Thanet

Located 12km off Foreness Point, Kent. Round 2 development.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2004’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 2 — awarded to VattenfallCrown Estate Round 2 Dec 2003 · auction recordView the source for Consent grantedConsent granted Dec 2006 View the source for Onshore constructionOnshore construction 2008 View the source for Offshore constructionOffshore construction 2008 View the source for First powerFirst power 16 May 2010 View the source for Commercial operationCommercial operation 2010-Q3 Crown Estate Round 2 — awarded to Vattenfall 2003-12 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDChristofferson Robb & Co → Vattenfall — 100% · €43m 2008-11 ACQUISITIONTODAYVattenfall — 100% today · operator Vattenfall Vattenfall 100%Christofferson Robb & Co Christofferson Robb & Co Christofferson Robb & Co exited 2008-11Crown Estate Round 2 — awarded to Vattenfall Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Christofferson Robb & Co → Vattenfall — 100% · €43m 100%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2010-Q32010-Q3 · 2 recorded revisions · held (announced 2010-Q3, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime: ROC 2.0 ROCs/MWh (Renewables Obligation banded support)
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing99100 turbines + 1 platform expected · 2 fewer than expected — a position the survey missed
Surveyed2026-09-01from 64 satellite passes
Built2008 → 2010-Q3offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed99 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Ramsgate O&M base
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (99)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Thanet, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationThanet Offshore Substation Platform (OSP)·132/33/33 kV · in service 2010 · owner Thanet OFTO Limited (Balfour Beatty 20% / Equitix 80%); assets built by Thanet Offshore Wind Limited (Vattenfall)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20102011201220132014201520162017201820192020202120222023202420252026developer’s stated start 2010-Q3nowThanet Offshore Substation Platform (OSP)Thanet Offshore Substation Platfo…in service 2010in service 2010

Sources & verification

17/18 fields verified · rests on 9 sources (10 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[2]
Ofgem2014-12-17◆ Ofgem grants licence for Thanet offshore…
"Thanet Offshore Wind Farm Limited is 100% owned by Vattenfall." ... "It is located approximately 12 km off Foreness Point - the most eastern part of Kent - and comprises 100 Vestas V90 3MW wind turbi…
supportsoperatorStatusConnection point
[9]
UK Government (legislation.gov.uk)2010-03-30◆ The Renewables Obligation (Amendment) Or…
“Inserted article 30A applies to offshore wind generating stations using relevant wind turbines: "the amount of electricity to be stated in each ROC issued in respect of that electricity is 0.5 megawat…”
supportsMechanismDetail
[11]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2499: Site Name "Thanet", Development Status "Operational", Installed Capacity 300 MWelec, Operator "Vattenfall"”
supportsRegister entry
Operator2
[1]
Vattenfall AB2025◆ Power plants: Thanet - Vattenfall
“Located about 12 kilometres off Foreness Point, the easternmost part of Kent. 300 MWe. 100 turbines supplied by Vestas. Water depths of 20–25 metres. Status: In Operation. 100 %. Construction was comp…”
supportsTurbinesUnit capacityTotal capacityWater depthDistance from shore+1 more
[12]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000212: "Thanet Offshore Wind Farm", Status "Built", MW Connected 300, Effective From n/a, Customer "THANET OFFSHORE WIND LIMITED"”
supportsRegister entry
Trade press4
[3]
Power Technology (GlobalData)2024◆ Thanet Offshore Wind Farm, Kent
Press report — cited, not quoted; read it at the source link.
supportsConsentFirst powerTurbinesModelUnit capacity+2 more
[4]
Pacific Northwest National Laboratory (Tethys)2025-07-28◆ Thanet Offshore Wind Farm | Tethys
"Construction start: January 1, 2008. COD: September 23, 2010. Turbine model: Vestas V90. Foundation type: Monopile. Hub height: 70 m. Rotor diameter: 90 m. Turbine count: 100. Capacity per turbine: 3…
supportsOnshore constructionOffshore constructionCommercial operationCOD historyTurbines+6 more
[7]
Power Magazine2011
“Two submarine power cables connect to an existing onshore substation in Richborough, Kent. A local maintenance facility was built in the Port of Ramsgate. Turbines: 100 x Vestas V90, 3 MW each, 300 MW…”
supportsO&M base
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed