Revolution Wind

Located ~32 km southeast of Point Judith, Rhode Island and ~52 km southeast of New London, CT. First multi-state offshore wind project in the US.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

Near certainHafrok's delivery likelihood for Revolution Wind
The developer says 2026-H2. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

6 dated milestones on the spine, each with its source · 4 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 22 sources (24 primary) · ◆ 19 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Bureau of Ocean Energy Management (joint BOEM/NMFS/USACE)2023-08-21◆ Revolution Wind Record of Decision (OCS-…
“The Proposed Action will construct and install, operate, maintain, and include the eventual decommissioning of a wind energy facility within the Project Design Envelope (PDE) and implementation of app…”
supportsConsentTotal capacityFoundationStatusConnection point+2 more
[2]
Bureau of Ocean Energy Management2023-11-17◆ Revolution Wind COP approval letter
“On Nov. 17, 2023, the Bureau of Ocean Energy Management (BOEM) approved the Construction and Operations Plan (COP), as modified by the selected alternative in the Record of Decision, for the Revolutio…”
supportsConsentConsent appliedConsent granted
[32]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0486: companies ['Revolution Wind, LLC']; lease_dates ['10/01/2013']; lease_terms ['25 Years']; states ['Rhode Island / Massachusetts']; block_count 174.”
supportsRegister entry
Operator11
[3]
Ørsted2018-12◆ Connecticut Regulators Approve Revolutio…
“Connecticut's Public Utilities Regulatory Authority today approved Ørsted's long-term power-purchase agreement with Eversource and United Illuminating, two Connecticut utilities, for the 200 megawatts…”
supportsMechanismDetailmarshalling
[4]
Ørsted2025-08-22◆ Revolution Wind receives offshore stop-w…
“On 22 August 2025, Ørsted's subsidiary Revolution Wind LLC, a 50/50 joint venture with Global Infrastructure Partner's Skyborn Renewables, received an order instructing the project to stop activities …”
supportsTurbines
[5]
Ørsted2025-12-22◆ Revolution Wind and Sunrise Wind receive…
“On 22 December 2025, Revolution Wind LLC, a 50/50 joint venture with Global Infrastructure Partners' Skyborn Renewables, and Sunrise Wind LLC, a fully-owned subsidiary, received orders from the U.S. D…”
supportsoperatorco-owner
[6]
Ørsted2026-01-02◆ Revolution Wind LLC to file Preliminary …
“The Project, now approximately 87 percent complete, has already installed all offshore foundations and 58 of 65 wind turbines. Export cable installation is complete, and both offshore substations have…”
supportsStatusConnection pointmarshalling
[7]
Ørsted2026-03-14◆ Revolution Wind begins delivering power …
“Revolution Wind, LLC, a 50/50 joint venture between Global Infrastructure Partners' Skyborn Renewables and Ørsted, announced today that the Revolution Wind project has started delivering power to New …”
supportsFirst power
[8]
Ørsted2024-02◆ Ørsted Annual Report 2023
“In the US, we took FID on the 704 MW Revolution Wind project, which we own in a 50/50 partnership with Eversource Energy. Onshore construction has started, and offshore construction will start in 2024…”
supportsFinal investment decisionOnshore constructionOffshore construction
[13]
Ørsted2026-05◆ Ørsted IR presentation Q1 2026
“Revolution Wind. Location US. Capacity 704 MW. Offtake contract: Nominal offtake with state of Rhode Island and Connecticut. Commercial operation date H2 2026. Degree of completion ~94 %, up from 87 %…”
supportsCommercial operationCOD historyTurbinesUnit capacity
[19]
Ørsted2023-11-01◆ document
“Ørsted has today taken the final investment decision (FID) on the 704 MW Revolution Wind project, which Ørsted owns in a 50/50 partnership with Eversource. Onshore construction has started, and offsho…”
supportsFinal investment decision
[29]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
“Borkum Riffgrund 3 Changhua 2b and 4 Revolution Wind Sunrise Wind Baltica 2 Hornsea 3 / BESS Capacity1 913 MW 920 MW 704 MW 924 MW 1,498 MW 2,852 MW / 300 MW COD Q3 2026 Q3 2026 H2 2026 H2 2027 H2 20…”
supportsBackground
[34]
Revolution Wind (Ørsted / Eversource)2024-05-15◆ Revolution Wind Achieves First Steel in …
“RHODE ISLAND / CONNECTICUT – MAY 15, 2024 – Revolution Wind has achieved its “steel in the water” milestone with the installation of the project’s first turbine foundation, a momentous milestone for R…”
supportsOnshore constructionOffshore construction
[37]
Ørsted2023-11-01◆ Company announcement No. 24/2023: Ørsted…
“Company announcement No. 24/2023 ... 1 November 2023”
supportsFinal investment decision
Auction results2
[38]
Connecticut General Assembly2017◆ us-ct-pa-17-144
Connecticut Public Act 17-144 - the procurement authority for the 2018 Revolution Wind selection.
supportsUtility PPA · Connecticut Offshore Wind Procurement (Revolution Wind; PA 17-144 Clean Energy RFP 200 MW + PA 17-3 Zero-Carbon RFP ~100 MW)
[39]
Wikipedia (citing RI PUC docket)2024◆ ri-rev-2018-puc
The RI PPA secures 400 MW over 20 years; National Grid pays 9.84 c/kWh. (Wikipedia citing the RI PUC docket; price not re-verified against the primary order.)
supportsUtility PPA · Rhode Island Offshore Wind Procurement (2018, National Grid)
Record source1
[40]
offshore-energy.biz / offshoreWIND.biz2026-04-17◆ oe-sunrise-first-turbine-2026-04
Press report — cited, not quoted; read it at the source link.
supportsWind Scylla — turbine installation
Trade press5
[14]
Global Energy Monitor2026-07-02
supportsCoordinates
[15]
GEBCO Compilation Group2020
supportsWater depth
[18]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[28]
Ørsted A/S2025-Q3◆ Ørsted Q3 2025 earnings call transcript
“First power is expected during the first half of 2026, and the project remains on track for commissioning in the second half of 2026.”
supportsCommercial operation
[36]
offshoreWIND.biz2021-10-01◆ Siemens Gamesa Receives Firm Order for T…
Press report — cited, not quoted; read it at the source link.
supportsModel
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.