Avedøre Holme (2009/2010) — 10.8 MW, 3 turbines. Energistyrelsen gav den 18. november 2008 Ørsted tilladelse til opstilling af 3 store demonstrationsvindmøller i havet umiddelbart syd for diget på den…”
supportsConsentFinal investment decisionOnshore constructionOffshore constructionFirst power+8 more
Operator2
[4]
Ørsted A/S2022-02◆ Ørsted Annual Report 2021
“In 2021, we started construction work at our demonstration project H2RES, which will produce renewable hydrogen for road transport powered by our two 3.6 MW offshore wind turbines at Avedøre Holme, De…”
supportsoperatorTurbinesUnit capacity
[5]
Trade press3
[6]
[7]
Maritimedanmark.dk (trade publication)2008-11
“Three new turbines were planned with a combined capacity of 10-15 MW, positioned between 20 and 100 meters out in the water at Avedøreværket on Avedøre Holme in Hvidovre. As part of the project, 13 ex…”
supportsDistance from shore
[10]
Encyclopaedic2
[8]
[9]