Sunrise Wind
Located ~48 km east of Montauk Point, Long Island NY. 84 monopiles fabricated at Sif/Smulders Netherlands.
Status
Under Constructionlifecycle stage
Near certainHafrok delivery likelihood
Ownership
Ørsted — 100% ◆Location
Northwest Atlantic
Technology
Capacity
924 MW ◆
Turbines
84 × 11 MW ◆
Model
Siemens Gamesa SG 11-0-200 DD ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
BOEM Lease Sale 2 · 2013 ·
Water depth
31–38 m ≈
Distance from shore
48 km ◆
Revenue & grid
Offtake
OREC · $146/MWh ◆
Grid
Secured · 12 May 2023 ◆
Connection
LIPA Holbrook substation, Long Island (NYISO Zone K); HVDC … ◆
Schedule
FID
Mar 2024 ◆
COD · announced
2027-H2 ◆
COD · Hafrok
for registered readers
Delivery outlook modelled by Hafrok · calibrated on delivered projects
Near certainHafrok's delivery likelihood for Sunrise Wind
The developer says 2027-H2. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
5 dated milestones on the spine, each with its source · 4 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 25 sources (25 primary) · ◆ 20 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[12]
Bureau of Ocean Energy Management (BOEM)2024-06◆ Sunrise Wind | Bureau of Ocean Energy Ma…
“Lease Number OCS-A 0487. Capacity 924 megawatts. Up to 84 wind turbine generators. Located approximately 16.4 nautical miles south of Martha's Vineyard, MA; approximately 26.5 nautical miles east of M…”
supportsConsentTurbinesTotal capacityStatusConnection point+2 more
[30]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0487: companies ['Sunrise Wind, LLC']; lease_dates ['10/01/2013']; lease_terms ['25 Years']; states ['New York', 'Rhode Island / Massachusetts']; block_count 163.”
supportsRegister entry
Operator15
[1]
Ørsted A/S2024-03◆ Sunrise Wind receives federal record of …
“Sunrise Wind today received its Record of Decision (RoD) from the US Department of the Interior's Bureau of Ocean Energy Management (BOEM), crossing a critical milestone in the federal environmental r…”
supportsFinal investment decisionTotal capacityDistance from shore
[2]
Ørsted A/S2024-06◆ Sunrise Wind receives final approval fro…
“Sunrise Wind, New York's largest offshore wind project, has received approval of its construction and operations plan (COP) from the US Department of the Interior's Bureau of Ocean Energy Management (…”
supportsConsentTotal capacityConsent appliedConsent granted
[3]
Ørsted A/S2024-02◆ Sunrise Wind selected for award in New Y…
“New York's energy agency, NYSERDA, has conditionally awarded Ørsted and Eversource's Sunrise Wind project the right to negotiate a 25-year offshore wind renewable energy certificate (OREC) agreement f…”
supportsTotal capacity
[4]
Ørsted A/S2024-01◆ Ørsted to acquire full ownership of Sunr…
“Ørsted has signed an agreement with Eversource to acquire Eversource's 50 % share of Sunrise Wind, a 924 MW offshore wind farm which would deliver power to New York. The acquisition is subject to the …”
supportsTotal capacity
[5]
Ørsted A/S2025-12◆ Revolution Wind and Sunrise Wind receive…
“On 22 December 2025, Revolution Wind LLC, a 50/50 joint venture with Global Infrastructure Partners' Skyborn Renewables, and Sunrise Wind LLC, a fully-owned subsidiary, received orders from the U.S. D…”
supportsBackground
[6]
Ørsted A/S2026-01◆ Sunrise Wind LLC to file Preliminary Inj…
“Today, Sunrise Wind LLC ("Sunrise Wind"), a wholly owned subsidiary of Ørsted, will file a complaint in the U.S. District Court for the District of Columbia, challenging the lease suspension order iss…”
supportsTurbinesFoundation
[7]
Ørsted A/S2026-02◆ Ørsted Annual Report 2025
“Sunrise Wind is ~45 % complete, with more than half of the foundations installed, and commissioning is planned for H2 2027. Commercial operation date: H2 2027. Resumed offshore activities following gr…”
supportsBackground
[8]
Ørsted A/S2025-02◆ Ørsted Annual Report 2024
“We took final investment decisions for the offshore wind farm Sunrise Wind (924 MW). In July, we completed the acquisition of Eversource's 50 % interest in Sunrise Wind, which was owned jointly by Ørs…”
supportsoperatorTotal capacity
[9]
Ørsted A/S2026-05◆ Ørsted IR presentation Q1 2026
“Sunrise Wind. Location US. Capacity 924 MW. Offtake contract: Nominal offtake with state of New York. Commercial operation date H2 2027. Degree of completion ~47 %, up from 45 % in January 2026. The p…”
supportsCommercial operationCOD historyUnit capacityTotal capacity
[10]
Ørsted A/S2026-05◆ Ørsted Q1 2026 earnings call transcript
“Turning now to slide 9 and an update on the progress at Sunrise Wind. During the quarter, the project has continued to make progress and achieved an important milestone as the first turbines have succ…”
supportsTurbines
[14]
Connecticut Port Authority2024
“Sunrise Wind is already scheduled to be delivered from the completed State Pier Terminal facility. The facility is used for staging and assembly of offshore wind turbines for multiple projects includi…”
supportsturbines
[21]
Ørsted2025-05-07◆ Orsted — q1 2025 earnings call transcr…
“As always, unless I stayed otherwise, the numbers I referred to will be in Danish kroner. ... we had a net impairment reversal of 300 million. The main contributor to this reversal was a decrease in l…”
supportsOnshore constructionOffshore construction
[27]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
"Commercial operation date H2 2027" ... "Degree of completion ~50 %, up from 47 % in Q1 2026" ... "The project continues work towards commissioning of first turbines later this year and commercial op…
supportsBackground
[31]
NYSERDA2024-05-31◆ OREC Purchase and Sale Agreement No. 231…
“(i) The Index OREC Strike Price, for each month in the respective Contract Years shall be $146.00/MWh. [...] The Contract Tenor under this Agreement shall be twenty five (25) Contract Years [...] The …”
supportsMechanismStrike / priceDetailStatusConnection point
[32]
New York Independent System Operator (NYISO)2023-05-15◆ Notice of Class Year 2021 Additional SDU…
“May 15, 2023 TO: Remaining Class Year 2021 Additional SDU Study Projects Queue # Project/Facility Developer/Owner 766 Sunrise Wind (aka NY Wind Holbrook) Sunrise Wind LLC [...] This is to inform you t…”
supportsStatusConnection point
OEM1
[13]
EVWIND (reporting Siemens Gamesa press release)2022-09
“Siemens Gamesa confirmed a firm order to supply 84 SG 11.0-200 DD offshore wind turbines for the 924 MW Sunrise Wind offshore wind project developed by Ørsted and Eversource off Montauk Point, New Yor…”
supportsTurbinesModelUnit capacity
Auction results2
[33]
New York PSC2026-06-22◆ us-nyserda-sol1-2019-nypsc-repricing
NY PSC denies OREC inflation-adjustment petitions (Oct 2023): the contracts had no reopener
supportsOREC · NYSERDA Offshore Wind Solicitation 1 (ORECRFP18-1)
[34]
NY Dept of Public Service2018◆ us-ny-psc-order-18e0071
NY PSC Order, Case 18-E-0071 - establishes the Offshore Wind Standard and the OREC mechanism.
supportsOREC · NYSERDA Fourth (Expedited) Offshore Wind Solicitation (2024)
Record source1
[35]
offshore-energy.biz / offshoreWIND.biz2026-04-17◆ oe-sunrise-first-turbine-2026-04
Press report — cited, not quoted; read it at the source link.
supportsWind Scylla — turbine installation
Trade press4
[15]
Offshore Wind (offshorewind.biz)2024-09
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionassembly
[16]
[17]
[19]
Ørsted2025-05-07◆ Orsted — interim financial report q1 202…
“our Sunrise Wind project, offshore installation commenced in Q1 2025 and the degree of completion is now at approx. 35 %.”
supportsOnshore constructionOffshore construction