Dogger Bank C

Final phase of the 3.6 GW Dogger Bank Wind Farm complex.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2028
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2028: 86.7% (conditional on completion) 2029: 13.3% (conditional on completion)2026now2027202887%2029 Developer-announced COD: 2028 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2028developer cod guidance2021-12-02: the developer guided 2026-Q1 — source [4] — click for it2021-122026-Q1 [4]2024-05 → 2025-05: the developer guided 2027 in 3 statements — sources [14] [7] [11] — click for the sources2025-052027 · held since 2024-05 (×3) [14,7,11]2026-05-06: the developer guided 2028 — source [17] — click for it2026-052028 [17]
COD probability by year, conditional on completion
YearProbability
2028 (expected)86.7%
202913.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2021-12-022026-Q1
2025-05-232027 (held since 2024-05-22, 3 statements)
2026-05-062028
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2022. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2024; the faster quarter of similar projects would be done by 2023, the slower quarter not until 2025. Dates already in the past are moved up to today — this project has run beyond the typical timing.
3
Result
Expected commercial operation 2028, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26’27’28Developer-announced COD: 2028 announced COD 2028Crown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft)Crown Estate Round 3 Jan 2010 · auction recordView the source for Consent grantedConsent granted 4 Aug 2015 View the sources for Final investment decisionFinal investment decision Dec 2021 View the source for Onshore constructionOnshore construction 2022 Commercial operation 2028 ·Hafrok expectedCrown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDSSE Renewables / Equinor → Eni — 20% · €164m · closed 2022-02 2021-11 JV ENTRYEni Plenitude → Vårgrønn (Plenitude / HitecVision JV) — 20% · closed 2022-10 2022-06 TODAYForewind (SSE, RWE Npower, Statoil, Statkraft) Forewind Forewind not among today’s recorded owners — no sale recordedSSE Renewables — 40% today · operator SSE Renewables SSE Renewables 40%Equinor — 40% today Equinor Equinor 40%Eni Plenitude Eni Eni exited 2022-06Vårgrønn — 20% today Vårgrønn Vårgrønn 20%Crown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed. SSE Renewables / Equinor → Eni — 20% · €164m · closed 2022-02 SSE Renewables / Equinor → Eni — 20% · €164m · closed 2022-02 20% → consortiumEni Plenitude → Vårgrønn (Plenitude / HitecVision JV) — 20% · closed 2022-10 20%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +2.4 yr (first announced 2026-Q1) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
CfD · AR3
Price£41.611/MWh ·
Basis2012 real · CPI-indexed
Capacity1,200 MWAwardedSep 2019
Term15 yrs · delivery 2024/25
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR3
20406080nowCfD · AR3 — £41.611/MWh · 2012 real · CPI-indexedCfD · AR3 — £41.611/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR3 term · 15 yrs20192022202520282031203420372040CfD · AR3 — £41.611/MWh · 2012 real · CPI-indexed — 46.7 at award61.3 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations87 of 87100% · first seen 2025-04-27
Turbines6 of 877% · first seen 2025-05-09
Latest count2026-08-30from 544 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (87 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
2040608088 planned (turbines and platforms)latest count 2026-08-30foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedApr 2025 — 4 this month · 4 in totalMay 2025 — 17 this month · 21 in totalJun 2025 — 20 this month · 41 in totalJul 2025 — 27 this month · 68 in totalAug 2025 — 13 this month · 81 in totalSep 2025 — 7 this month · 88 in totalAug 2026 — 0 this month · 88 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedApr 2025 — 0 this month · 0 in totalMay 2025 — 1 this month · 1 in totalJun 2025 — 2 this month · 3 in totalJul 2025 — 2 this month · 5 in totalAug 2025 — 0 this month · 5 in totalSep 2025 — 2 this month · 7 in totalAug 2026 — 0 this month · 7 in total88 foundations7 turbines upApr 2025May 2025Jun 2025Jul 2025Aug 2025Sep 2025Aug 2026Seaway Strashnov · Foundations
Satellite image
Image taken2026-09-02Copernicus Sentinel-1 radar satellite, northbound pass · 6 newer passes skipped because the satellite’s track only caught part of the farm (the best of them 67%)
Farm covered73%a ring on black is a structure this pass could not see, not a mistake
Structures ringed88 confirmed · 0 not yet confirmedas counted on 2026-08-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortMaraen Port of Nigg turbine marshalling
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-02
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (88)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Dogger Bank C, 2026-09-02
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemDogger Bank C HVDC·1200 MW · ±320 kV · under construction, expected 2026
Export & onshore
Export cableDogger Bank C Export Cable·HVDC subsea · 500 km · NKT · under construction · to Lackenby, Teesside
Onshore connectionLackenby Substation (Dogger Bank C / Sofia connection)·400 kV · under construction · also serves Sofia Offshore Wind Farm
Converter supplierHitachi Energy·Dogger Bank C HVDC · Aibel (Haugesund, Norway) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2025202620272028Hafrok expects the farm to start in 2028developer’s stated start 2028nowDogger Bank C HVDCDogger Bank C HVDCplatform installed 2025-05platform installed 2025-05expected 2026expected 2026Lackenby Substation (Dogger Bank C / Sofia connection)Lackenby Substation (Dogger Bank …expected 2026expected 2026Dogger Bank C Export CableDogger Bank C Export Cableexpected 2026expected 2026

Sources & verification

13/17 fields verified · rests on 16 sources (14 primary) · ◆ 12 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
legislation.gov.uk2015-08-04◆ The Dogger Bank Teesside A and B Offshor…
"Work No. 1A — (a) an offshore wind turbine generating station with a gross electrical output capacity of up to 1.2 gigawatts comprising up to 200 wind turbine generators each fixed to the seabed by m…
supportsConsentTotal capacityFoundationCoordinatesConsent granted
[3]
DESNZ (gov.uk)2019-09-20◆ Contracts for Difference (CfD) Allocatio…
“Doggerbank Teeside A P1 | Doggerbank Offshore WindFarm Project3ProjcoLimited | Offshore Wind | 1200.00 MW | £41.611/MWh | 2024/25”
supportsMechanismStrike / priceDetailCfD · AR3
[15]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2517: Site Name "Dogger Bank C (was Teesside A)", Development Status "Under Construction", Installed Capacity 1200 MWelec, Operator "SSE/Equinor (formerly Stato…”
supportsRegister entry
Operator7
[4]
Dogger Bank Wind Farm (SSE Renewables / Equinor)2021-12-02◆ DOGGER BANK C REACHES FINANCIAL CLOSE - …
“SSE Renewables, together with its joint venture partner Equinor, has reached financial close on Dogger Bank C … first power is anticipated in Q3, 2025 and full power in Q1, 2026. Onshore cable install…”
supportsFinal investment decisionOnshore construction
[5]
Equinor2021-12-02◆ Equinor and partner reach financial clos…
“Reaching financial close on the third phase of Dogger Bank is a significant milestone as it demonstrates that we are on track with developing what will become the world's largest offshore wind farm.”
supportsFinal investment decision
[6]
Dogger Bank Wind Farm2022-10-17◆ Vargronn acquires Plenitude's 20% intere…
“Vårgrønn acquires Plenitude's 20% interest in the world's largest offshore wind farm … SSE Renewables (40 per cent), Equinor (40 per cent) and Vårgrønn (20 per cent).”
supportsoperatorowner
[7]
SSE Renewables2024-12◆ Dogger Bank Wind Farm signs vessel reser…
“When fully complete in 2027, Dogger Bank will be the world's largest offshore wind farm.”
supportsModelSeaway Ventus — turbine installation
[11]
SSE Renewables2025-05-23◆ Dogger Bank Wind Farm and delivery partn…
"Dogger Bank Wind Farm and its delivery partners have completed the installation of the HVDC offshore substation platform for Dogger Bank C, the third and final offshore substation platform across all…
supportsStatusConnection point
[16]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000409: "Dogger Bank Project C", Status "Consents Approved", MW Connected 0, Effective From 2025-04-01, Customer "DOGGERBANK OFFSHORE WIND FARM PROJECT 3 …”
supportsRegister entry
[17]
Equinor2026-05-06◆ Equinor Q1 2026 results call transcript …
"When it comes to Dogger Bank C, the transition pieces those things are ongoing. And we actually, well, no, let me say -- those were actually completed. Those are actually done half a year ago. And we…
supportsCommercial operationCOD history
Record source2
[20]
offshore-energy.biz / offshoreWIND.biz2025-09-03◆ oe-dbc-iac-strashnov-2025-09
Press report — cited, not quoted; read it at the source link.
supportsSeaway Strashnov — foundation installation
[21]
Dogger Bank Wind Farm (SSE Renewables / Equinor / Vargronn)2025-05-23◆ doggerbank-dbc-hvdc-platform-2025-05
Manufactured and supplied by Aibel and installed by Heerema Marine Contractors' Sleipnir vessel, the Dogger Bank C platform measures approximately 75 x 50 metres across and 36 metres high and sits on …
supportsSleipnir — substation installation
Trade press4
[8]
reNEWS2025-11-15
Press report — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[10]
offshoreWIND.biz2026-05-12
Press report — cited, not quoted; read it at the source link.
supportsturbine marshalling
[12]
GEBCO Compilation Group2020
supportsWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed