Hornsea Two

Located 89km off Yorkshire coast. 1320 MW grid connection capacity (165 x 8 MW turbines).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures)Crown Estate Round 3 Jan 2010 · auction recordView the source for Final investment decisionFinal investment decision 2017 View the sources for Onshore constructionOnshore construction Apr 2018 View the sources for Offshore constructionOffshore construction Oct 2020 View the source for First powerFirst power 2021-Q4 View the source for Commercial operationCommercial operation 2022-Q3 Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDØrsted → AXA IM Alts / Credit Agricole Assurances — 50% · €1,815m · closed 2023-06 2022-03 FARMDOWNØrsted → Brookfield — 12.45% · closed 2024-12 2024-10 PORTFOLIOTODAYSMart Wind (Mainstream Renewable Power + Siemens Project Ventures) SMart Wind SMart Wind not among today’s recorded owners — no sale recordedØrsted — 37.55% today · operator Ørsted Ørsted 37.55%AXA IM Alts — 25% today AXA IM Alts AXA IM Alts 25%Credit Agricole Assurances — 25% today Credit Agricole Assuran… Credit Agricole Assuran… 25%Brookfield — 12.45% today Brookfield Brookfield 12.45%Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Ørsted → AXA IM Alts / Credit Agricole Assurances — 50% · €1,815m · closed 2023-06 Ørsted → AXA IM Alts / Credit Agricole Assurances — 50% · €1,815m · closed 2023-06 50% → consortiumØrsted → Brookfield — 12.45% · closed 2024-12 12.45%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2023202220222022-08-31 · 4 recorded revisions · pulled forward -0.8 yr (first announced 2023)

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
CfD · AR2
Price£57.5/MWh ·
Basis2012 real · CPI-indexed
Capacity1,386 MWAwardedSep 2017
Term15 yrs · delivery 2022/23
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR2
255075100nowCfD · AR2 — £57.5/MWh · 2012 real · CPI-indexedCfD · AR2 — £57.5/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR2 term · 15 yrs20172020202320262029203220352038CfD · AR2 — £57.5/MWh · 2012 real · CPI-indexed — 61.9 at award84.7 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations165 of 165100% · first seen 2018-07-10 · 14 more than the record expects — a met mast, a platform not on the register, or a survey artefact
Turbines163 of 16599% · first seen 2018-07-10
Latest count2023-12-30from 924 satellite passes · 2 substation platforms left out so the counts compare with the turbine number · the count has ended: the build is complete
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (165 turbines + 2 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
50100150167 planned (turbines and platforms)latest count 2023-12-30foundations — running total, confirmedAug 2019 — 4 this month · 14 in totalSep 2019 — 5 this month · 19 in totalOct 2020 — 9 this month · 28 in totalNov 2020 — 9 this month · 37 in totalDec 2020 — 9 this month · 46 in totalJan 2021 — 10 this month · 56 in totalFeb 2021 — 7 this month · 63 in totalMar 2021 — 16 this month · 79 in totalApr 2021 — 7 this month · 86 in totalMay 2021 — 10 this month · 96 in totalJun 2021 — 18 this month · 114 in totalJul 2021 — 20 this month · 134 in totalAug 2021 — 21 this month · 155 in totalSep 2021 — 16 this month · 171 in totalOct 2021 — 9 this month · 180 in totalNov 2021 — 0 this month · 180 in totalDec 2021 — 1 this month · 181 in totalJan 2022 — 0 this month · 181 in totalFeb 2022 — 0 this month · 181 in totalMar 2022 — 0 this month · 181 in totalApr 2022 — 0 this month · 181 in totalMay 2022 — 0 this month · 181 in totalAug 2022 — 0 this month · 181 in totalApr 2023 — 0 this month · 181 in totalMay 2023 — 0 this month · 181 in totalAug 2023 — 0 this month · 181 in totalturbines up — running total, confirmedAug 2019 — 0 this month · 1 in totalSep 2019 — 0 this month · 1 in totalOct 2020 — 0 this month · 1 in totalNov 2020 — 0 this month · 1 in totalDec 2020 — 0 this month · 1 in totalJan 2021 — 0 this month · 1 in totalFeb 2021 — 0 this month · 1 in totalMar 2021 — 0 this month · 1 in totalApr 2021 — 2 this month · 3 in totalMay 2021 — 5 this month · 8 in totalJun 2021 — 19 this month · 27 in totalJul 2021 — 18 this month · 45 in totalAug 2021 — 12 this month · 57 in totalSep 2021 — 23 this month · 80 in totalOct 2021 — 17 this month · 97 in totalNov 2021 — 17 this month · 114 in totalDec 2021 — 28 this month · 142 in totalJan 2022 — 10 this month · 152 in totalFeb 2022 — 2 this month · 154 in totalMar 2022 — 4 this month · 158 in totalApr 2022 — 1 this month · 159 in totalMay 2022 — 1 this month · 160 in totalAug 2022 — 2 this month · 162 in totalApr 2023 — 1 this month · 163 in totalMay 2023 — 1 this month · 164 in totalAug 2023 — 1 this month · 165 in total181 foundations165 turbines upAug 2019Nov 2020Feb 2021May 2021Aug 2021Nov 2021Feb 2022May 2022May 2023Sleipnir · Offshore substation
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed181 confirmed · 0 not yet confirmedas counted on 2023-12-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (181)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Hornsea Two, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationHornsea Two offshore substation (OSS)·66/220 kV · owner Diamond Transmission Partners Hornsea Two (OFTO); built by Ørsted
Offshore substationHornsea Two Reactive Compensation Station·owner Diamond Transmission Partners Hornsea Two (OFTO); built by Ørsted

Sources & verification

16/17 fields verified · rests on 12 sources (9 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[2]
UK Department for Business, Energy & Industrial Strategy / National Grid2017-09-11◆ CfD Allocation Round 2 results
“Hornsea Project 2 Breesea Limited Offshore Wind 1,3 86.00 57.50 2022/23 2 1,440,300 England ... 2 Hornsea will be built in three phases; 2022/23 is the delivery year for phase 1”
supportsMechanismDetail
[14]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2502: Site Name "Hornsea 2 - Optimus and Breesea", Development Status "Operational", Installed Capacity 1320 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
Operator3
[1]
Ørsted (Decommissioning Programme filed under the Energy Act 2004)◆ Hornsea Project Two Offshore Wind Farm D…
"Onshore construction works commenced in April 2018, works in the intertidal area commenced in April 2019, and offshore construction is due to commence in 2020 with commissioning in 2022." ... Hornsea…
supportsConsentOnshore constructionOffshore constructionTurbinesModel+7 more
[3]
Ørsted2022-08-31◆ Hornsea 2, the world’s largest windfarm,…
“Ørsted is proud to announce that the world's largest installed windfarm, Hornsea 2, is now fully operational.”
supportsCommercial operationCOD historyTotal capacity
[15]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000333: "Hornsea Power Station 2A", Status "Built", MW Connected 440, Effective From n/a, Customer "BREESEA LIMITED"; PRO-000334: "Hornsea Power Station 2…”
supportsRegister entry
Auction results1
[16]
BEIS (gov.uk)2017-09◆ cfd-ar2-results-2017
Triton Knoll Offshore Wind Farm — Offshore Wind 860.00 MW, GBP 74.75, 2021/22; Hornsea Project 2 (Breesea Limited) — 1,386.00 MW, GBP 57.50, 2022/23; Moray Offshore Windfarm (East) — 950.00 MW, GBP 57…
supportsCfD · AR2
Record source1
[17]
offshore-energy.biz / offshoreWIND.biz2021-10-27◆ oe-hornsea-two-substations-2021-10
Press report — cited, not quoted; read it at the source link.
supportsSleipnir — substation installation
Trade press5
[4]
CNBC2021-12-21◆ Orsted: Milestone for wind farm expected…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
offshoreWIND.biz2024-10
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[9]
offshoreWIND.biz2017-09-11
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[10]
offshoreWIND.biz2020-10-09
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed