East Anglia THREE

Part of the East Anglia Hub, a 3+ GW multi-project complex off the Suffolk coast developed by ScottishPower Renewables (Iberdrola).

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2026: 86.7% (conditional on completion) 2027: 13.3% (conditional on completion)2026now87%2027 Developer-announced COD: 2026 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2026developer cod guidance2023-06 → 2025-10: the developer guided 2026 in 3 statements — sources [15] [5] [16] — click for the sources2025-102026 · held since 2023-06 (×3) [15,5,16]2026-06 → 2026-08: the developer guided 2026-12 in 2 statements — sources [19] [20] — click for the sources2026-082026-12 · held since 2026-06 (×2) [19,20]
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2025-10-272026 (held since 2023-06-30, 3 statements)
2026-08-172026-12 (held since 2026-06-30, 2 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2022. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2024; the faster quarter of similar projects would be done by 2023, the slower quarter not until 2025. Dates already in the past are moved up to today — this project has run beyond the typical timing.
3
Result
Expected commercial operation 2026, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Developer-announced COD: 2026-12 announced COD Dec 2026Crown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall)Crown Estate Round 3 Jan 2010 · auction recordView the source for Consent grantedConsent granted 7 Aug 2017 View the source for Onshore constructionOnshore construction Aug 2022 View the source for Offshore constructionOffshore construction Apr 2025 Commercial operation 2026 ·Hafrok expectedCrown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDScottishPower Renewables (Iberdrola) → Masdar — 50% · closed 2025-07 2023-12 FARMDOWNTODAYEast Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) East Anglia Offshore Wi… East Anglia Offshore Wi… not among today’s recorded owners — no sale recordedScottishPower Renewables — 50% today · operator ScottishPower Renewables ScottishPower Renewables 50%Masdar — 50% today Masdar Masdar 50%Crown Estate Round 3 — awarded to East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. ScottishPower Renewables (Iberdrola) → Masdar — 50% · closed 2025-07 50%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +0.5 yr (first announced 2026) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

CfD-backed — 2 allocation rounds
CfD · AR4
Price£37.35/MWh ·
Basis2012 real · CPI-indexed
Capacity1,372.34 MWAwardedJul 2022
Term15 yrs · delivery 2026/27
CfD · AR6
Price£54.23/MWh ·
Basis2012 real · CPI-indexed
Capacity158.9 MWAwardedSep 2024
Term15 yrs · delivery 2027/28
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR4CfD · AR6
255075100125nowCfD · AR4 — £37.35/MWh · 2012 real · CPI-indexedCfD · AR4 — £37.35/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexedCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR4 term · 15 yrsCfD · AR6 term · 15 yrs20222025202820312034203720402043CfD · AR4 — £37.35/MWh · 2012 real · CPI-indexed — 47.3 at award55.0 nowCfD · AR6 — £54.23/MWh · 2012 real · CPI-indexed — 75.6 at award79.9 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations95 of 95100% · first seen 2025-04-20 · 14 seen recently, not yet confirmed
Turbines58 of 9561% · first seen 2025-10-14
Latest count2026-08-30from 370 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (95 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
2040608096 planned (turbines and platforms)latest count 2026-08-30foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedApr 2025 — 2 this month · 2 in totalMay 2025 — 3 this month · 5 in totalJun 2025 — 5 this month · 10 in totalJul 2025 — 6 this month · 16 in totalAug 2025 — 1 this month · 17 in totalSep 2025 — 6 this month · 23 in totalOct 2025 — 6 this month · 29 in totalNov 2025 — 4 this month · 33 in totalDec 2025 — 5 this month · 38 in totalJan 2026 — 5 this month · 43 in totalFeb 2026 — 9 this month · 52 in totalMar 2026 — 1 this month · 53 in totalApr 2026 — 8 this month · 61 in totalMay 2026 — 7 this month · 68 in totalJun 2026 — 11 this month · 79 in totalJul 2026 — 13 this month · 92 in totalAug 2026 — 4 this month · 96 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedApr 2025 — 0 this month · 0 in totalMay 2025 — 0 this month · 0 in totalJun 2025 — 0 this month · 0 in totalJul 2025 — 0 this month · 0 in totalAug 2025 — 0 this month · 0 in totalSep 2025 — 0 this month · 0 in totalOct 2025 — 1 this month · 1 in totalNov 2025 — 0 this month · 1 in totalDec 2025 — 0 this month · 1 in totalJan 2026 — 0 this month · 1 in totalFeb 2026 — 1 this month · 2 in totalMar 2026 — 1 this month · 3 in totalApr 2026 — 3 this month · 6 in totalMay 2026 — 19 this month · 25 in totalJun 2026 — 13 this month · 38 in totalJul 2026 — 10 this month · 48 in totalAug 2026 — 11 this month · 59 in total96 foundations59 turbines upApr 2025Jun 2025Aug 2025Oct 2025Dec 2025Feb 2026Apr 2026Jun 2026Aug 2026Seaway Ventus · FoundationsWind Osprey · TurbinesWind Pace · Turbines
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed82 confirmed · 14 not yet confirmedas counted on 2026-08-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortLowestoft (ABP Eastern Energy Facility) operations maintenance
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (82)seen recently, not yet confirmed (14)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over East Anglia THREE, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemEast Anglia THREE HVDC·1400 MW · ±320 kV · under construction, expected 2026
Export & onshore
Export cableEast Anglia THREE Export Cable·HVDC subsea · 380 km · NKT · under construction · to Bramford, Suffolk
Onshore connectionBramford Converter Station (East Anglia THREE)·400 kV · under construction
Converter supplierSiemens Energy·East Anglia THREE HVDC · Aker Solutions (Stord, Norway) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20252026Hafrok expects the farm to start in 2026developer’s stated start 2026-12nowEast Anglia THREE HVDCEast Anglia THREE HVDCplatform installed 2025-10platform installed 2025-10expected 2026expected 2026Bramford Converter Station (East Anglia THREE)Bramford Converter Station (East …expected 2026expected 2026East Anglia THREE Export CableEast Anglia THREE Export Cableexpected 2026expected 2026

Sources & verification

14/19 fields verified · rests on 19 sources (6 primary) · ◆ 11 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Planning Inspectorate2017-08-07◆ East Anglia THREE Offshore Wind Farm - P…
“East Anglia THREE Offshore Wind Farm (EN010056). The Secretary of State approved the application for consent on 7 August 2017. The development involves an offshore windfarm with an approximate capacit…”
supportsConsentDistance from shoreConsent granted
[4]
BEIS / DESNZ2022-07-07◆ Contracts for Difference Allocation Roun…
“East Anglia Three, 1,372 MW, awarded CfD at a strike price of GBP 37.35/MWh in Allocation Round 4. Results published 7 July 2022.”
supportsMechanismStrike / priceDetailCfD · AR4
[17]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2470: Site Name "East Anglia 3 (EA 3)", Development Status "Under Construction", Installed Capacity 1400 MWelec, Operator "Scottish Power Renewables"”
supportsRegister entry
Operator3
[11]
Masdar2025-07
“Masdar and Iberdrola announced their co-investment in East Anglia THREE this month, with each party taking a 50 percent stake and having co-governance of the 1.4GW asset”
supportsoperatorowner
[18]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000270-1: "East Anglia Three", Status "Consents Approved", MW Connected 0, Effective From 2026-01-31, Customer "EAST ANGLIA THREE LIMITED"; PRO-000270-2: …”
supportsRegister entry
[20]
Masdar2026-08-17◆ Scottishpower renewables and masdar mark…
“ScottishPower Renewables and Abu Dhabi Future Energy Company PJSC – Masdar have completedd a major construction milestone at the £4 billion East Anglia THREE offshore wind farm, with all 95 foundation…”
supportsCOD historySeaway Ventus — foundation installation
OEM1
[3]
Siemens Gamesa Renewable Energy2023-03-29◆ Green energy for more than one million U…
“95 units of Siemens Gamesa's largest offshore wind turbine, the SG 14-236 DD, will be supplied for the East Anglia 3 wind power project. The 1.4 GW wind project is the second of the East Anglia develo…”
supportsTurbinesModelUnit capacityTotal capacity
Auction results1
[21]
DESNZ (gov.uk)2024-09◆ cfd-ar6-results-2024
New offshore wind (Pot 3) GBP 58.87, 2028/29: Hornsea Project Four 2,400.00 MW; East Anglia Two Phase 1 963.07 MW. Offshore Wind Permitted Reduction GBP 54.23, 2027/28: Inch Cape A 177.41 / B 88.70 MW…
supportsCfD · AR6
Record source2
[22]
Cadeler A/S2026-04-21◆ first-turbine-standing-at-east-anglia-th…
...p! Taxation Policy Copyright © Cadeler - All rigths reserved. News, Press Releases First turbine installed at East Anglia THREE 21 Apr 2026 Wind Osprey and team have completed the installation of t…
supportsWind Osprey — turbine installationWind Pace — turbine installation
[23]
reNEWS2025-10-27◆ renews-ea3-hvdc-station-2025-10
Press report — cited, not quoted; read it at the source link.
supportsSleipnir — substation installation
Trade press9
[2]
offshoreWIND.biz2019-06-07
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[5]
offshoreWIND.biz2025-07-10◆ 'Largest Offshore Wind Transaction of De…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[6]
offshoreWIND.biz2022-08-12
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionFoundationStatusConnection point
[7]
offshoreWIND.biz2025-04-25
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelFoundation
[8]
offshoreWIND.biz2025-12-17
Press report — cited, not quoted; read it at the source link.
supportsoperations maintenance
[12]
4C Offshore (TGS)2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[13]
GEBCO Compilation Group2020
supportsWater depth
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[19]
Iberdrola2026-07◆ Iberdrola — report 26H1
“The project remains on-track for commercial operations in December 2026.”
supportsCommercial operation