Aflandshage
Open-door project located 10km south of Amager (Copenhagen), 8km northeast of Stevns in Oresund. 26 gravity-based foundations ordered from Aarsleff.
Status
On Holdlifecycle stage
UnlikelyHafrok delivery likelihood
Ownership
HOFOR — 100% ◇Location
Øresund
Technology
Capacity
286 MW ◇
Turbines
26 × 11 MW ◇
Model
Siemens Gamesa SG 11-0-200 DD ◇
Foundation
GBS ◇
Site & conditions
Site rights
Application filed 2023-07 ◆
Water depth
13–17 m ≈
Distance from shore
10 km ◇
Wind speed
9.6 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Not taken
COD · Hafrok
for registered readers
On hold since
3 Nov 2023 ◆
Delivery outlook modelled by Hafrok · calibrated on delivered projects
UnlikelyHafrok's delivery likelihood for Aflandshage
On hold. Hafrok's view of a restart is for registered readers.
Free for registered readers in early access · register below ↓
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
2 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 12 sources (3 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[10]
Energistyrelsen (Danish Energy Agency)2022-11-11◆ Energistyrelsen udsteder etableringstill…
“Energistyrelsen har den 11. november 2022 meddelt etableringstilladelse til Aflandshage Vindmøllepark. [...] Energistyrelsen har med tilladelsen givet HOFOR Vind A/S ret til at opføre elproduktionsanl…”
supportsConsentSite rightsConsent applied
Operator2
[1]
HOFOR (operator)2025◆ Aflandshage Vindmøllepark - HOFOR
“As of 2025, HOFOR has completed two years of bat surveys (started August 2023) and is in dialogue with authorities about reacquiring permits. A central question involves whether modern turbines can re…”
supportsTurbinesDistance from shore
[11]
HOFOR2023-11-03◆ HOFORs investering i Øresunds havvindpro…
“Energistyrelsens afgørelse blev dog påklaget til Energiklagenævnet, som i begyndelsen af juli 2023 ophævede etableringstilladelsen, primært med henvisning til at en allerede planlagt flagermusundersøg…”
supportsConsentOn holdSite rights
Auction pipeline1
[13]
Danish Energy Agency (Energistyrelsen)2025-11◆ dea-3-tenders-2025
DEA — Nordsøen Syd, >=1,000 MW, bid deadline autumn 2028.
supportsNordsøen Syd (North Sea South)
Trade press8
[2]
Offshore Wind (offshorewind.biz)2023-11-06◆ HOFOR Shelves 300 MW Offshore Wind Proje…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityFoundationturbines
[3]
Baltic Wind2023-11
Press report — cited, not quoted; read it at the source link.
supportsBackground
[4]
Splash2472023-11
“HOFOR has put its Aflandshage offshore wind project on hold with the possibility of completely pulling the plug on the project. The establishment permit was withdrawn in July 2023 following complaints…”
supportsBackground
[5]
[6]
[7]
[8]
NS Energy2023
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[9]