Sunrise Wind
Located ~48 km east of Montauk Point, Long Island NY. 84 monopiles fabricated at Sif/Smulders Netherlands.
Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
Ørsted — 100% ◆Location
Northwest Atlantic
Technology
Capacity
924 MW ◆
Turbines
84 × 11 MW ◆
Model
Siemens Gamesa SG 11-0-200 DD ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
BOEM Lease Sale 2 · 2013 ·
Water depth
31–38 m ≈
Distance from shore
48 km ◆
Revenue & grid
Offtake
OREC · NY4-ORECRFP23-1 · $146/MWh ◆
Grid
No agreement ◆
Connection
HVDC to Holbrook onshore substation, Long Island (PSEG Long … ◆
Schedule
FID
Mar 2024 ◆
COD · announced
2027-H2 ◆
COD · Hafrok
2027 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2027
expected year of commercial operation
Chance of delivery
≈97%
estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a market with a thinner delivery record, its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
| Year | Probability |
|---|---|
| 2027 (expected) | 86.7% |
| 2028 | 13.3% |
| Stated | Announced COD |
|---|---|
| 2019-07-18 | 2024 |
| 2022-09-12 | 2025 |
| 2024-03-26 | 2026 (held since 2024-02-29, 2 statements) |
| 2026-05 | 2027-H2 (held since 2025-Q1, 3 statements) |
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in
2024. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2027; the faster quarter of similar projects would be done by 2026, the slower quarter not until 2027 Q3.3
Result
Expected commercial operation
2027, likely range 2026–2028 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈97%, which rates it
Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2013-07
BOEM Lease Sale 2
- Awarded to
- Deepwater Wind New England, LLC
- Zone
- OCS-A 0486 + OCS-A 0487 (RI/MA WEA, North + South)
- Lease
- OCS-A 0486 + OCS-A 0487
- Basis
- seabed award
From the auction results — the round that created the project.
JV formation · 2019-02
Ørsted · Eversource stake not disclosed
- Stake
- not disclosed
- Consideration
- not disclosed
- Announced
- 2019-02
- Closed
- 2019-Q2
- Project stage
- early development
Ørsted and Eversource had established a broader 50/50 strategic partnership in US offshore wind since 2016 via Bay State Wind LLC (a joint JV covering multiple New England BOEM lease areas). In February 2019, alongside the South Fork / Revolution Wind farmdown, Ørsted disclosed the Bay State Wind partnership as the vehicle for the Sunrise Wind project (OCS-A 0487, located offshore New York). The Sunrise Wind JV was formally established as a 50/50 partnership between Ørsted and Eversource, developed from the Bay State Wind / Deepwater Wind lease area OCS-A 0487. No standalone consideration was paid; the partnership structure was an extension of the pre-existing Bay State Wind 50/50 collaboration. Eversource had been a JV partner with Ørsted in Bay State Wind prior to 2019. Sunrise Wind was later rebid and awarded in the New York State NY4 offshore wind solicitation (February 2024). FID taken March 2024.
Evidence
- orsted.com — Ørsted divests 50% of South Fork, Revolution Wind and two New England offshore wind lease areas to Eversource ↗ 2019-02 ◆ held
- offshorewind.biz ↗
From Hafrok’s transactions record
Secondary trade · 2023-05
Eversource → Ørsted 50%
- Stake
- 50%
- Consideration
- €581m
- Announced
- 2023-05
- Closed
- 2023-09
- Project stage
- early development
NOT A SUNRISE WIND PROJECT EQUITY TRANSACTION — covers uncontracted seabed and infrastructure only. Recorded under Sunrise Wind as the nearest FK match (same Ørsted-Eversource partnership). As the first stage of Eversource's full exit from US offshore wind, Ørsted acquired Eversource's 50% share of the uncontracted Bay State Wind lease area (OCS-A 0500, ~187,000 acres, ~4 GW potential) plus key operational assets (port partnerships at Providence, Davisville/Quonset Point RI, New London CT; an O&M hub in East Setauket NY; and charter of the first US-built offshore wind SOV). Total consideration: USD 625 million. Announced May 25, 2023; closed September 7, 2023. This transaction covered uncontracted seabed and supporting operational infrastructure — it did NOT include the contracted Sunrise Wind project stake, which was handled in a separate subsequent transaction (see next record). Eversource also agreed to contribute its tax equity member interest in South Fork Wind (approximately USD 545 million) as part of the broader arrangement. USD 625m × 0.93 (2023 rate) = EUR 581m. Note: Sunrise Wind FID was taken subsequently (March 2024) by both companies before Eversource's 50% project stake sale closed.
Evidence
- us.orsted.com — Ørsted to Acquire Eversource Share of Uncontracted Offshore Wind Seabed and Key Northeast Operational Assets ↗ 2023-05 ◆ held
- us.orsted.com — Ørsted Completes Acquisition of Eversource’s Share of Uncontracted Offshore Wind Seabed and Key Northeast Operational Assets ↗ 2023-05 ◆ held
- offshoreWIND.biz — Eversource Sells Seabed Acreage Offshore US to JV Partner Ørsted for USD 625 Million ↗ 2023-05 ◆ held
From Hafrok’s transactions record
Divestment · 2024-04
Eversource → Ørsted 50%
- Stake
- 50%
- Consideration
- €141m
- Implied 100% value
- €283m
- Implied
- €0.31m / MW
- Announced
- 2024-04
- Closed
- 2024-07
- Project stage
- FID
Eversource agreed in January 2024 to sell its 50% interest in the Sunrise Wind project (924 MW, OCS-A 0487, offshore New York) to Ørsted, with the definitive agreement executed April 19, 2024. The transaction closed July 10, 2024, making Ørsted 100% owner of Sunrise Wind. FID was taken in March 2024 (before the definitive agreement); stage at close is therefore fid. The announced consideration was USD 230 million (gross proceeds, subject to spending adjustments); actual closing consideration was USD 152 million, reduced from USD 230 million due to lower actual versus forecast capex between signing and closing. At USD/EUR 0.93 (2024 rate): announced EUR 214 million; actual EUR 141 million. Implied 100% project equity value at closing: USD 304 million = EUR 283 million. Implied EUR/MW = EUR 283m / 924 MW × 1,000,000 = EUR 306,000/MW. This is well below the fid typical range (EUR 700k–2,300k/MW), reflecting a DISTRESSED EXIT — Eversource's distressed exit (recording a USD 520 million total loss on its US OW portfolio) and political/regulatory uncertainty under the Trump administration. Sunrise Wind FID was taken by Ørsted and Eversource jointly in March 2024 (shortly before Eversource's exit), so the project was transitioning from pre-FID to FID at the time of announcement.
Evidence
- businesswire.com — Eversource Energy Announces Execution of Definitive Agreement with Ørsted to Sell Sunrise Wind ↗ 2024-04 ◆ held
- orsted.com — Ørsted closes acquisition of Eversource’s share of Sunrise Wind ↗ 2024-04 ◆ held
- offshoreWIND.biz — Ørsted Becomes Sole Owner of 924 MW Sunrise Wind in US for USD 152 Million ↗ 2024-04 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +3.2 yr (first announced 2024) · the full guidance history is in the delivery chart above
Revenue & offtake contract duration and price levels · money of the day
1,848 MW contracted — OREC
● OREC · NYSERDA Offshore Wind Solicitation 1 (ORECRFP18-1) terminated
Price$83.36/MWh ·Capacity924 MWAwardedOct 2019● OREC · NYSERDA Fourth (Expedited) Offshore Wind Solicitation (2024)
Price$150.15/MWh ·Capacity924 MWAwardedFeb 2024Installation how the build is going · from satellite counts and Hafrok’s registers
Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations10 of 84≈12% · first seen 2025-07-24
Turbines1 of 84≈1% · first seen 2026-04-26
Latest count2026-08-19from 69 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (84 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
Installation contracts
TurbinesWind Scylla◇Cadeler · turbine installation vessel · 2026-04 → · UnderwaySatellite image
Image taken2026-08-19≈Copernicus Sentinel-1 radar satellite, northbound pass · 8 newer passes skipped because the satellite’s track only caught part of the farm (the best of them 90%)
Farm covered100%≈the whole farm lies inside the image
Structures ringed11 confirmed · 0 not yet confirmed≈as counted on 2026-08-19
Construction ports
PortState Pier ◆turbines
PortPort of Coeymans ◆assembly
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-08-19
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (11)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary

Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationSunrise Wind Offshore Converter Station (OCS-DC)·under construction · owner Sunrise Wind, LLC (Ørsted)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
13/17 fields verified · rests on 23 sources (23 primary) · ◆ 17 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[12]
Bureau of Ocean Energy Management (BOEM)2024-06◆ Sunrise Wind | Bureau of Ocean Energy Ma…
“Lease Number OCS-A 0487. Capacity 924 megawatts. Up to 84 wind turbine generators. Located approximately 16.4 nautical miles south of Martha's Vineyard, MA; approximately 26.5 nautical miles east of M…”
supportsConsentTurbinesTotal capacityConsent granted
[30]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0487: companies ['Sunrise Wind, LLC']; lease_dates ['10/01/2013']; lease_terms ['25 Years']; states ['New York', 'Rhode Island / Massachusetts']; block_count 163.”
supportsRegister entry
Operator13
[1]
Ørsted A/S2024-03◆ Sunrise Wind receives federal record of …
“Sunrise Wind today received its Record of Decision (RoD) from the US Department of the Interior's Bureau of Ocean Energy Management (BOEM), crossing a critical milestone in the federal environmental r…”
supportsFinal investment decisionTotal capacityDistance from shore
[2]
Ørsted A/S2024-06◆ Sunrise Wind receives final approval fro…
“Sunrise Wind, New York's largest offshore wind project, has received approval of its construction and operations plan (COP) from the US Department of the Interior's Bureau of Ocean Energy Management (…”
supportsConsentTotal capacityConsent granted
[3]
Ørsted A/S2024-02◆ Sunrise Wind selected for award in New Y…
“New York's energy agency, NYSERDA, has conditionally awarded Ørsted and Eversource's Sunrise Wind project the right to negotiate a 25-year offshore wind renewable energy certificate (OREC) agreement f…”
supportsTotal capacity
[4]
Ørsted A/S2024-01◆ Ørsted to acquire full ownership of Sunr…
“Ørsted has signed an agreement with Eversource to acquire Eversource's 50 % share of Sunrise Wind, a 924 MW offshore wind farm which would deliver power to New York. The acquisition is subject to the …”
supportsTotal capacity
[5]
Ørsted A/S2025-12◆ Revolution Wind and Sunrise Wind receive…
“On 22 December 2025, Revolution Wind LLC, a 50/50 joint venture with Global Infrastructure Partners' Skyborn Renewables, and Sunrise Wind LLC, a fully-owned subsidiary, received orders from the U.S. D…”
supportsBackground
[6]
Ørsted A/S2026-01◆ Sunrise Wind LLC to file Preliminary Inj…
“Today, Sunrise Wind LLC ("Sunrise Wind"), a wholly owned subsidiary of Ørsted, will file a complaint in the U.S. District Court for the District of Columbia, challenging the lease suspension order iss…”
supportsTurbinesFoundationStatusConnection point
[7]
Ørsted A/S2026-02◆ Ørsted Annual Report 2025
“Sunrise Wind is ~45 % complete, with more than half of the foundations installed, and commissioning is planned for H2 2027. Commercial operation date: H2 2027. Resumed offshore activities following gr…”
supportsBackground
[8]
Ørsted A/S2025-02◆ Ørsted Annual Report 2024
“We took final investment decisions for the offshore wind farm Sunrise Wind (924 MW). In July, we completed the acquisition of Eversource's 50 % interest in Sunrise Wind, which was owned jointly by Ørs…”
supportsoperatorTotal capacity
[9]
Ørsted A/S2026-05◆ Ørsted IR presentation Q1 2026
“Sunrise Wind. Location US. Capacity 924 MW. Offtake contract: Nominal offtake with state of New York. Commercial operation date H2 2027. Degree of completion ~47 %, up from 45 % in January 2026. The p…”
supportsCommercial operationCOD historyTotal capacity
[10]
Ørsted A/S2026-05◆ Ørsted Q1 2026 earnings call transcript
“Turning now to slide 9 and an update on the progress at Sunrise Wind. During the quarter, the project has continued to make progress and achieved an important milestone as the first turbines have succ…”
supportsTurbines
[11]
Ørsted A/S (via energy-pedia.com)2024-07
“Further to our announcement from 24 January 2024 and following the successful award of Sunrise Wind in the New York 4 solicitation, Ørsted today closes the acquisition of Eversource's 50 % share of Su…”
supportsMechanismStrike / priceDetail
[14]
Connecticut Port Authority2024
“Sunrise Wind is already scheduled to be delivered from the completed State Pier Terminal facility. The facility is used for staging and assembly of offshore wind turbines for multiple projects includi…”
supportsturbines
[27]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
"Commercial operation date H2 2027" ... "Degree of completion ~50 %, up from 47 % in Q1 2026" ... "The project continues work towards commissioning of first turbines later this year and commercial op…
supportsBackground
OEM1
[13]
EVWIND (reporting Siemens Gamesa press release)2022-09
“Siemens Gamesa confirmed a firm order to supply 84 SG 11.0-200 DD offshore wind turbines for the 924 MW Sunrise Wind offshore wind project developed by Ørsted and Eversource off Montauk Point, New Yor…”
supportsTurbinesModelUnit capacity
Auction results2
[31]
New York PSC2026-06-22◆ us-nyserda-sol1-2019-nypsc-repricing
NY PSC denies OREC inflation-adjustment petitions (Oct 2023): the contracts had no reopener
supportsOREC · NYSERDA Offshore Wind Solicitation 1 (ORECRFP18-1)
[32]
NY Dept of Public Service2018◆ us-ny-psc-order-18e0071
NY PSC Order, Case 18-E-0071 - establishes the Offshore Wind Standard and the OREC mechanism.
supportsOREC · NYSERDA Fourth (Expedited) Offshore Wind Solicitation (2024)
Record source1
[33]
offshore-energy.biz / offshoreWIND.biz2026-04-17◆ oe-sunrise-first-turbine-2026-04
Press report — cited, not quoted; read it at the source link.
supportsWind Scylla — turbine installation
Trade press4
[15]
Offshore Wind (offshorewind.biz)2024-09
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionassembly
[16]
[17]
[19]
Ørsted2025-05-07◆ Orsted — interim financial report q1 202…
“our Sunrise Wind project, offshore installation commenced in Q1 2025 and the degree of completion is now at approx. 35 %.”
supportsOnshore constructionOffshore construction