Planned 1,148 MW follow-on to Ocean Wind 1, also off New Jersey coast.
Technology
Capacity
1,148 MW ◆
Turbines
—
Foundation
—
Site & conditions
Site rights
Seabed rights held Seabed lease · Bureau of Ocean Energy Management (BOEM) · 2016-03 ◆
Water depth
15–35 m ≈
Wind speed
9.6 m/s @ 150 m ≈
Revenue & grid
Offtake
OREC cancelled ◆
Grid
—
Schedule
COD
—
Cancelled
31 Oct 2023 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
1 dated milestone on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 8 sources (3 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[9]
Bureau of Ocean Energy Management (BOEM)2024◆ Ocean Wind 2 (OCS-A 0532) - BOEM project…
“Ocean Wind 2 has not submitted a Construction and Operations (COP) for BOEM review.”
supportsConsentSite rights
Operator3
[3]
[4]
[5]
Ørsted2021◆ Ørsted awarded 1,148 MW offshore wind co…
“Subject to contract signing and Ørsted's final investment decision, Ocean Wind 2 is expected to be commissioned in 2029.”