Kitty Hawk South
Status
Early Developmentlifecycle stage
FragileHafrok completion outlook
Ownership
AVAvangrid — 100% ◇
Location
Northwest Atlantic
Technology
Capacity
2,400 MW ◇
Turbines
—
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Origination
BOEM Lease Sale 7 · 2017 ·
Water depth
32–42 m ≈
Wind speed
9.6 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Not taken
COD · Hafrok
2037 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2037
expected year of commercial operation
Chance of delivery
≈26%
estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: a market with a thinner delivery record, a very large build and technical complexity. A secured offtake contract helps only slightly. That figure is then halved while Hafrok reads the United States route as closed: a route that has to be won again is less likely to be won.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2036 | 14.1% |
| 2037 (expected) | 28.0% |
| 2038 | 22.7% |
| 2039 | 14.6% |
| 2040 | 8.7% |
| 2041 | 5.1% |
| 2042 | 3.1% |
| 2043 | 1.8% |
| 2044 | 1.1% |
| 2045 | 0.7% |
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (
2026), adds the time similar projects (in developing offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.2
Route closed until 2029
Hafrok believes no approval that opens a route to build is likely to be issued in the United States before a new administration takes office, which cannot happen before
January 2029. On that reading the clock for this project starts in 2029, not today: what it holds is kept, but Hafrok does not expect the process that turns it into a consent to begin before then. This is Hafrok's judgment, not a fact on the record — what it rests on: United States market page.3
Earliest credible date
Typical consent-to-operation time plus allowances, counted from
2029, means commercial operation before 2037 is not credible.4
Still needs an offtake award: US-NY-SOLICITATION-6
The project has no offtake contract yet. The next visible auction is pencilled for
2027 Q3, but on Hafrok's reading no round can award a route to build before 2029, so it is counted from then; winners typically reach final investment decision about 2 years after an award (2031), then build time on top gives 2034. The milestone timing is already later than that, so it stands.5
Result
Expected commercial operation
2037, likely range 2037–2042 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.6
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
7
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — and halve the result while Hafrok reads the United States route as closed (a route that has to be won again is less likely to be won) — to ≈26%, which rates it
Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2017-03
BOEM Lease Sale 7
- Awarded to
- Avangrid Renewables, LLC
- Zone
- OCS-A 0508 (Kitty Hawk WEA)
- Lease
- OCS-A 0508
- Basis
- seabed award
From the auction results — the round that created the project.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake route to market — open
No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
NYSERDA Offshore Wind Solicitation 6 (NY6) ◇
design/RFI stage only; no timetable, conditioned on the federal market improving
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
0/9 fields verified · rests on 6 sources (1 primary) · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
[5]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0508: companies ['Kitty Hawk Wind, LLC']; lease_dates ['11/01/2017']; lease_terms ['25 Years']; states ['North Carolina']; block_count 104.”
supportsRegister entry
Auction pipeline1
[6]
Offshore Wind (offshorewind.biz)2026-02◆ ny-ny5-ended-2026
Press report — cited, not quoted; read it at the source link.
supportsNYSERDA Offshore Wind Solicitation 6 (NY6)
Trade press3
[2]
[3]
[4]