Hornsea 3

Will be world's single largest offshore wind farm. Part of Hornsea Zone cluster with total ~8GW potential.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2028
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a very large build and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
COD probability by year, conditional on completion
YearProbability
2028 (expected)86.7%
202913.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2023-12-202027 (held since 2022-07-07, 2 statements)
2024-09-032028
2025-03-312027
2025-11-052027-H2
2026-05-062028-Q1
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2028; the faster quarter of similar projects would be done by 2027, the slower quarter not until 2029.
3
Result
Expected commercial operation 2028, likely range 2027–2029 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26’27’28Developer-announced COD: 2028-Q1 announced COD 2028-Q1Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures)Crown Estate Round 3 Jan 2010 · auction recordView the source for Consent grantedConsent granted 31 Dec 2020 View the source for Final investment decisionFinal investment decision Dec 2023 View the source for Offshore constructionOffshore construction May 2026 Commercial operation 2028 ·Hafrok expectedCrown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDØrsted → Apollo Global Management — 50.0% · €5,224m · closed 2025-12 2025-11 FARMDOWNTODAYSMart Wind (Mainstream Renewable Power + Siemens Project Ventures) SMart Wind SMart Wind not among today’s recorded owners — no sale recordedØrsted — 50% today · operator Ørsted Ørsted 50%Apollo-led consortium — 50% today Apollo-led consortium Apollo-led consortium 50%Crown Estate Round 3 — awarded to SMart Wind (Mainstream Renewable Power + Siemens Project Ventures) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Ørsted → Apollo Global Management — 50.0% · €5,224m · closed 2025-12 50%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +0.6 yr (first announced 2027) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

CfD-backed — 2 allocation rounds
CfD · AR4
Price£37.35/MWh ·
Basis2012 real · CPI-indexed
Capacity2,852 MWAwardedJul 2022
Term15 yrs · delivery 2026/27
CfD · AR6
Price£54.23/MWh ·
Basis2012 real · CPI-indexed
Capacity1,080 MWAwardedSep 2024
Term15 yrs · delivery 2027/28
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR4CfD · AR6
255075100125nowCfD · AR4 — £37.35/MWh · 2012 real · CPI-indexedCfD · AR4 — £37.35/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexedCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR4 term · 15 yrsCfD · AR6 term · 15 yrs20222025202820312034203720402043CfD · AR4 — £37.35/MWh · 2012 real · CPI-indexed — 47.3 at award55.0 nowCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexed — 75.6 at award79.9 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations46 of 19723% · first seen 2026-03-25 · 24 seen recently, not yet confirmed
Turbinesnone yet0 of 197
Latest count2026-08-30from 187 satellite passes · 2 substation platforms left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (197 turbines + 2 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
50100150199 planned (turbines and platforms)latest count 2026-08-30foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedMar 2026 — 1 this month · 1 in totalApr 2026 — 3 this month · 4 in totalMay 2026 — 7 this month · 11 in totalJun 2026 — 13 this month · 24 in totalJul 2026 — 17 this month · 41 in totalAug 2026 — 7 this month · 48 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedMar 2026 — 0 this month · 0 in totalApr 2026 — 0 this month · 0 in totalMay 2026 — 1 this month · 1 in totalJun 2026 — 1 this month · 2 in totalJul 2026 — 0 this month · 2 in totalAug 2026 — 0 this month · 2 in total48 foundations2 turbines upMar 2026Apr 2026May 2026Jun 2026Jul 2026Aug 2026Wind Ally · FoundationsWind Orca · FoundationsNorse Energi · TurbinesSleipnir · Offshore substation
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered92%a ring on black is a structure this pass could not see, not a mistake
Structures ringed24 confirmed · 24 not yet confirmedas counted on 2026-08-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortTeesworks (Steel River Quay) ·foundations / marshalling · quay 450 m · draft 13.6 m
PortPort of Tyne ·secondary steel · draft 13.5 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (24)seen recently, not yet confirmed (24)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Hornsea 3, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
HVDC systemHornsea 3 Link 1 HVDC·1426 MW · ±320 kV · under construction, expected 2027
HVDC systemHornsea 3 Link 2 HVDC·1426 MW · ±320 kV · under construction, expected 2027
Export & onshore
Export cableHornsea 3 Export Cable·HVDC subsea · 220 km · NKT · under construction · to Norwich, Norfolk
Onshore connectionSwardeston Onshore Converter Station (Hornsea 3)·400 kV · under construction
Converter supplierHitachi Energy·Hornsea 3 Link 1 HVDC · Aibel (Maptaphut, Thailand + Haugesund, Norway) · for National Grid ESO
Converter supplierHitachi Energy·Hornsea 3 Link 2 HVDC · Aibel (Maptaphut, Thailand + Haugesund, Norway) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
202620272028Hafrok expects the farm to start in 2028developer’s stated start 2028-Q1nowHornsea 3 Link 1 HVDCHornsea 3 Link 1 HVDCplatform installed 2026-03platform installed 2026-03expected 2027expected 2027Hornsea 3 Link 2 HVDCHornsea 3 Link 2 HVDCexpected 2027expected 2027Swardeston Onshore Converter Station (Hornsea 3)Swardeston Onshore Converter Stat…expected 2027-Q4expected 2027-Q4Hornsea 3 Export CableHornsea 3 Export Cableexpected 2027expected 2027

Sources & verification

14/17 fields verified · rests on 28 sources (16 primary) · ◆ 20 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator5
[3]
Planning Inspectorate2020-12-31◆ Hornsea Project Three Offshore Wind Farm…
“This application was granted on 31 December 2020. ... Approximately 120km offshore, to the east of Trimingham [Norfolk]. ... Hornsea Project Three Offshore Wind Farm ... This project is at the post-de…”
supportsConsentConsent granted
[6]
GOV.UK (BEIS / Low Carbon Contracts Company)2022-07-07◆ Contracts for Difference (CfD) Allocatio…
“Hornsea Project Three (Ørsted): 2,852 MW awarded an inflation-indexed strike price of £37.35/MWh (2012 prices), delivery year 2026/27 (CfD AR4, awarded 7 July 2022).”
supportsMechanismStrike / priceDetail
[22]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2472: Site Name "Hornsea 3", Development Status "Awaiting Construction", Installed Capacity 2955 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
[30]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 2472: Site Name "Hornsea 3", Development Status "Under Construction", Installed Capacity 2955 MWelec, Operator "Orsted (formerly Dong Energy)", Record Last Upda…”
supportsRegister entry
[31]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010080: "Hornsea Project Three Offshore Wind Farm"; applicant "Orsted Hornsea Project Three (UK) Ltd"; Stage "Post-decision"; anticipated submission May 2018; applied 2018-05-14; a…”
supportsRegister entry
Operator8
[11]
Ørsted2026-02-11◆ First foundations for Orsted Hornsea 3 O…
“First foundations for Ørsted's Hornsea 3 offshore wind farm arrive in the UK.”
supportsWind Ally — foundation installation
[13]
Ørsted2025-07◆ Orsteds Hornsea 3 backs Teesworks Steel …
“Ørsted's Hornsea 3 backs Teesworks' Steel River Quay as first large-scale offshore wind port users [marshalling of monopile foundations].”
supportsfoundations / marshallingsecondary steel
[21]
Ørsted (Interim report, first quarter 2026)2026-05-06◆ Ørsted interim financial report Q1 2026
“Following discussions with National Grid and National Energy System Operator regarding delays to the grid connection date for Hornsea 3, we now anticipate first power for the project in Q1 2027 with C…”
supportsFirst powerCOD history
[23]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000434-1: "Hornsea Power Station 3", Status "Consents Approved", MW Connected 0, Effective From 2026-10-01, Customer "HORNSEA PROJECT THREE (UK) LIMITED";…”
supportsRegister entry
[24]
Ørsted A/S2026-02◆ Orsted — green finance impact report 202…
"Hornsea 3 2,852 UK Under construction 2023-2027 1,881 5,844 - √" ... "Eksfin Hornsea 3 525 5252 2,852 – 127"
supportsTotal capacity
[27]
Ørsted A/S2025-Q3◆ Ørsted Q3 2025 earnings call transcript
“We continue to manage the risks related to the installation of the project, and we remain on track for commissioning in the second half of 2027.”
supportsCommercial operation
[28]
Ørsted A/S2026-05-06◆ Ørsted Q1 2026 earnings call transcript
“For Hornsea 3, we have made significant progress. We have commenced the installation of turbine foundations, pulled the export cable onshore to meet its onshore counterpart and successfully installed …”
supportsStatus note
[29]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
"Commercial operation date Q4 2027 / Q1 2028" ... "Degree of completion ~30 %, up from 25 % in Q1 2026" ... "Of the total 197 positions, the project has installed 43 turbine foundations, and the inst…
supportsBackground
Auction results2
[32]
BEIS (gov.uk)2022-07◆ cfd-ar4-results-2022
Offshore Wind (Pot 3) cleared GBP 37.35, delivery 2026/27: Inch Cape Phase 1 1,080.00 MW; EA3 Phase 1 1,372.34 MW; Norfolk Boreas Phase 1 1,396.00 MW; Hornsea Project Three 2,852.00 MW; Moray West 294…
supportsCfD · AR4
[33]
DESNZ (gov.uk)2024-09◆ cfd-ar6-results-2024
New offshore wind (Pot 3) GBP 58.87, 2028/29: Hornsea Project Four 2,400.00 MW; East Anglia Two Phase 1 963.07 MW. Offshore Wind Permitted Reduction GBP 54.23, 2027/28: Inch Cape A 177.41 / B 88.70 MW…
supportsCfD · AR6
Record source4
[34]
Cadeler A/S2026-06-14◆ cadeler-installs-first-complete-monopile
...e scopes across vessels and project partners. The monopile itself was installed by Cadeler’s purpose-built A-class vessel, Wind Ally, while Wind Orca executed the installation of secondary steel. T…
supportsWind Orca — foundation installation
[35]
offshore-energy.biz / offshoreWIND.biz2026-05-14◆ oe-norse-energi-windanker-hornsea3-2026-…
Press report — cited, not quoted; read it at the source link.
supportsNorse Energi — turbine installation
[36]
Cadeler A/S2023-04-25◆ cadeler-orsted-two-contracts-2023-04
The second contract is for the installation of around half of the Wind Turbine Generators (WTGs) required. The turbine project is forecast to begin just as the foundations project is completed around …
supportsVessel — turbine installation
[37]
Heerema2026-03-24◆ heerema-hfg-hornsea-3-first-jacket-2026-…
This first jacket, Link 01, stands 54 meters tall and will support one of the project's Offshore Converter Stations (OCS)... Link 01 was loaded out on Wednesday, 11 March, and was towed to the SSCV Sl…
supportsSleipnir — substation installation
Trade press9
[1]
offshoreWIND.biz2023-12-21
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionUnit capacityTotal capacity
[2]
offshoreWIND.biz2026-05-14
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionTurbinesModelFoundationDistance from shore
[8]
Windtech International2025-12-30
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection point
[14]
offshoreWIND.biz2025-09-26
Press report — cited, not quoted; read it at the source link.
supportsfoundations / marshallingsecondary steel
[15]
offshoreWIND.biz2025-12◆ Apollo Becomes Co-Owner of Hornsea 3 Off…
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[16]
Windpower Monthly2026-05-06
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[17]
Vozpopuli2026-05-25
“Orsted says National Grid has informed it of a delay tied to works at the Norwich Main substation, shifting expectations to first power in Q1 2027 and commissioning across Q4 2027 into Q1 2028. Projec…”
supportsCommercial operation
[18]
GEBCO Compilation Group2020
supportsWater depth
[19]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed