Hornsea 4

Part of the Hornsea Zone, East of England. Seabed lease agreed with The Crown Estate March 2016 as part of Round 3 reconfiguration.

Status
On Holdlifecycle stage
FragileHafrok completion outlook
Ownership
Ørsted — 100% 
Location
United Kingdom
North Sea
Technology
Capacity 2,400 MW 
Turbines
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Crown Estate Round 3 · 2010 ·
Water depth 29–52 m  Distance from shore 90 km  Wind speed 10.5 m/s @ 150 m 
Revenue & grid
Offtake CfD · AR6 · £58.87/MWh terminated  Grid Secured  Connection Creyke Beck 400kV substation (connection agreement retained … 
Schedule
FID Not taken
COD · Hafrok

Delivery outlook modelled by Hafrok · calibrated on delivered projects

on hold — no credible date; the chart shows when a restarted project might complete
Chance of delivery
≈16% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a very large build and technical complexity pull a little the other way. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034 developer cod guidance2024-09 → 2024-10: the developer guided 2030 in 2 statements — sources [3] [12] — click for the sources2024-102030 · held since 2024-09 (×2) [3,12]
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2024-102030 (held since 2024-09-03, 2 statements)
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈16%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures)Crown Estate Round 3 Jan 2010 · auction recordView the source for Consent grantedConsent granted 12 Jul 2023 Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYSMart Wind (Mainstream Renewable Power + Siemens Project Ventures) SMart Wind SMart Wind not among today’s recorded owners — no sale recordedØrsted — 100% today · operator Ørsted Ørsted 100%Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2030, unchanged) · the full guidance history is in the delivery chart above

Revenue & offtake route to market — open

No offtake secured — route to market open

CfD · AR6 awarded 2024-09, terminated. No live offtake on record.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
CfD allocation round
The UK's principal route — a 15-year, CPI-indexed, two-sided CfD awarded in annual competitive rounds.
Next visible round · from the auction calendar
CfD Allocation Round 8
expected H2 2026 · scheduled · the round’s published documents do not name this project
AR8 confirmed (gov update, Mar 2026) to OPEN July 2026 — brought forward from the earlier mid/late-2026 expectation
Corporate PPA
Bilateral long-term offtake with corporate buyers; can cover part of output alongside or ahead of a CfD.
Merchant
Uncontracted sale into the wholesale market — no price floor, full exposure to power prices.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operationnot stated
Construction ports
PortHumber ports
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemHornsea 4 HVDC·2400 MW · ±320 kV · cancelled
Export & onshore
Onshore connectionCreyke Beck Extension (Wanlass Beck)·400 kV · planning
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2026nowHornsea 4 HVDCHornsea 4 HVDCCreyke Beck Extension (Wanlass Beck)Creyke Beck Extension (Wanlass Be…

Sources & verification

9/14 fields verified · rests on 16 sources (14 primary) · ◆ 13 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator4
[1]
Planning Inspectorate2023-07-12◆ Hornsea Project Four Offshore Wind Farm …
“Hornsea Project Four Offshore Wind Farm, reference EN010098. Application granted on 12 July 2023 by the Secretary of State for Energy Security and Net Zero. Applicant: Orsted Hornsea Project Four Limi…”
supportsConsentDistance from shoreConsent granted
[13]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2473: Site Name "Hornsea 4", Development Status "Awaiting Construction", Installed Capacity 2600 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
[17]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 2473: Site Name "Hornsea 4", Development Status "Planning Permission Granted", Installed Capacity 2400 MWelec, Operator "Orsted (formerly Dong Energy)", Record …”
supportsRegister entry
[18]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010098: "Hornsea Project Four Offshore Wind Farm"; applicant "Orsted Hornsea Project Four Limited"; Stage "Post-decision"; anticipated submission Q2 2020; applied 2021-09-29; accep…”
supportsRegister entry
Operator7
[2]
Ørsted A/S2025-05-07◆ Orsted to discontinue the Hornsea 4 offs…
“Orsted has today decided to discontinue the Hornsea 4 project in the UK in its current form. Since the Contract for Difference (CfD) award in allocation round 6 (AR6) in September 2024, the 2,400 MW H…”
supportsTotal capacityStatusConnection pointport
[3]
Ørsted A/S2024-09-03◆ Ørsted’s Hornsea 3 and Hornsea 4 awarded…
"The UK Department for Energy Security and Net Zero (DESNZ) has awarded Orsted contracts for difference (CfD) for a 1,080 MW share of the Hornsea 3 Offshore Wind Farm, as well as a 2,400 MW CfD for Ho…
supportsMechanismStrike / priceDetail
[4]
Ørsted A/S2026-02◆ Ørsted Annual Report 2025
“Hornsea 4 remains in the pipeline, as we continue to hold seabed rights, a grid connection agreement, and a development consent order. [...] In Q2 2025, we decided to discontinue our offshore wind pro…”
supportsBackground
[6]
Ørsted A/S2026-05-06◆ Ørsted Q1 2026 earnings call transcript
“We have moved Hornsea 4 back into development. We are moving that forward well and according to plan and we will be able to participate with that project should we decide to do so from AR9 and onwards…”
supportsBackground
[8]
Ørsted2025-05◆ Orsted to discontinue the Hornsea 4 offs…
supportsoperator
[12]
Ørsted A/S2024-10◆ Web Hornsea 4 Newsletter Oct 2024
“I am delighted to confirm that Hornsea 4 offshore wind farm has been awarded a 2,400 MW contract for difference (CfD). This is a major milestone for the project and we are now focused on moving toward…”
supportsCOD history
[14]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000435-1: "Hornsea Power Station 4", Status "Scoping", MW Connected 0, Effective From 2028-10-30, Customer "ORSTED HORNSEA PROJECT FOUR LIMITED"; PRO-0004…”
supportsRegister entry
Auction results1
[19]
DESNZ (gov.uk)2024-09◆ cfd-ar6-results-2024
New offshore wind (Pot 3) GBP 58.87, 2028/29: Hornsea Project Four 2,400.00 MW; East Anglia Two Phase 1 963.07 MW. Offshore Wind Permitted Reduction GBP 54.23, 2027/28: Inch Cape A 177.41 / B 88.70 MW…
supportsOfftake history
Auction pipeline1
[20]
DESNZ (gov.uk)2026◆ govuk-cfd-ar8
gov.uk AR8 collection — Allocation Framework, statutory framework and CIB documents published ahead of the round.
supportsCfD Allocation Round 8
Trade press3
[9]
4C Offshore (TGS)2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[10]
GEBCO Compilation Group2020
supportsWater depth
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed