New England Wind 2

Lease area OCS-A 0534 (same lease as NEW 1, different phase). Located ~50 km south of Cape Cod. Will use same Salem Harbor port as NEW 1.

Status
Early Developmentlifecycle stage
FragileHafrok completion outlook
Ownership
AVAvangrid Renewables — 100% 
Location
United States
Northwest Atlantic
Technology
Capacity 1,259 MW 
Turbines
Foundation Monopile 
Site & conditions
Site rights Seabed rights held Seabed lease · Bureau of Ocean Energy Management (BOEM) · 2015-04  Water depth 49–59 m  Wind speed 10.2 m/s @ 150 m 
Revenue & grid
Offtake Other terminated 
Grid
Schedule
FID Not taken
COD · announced 2031 
COD · Hafrok 2037 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2037
expected year of commercial operation
The developer says 2031; Hafrok expects 2037 — 6 years later.
Chance of delivery
≈28% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: a market with a thinner delivery record, its size and technical complexity. A secured offtake contract helps only slightly. That figure is then halved while Hafrok reads the United States route as closed: a route that has to be won again is less likely to be won.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2036: 14.1% (conditional on completion) 2037: 28.0% (conditional on completion) 2038: 22.7% (conditional on completion) 2039: 14.6% (conditional on completion) 2040: 8.7% (conditional on completion) 2041: 5.1% (conditional on completion) 2042: 3.1% (conditional on completion) 2043: 1.8% (conditional on completion) 2044: 1.1% (conditional on completion) 2045: 0.7% (conditional on completion)2026now202820302031203220342036203728%EXPECTED2038204020422044 Developer-announced COD: 2031 ANNOUNCED 2031
COD probability by year, conditional on completion
YearProbability
203614.1%
2037 (expected)28.0%
203822.7%
203914.6%
20408.7%
20415.1%
20423.1%
20431.8%
20441.1%
20450.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in developing offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Route closed until 2029
Hafrok believes no approval that opens a route to build is likely to be issued in the United States before a new administration takes office, which cannot happen before January 2029. On that reading the clock for this project starts in 2029, not today: what it holds is kept, but Hafrok does not expect the process that turns it into a consent to begin before then. This is Hafrok's judgment, not a fact on the record — what it rests on: United States market page.
3
Earliest credible date
Typical consent-to-operation time plus allowances, counted from 2029, means commercial operation before 2037 is not credible.
4
Still needs an offtake award: US-NY-SOLICITATION-6
The project has no offtake contract yet. The next visible auction is pencilled for 2027 Q3, but on Hafrok's reading no round can award a route to build before 2029, so it is counted from then; winners typically reach final investment decision about 2 years after an award (2031), then build time on top gives 2034. The milestone timing is already later than that, so it stands.
5
Result
Expected commercial operation 2037, likely range 2037–2042 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
6
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
7
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — and halve the result while Hafrok reads the United States route as closed (a route that has to be won again is less likely to be won) — to ≈28%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2027’28’29’30’31’32’33’34’35’36’37Developer-announced COD: 2031 announced COD 2031Commercial operation 2037 ·Hafrok expectedNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDCIP → Avangrid — 50.0% · closed 2022-01 2021-09 ACQUISITIONTODAYCIP CIP CIP exited 2021-09Avangrid Renewables — 100% today · operator Avangrid Avangrid 100%CIP → Avangrid — 50.0% · closed 2022-01 50%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open

Utility PPA · Massachusetts Section 83C Round 3 awarded 2021-12, terminated. No live offtake on record.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
NYSERDA Offshore Wind Solicitation 6 (NY6)
expected 2027 · planned · the round’s published documents do not name this project
design/RFI stage only; no timetable, conditioned on the federal market improving

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2031

Sources & verification

2/11 fields verified · rests on 12 sources (2 primary) · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[9]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0561: companies ['Commonwealth Wind LLC']; lease_dates ['05/15/2024']; lease_terms ['25 Years']; states ['Massachusetts']; block_count 127.”
supportsRegister entry
[10]
Bureau of Ocean Energy Management (BOEM)2026◆ New England Wind 1 and 2 — BOEM state ac…
“Through a competitive leasing process (30 CFR 585.211), BOEM awarded Lease OCS-A 0501 to Vineyard Wind, LLC on April 1, 2015. [...] On May 15, 2024, the New England Wind project was segregated into tw…”
supportsSite rights
Auction results1
[11]
MA DOER / EDCs2021◆ us-ma-83c-r3
Massachusetts 83C Round 3 RFP - Commonwealth Wind (Avangrid terminated 2023).
supportsOfftake history
Auction pipeline1
[12]
Offshore Wind (offshorewind.biz)2026-02◆ ny-ny5-ended-2026
Press report — cited, not quoted; read it at the source link.
supportsNYSERDA Offshore Wind Solicitation 6 (NY6)
Trade press7
[2]
offshoreWIND.biz2024-04
Press report — cited, not quoted; read it at the source link.
supportsoperator
[3]
Global Energy Monitor2026
supportsTotal capacity
[4]
PNNL Tethys2024
supportsFoundation
[5]
Global Energy Monitor2026-07-02
supportsCoordinates
[6]
GEBCO Compilation Group2020
supportsWater depth
[7]
Utility Dive
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetail
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsConsentCommercial operationTotal capacityFoundationWater depth+1 more