Ocean Wind 2
Planned 1,148 MW follow-on to Ocean Wind 1, also off New Jersey coast.
Technology
Capacity
1,148 MW ◆
Turbines
—
Foundation
—
Site & conditions
Site rights
Seabed rights held Seabed lease · Bureau of Ocean Energy Management (BOEM) · 2016-03 ◆
Water depth
15–35 m ≈
Wind speed
9.6 m/s @ 150 m ≈
Revenue & grid
Offtake
OREC cancelled ◆
Grid
—
Schedule
COD
—
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
5/12 fields verified · rests on 7 sources (3 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[9]
Bureau of Ocean Energy Management (BOEM)2024◆ Ocean Wind 2 (OCS-A 0532) - BOEM project…
“Ocean Wind 2 has not submitted a Construction and Operations (COP) for BOEM review.”
supportsConsentSite rights
Operator2
[4]
[5]
Ørsted2021◆ Ørsted awarded 1,148 MW offshore wind co…
“Subject to contract signing and Ørsted's final investment decision, Ocean Wind 2 is expected to be commissioned in 2029.”
supportsTotal capacityMechanismDetail
Trade press3
[6]
[7]
[8]
Unverified import1
[1]
