Dogger Bank A

Phase A of the 3.6 GW Dogger Bank complex (A+B+C) — when complete, the world's largest offshore wind farm.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2020-11-262024
2024-10-032025 (held since 2024-05-22, 2 statements)
2026-05-282026 (held since 2026-02-04, 2 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2020. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2022; the faster quarter of similar projects would be done by 2021, the slower quarter not until 2023. Dates already in the past are moved up to today — this project has run beyond the typical timing.
3
Result
Expected commercial operation 2026, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Developer-announced COD: 2026 announced COD 2026Crown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft)Crown Estate Round 3 Jan 2010 · auction recordView the source for Final investment decisionFinal investment decision 2020 View the source for Onshore constructionOnshore construction 2020 View the source for Offshore constructionOffshore construction Jul 2022 View the source for First powerFirst power 10 Oct 2023 Commercial operation 2026 ·Hafrok expectedCrown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft) 2010-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDSSE Renewables / Equinor → Eni — 20% · €227m · closed 2021-02 2020-12 JV ENTRYEni Plenitude → Vårgrønn (Plenitude / HitecVision JV) — 20% · closed 2022-10 2022-06 TODAYForewind (SSE, RWE Npower, Statoil, Statkraft) Forewind Forewind not among today’s recorded owners — no sale recordedSSE Renewables — 40% today · operator SSE Renewables SSE Renewables 40%Equinor — 40% today Equinor Equinor 40%Eni Plenitude Eni Eni exited 2022-06Vårgrønn — 20% today Vårgrønn Vårgrønn 20%Crown Estate Round 3 — awarded to Forewind (SSE, RWE Npower, Statoil, Statkraft) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed. SSE Renewables / Equinor → Eni — 20% · €227m · closed 2021-02 SSE Renewables / Equinor → Eni — 20% · €227m · closed 2021-02 20% → consortiumEni Plenitude → Vårgrønn (Plenitude / HitecVision JV) — 20% · closed 2022-10 20%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +2.0 yr (first announced 2024) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
CfD · AR3
Price£39.65/MWh ·
Basis2012 real · CPI-indexed
Capacity1,200 MWAwardedSep 2019
Term15 yrs · delivery 2023/24
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR3
20406080nowCfD · AR3 — £39.65/MWh · 2012 real · CPI-indexedCfD · AR3 — £39.65/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR3 term · 15 yrs2019202220252028203120342037CfD · AR3 — £39.65/MWh · 2012 real · CPI-indexed — 44.5 at award58.4 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations95 of 95100% · first seen 2022-08-01 · 1 more than the record expects — a met mast, a platform not on the register, or a survey artefact
Turbines70 of 9574% · first seen 2023-05-14
Latest count2026-08-29from 655 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (95 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
2040608096 planned (turbines and platforms)latest count 2026-08-29foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedSep 2023 — 6 this month · 95 in totalNov 2023 — 0 this month · 95 in totalDec 2023 — 0 this month · 95 in totalJan 2024 — 0 this month · 95 in totalFeb 2024 — 0 this month · 95 in totalMar 2024 — 0 this month · 95 in totalMay 2024 — 0 this month · 95 in totalJun 2024 — 0 this month · 95 in totalJul 2024 — 0 this month · 95 in totalAug 2024 — 0 this month · 95 in totalSep 2024 — 0 this month · 95 in totalOct 2024 — 0 this month · 95 in totalMar 2025 — 0 this month · 95 in totalApr 2025 — 0 this month · 95 in totalMay 2025 — 1 this month · 96 in totalJun 2025 — 0 this month · 96 in totalJul 2025 — 0 this month · 96 in totalAug 2025 — 0 this month · 96 in totalSep 2025 — 1 this month · 97 in totalOct 2025 — 0 this month · 97 in totalFeb 2026 — 0 this month · 97 in totalMar 2026 — 0 this month · 97 in totalApr 2026 — 0 this month · 97 in totalMay 2026 — 0 this month · 97 in totalJun 2026 — 0 this month · 97 in totalAug 2026 — 0 this month · 97 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedSep 2023 — 1 this month · 5 in totalNov 2023 — 1 this month · 6 in totalDec 2023 — 1 this month · 7 in totalJan 2024 — 1 this month · 8 in totalFeb 2024 — 3 this month · 11 in totalMar 2024 — 1 this month · 12 in totalMay 2024 — 2 this month · 14 in totalJun 2024 — 4 this month · 18 in totalJul 2024 — 2 this month · 20 in totalAug 2024 — 3 this month · 23 in totalSep 2024 — 2 this month · 25 in totalOct 2024 — 2 this month · 27 in totalMar 2025 — 1 this month · 28 in totalApr 2025 — 2 this month · 30 in totalMay 2025 — 2 this month · 32 in totalJun 2025 — 4 this month · 36 in totalJul 2025 — 7 this month · 43 in totalAug 2025 — 6 this month · 49 in totalSep 2025 — 4 this month · 53 in totalOct 2025 — 2 this month · 55 in totalFeb 2026 — 2 this month · 57 in totalMar 2026 — 2 this month · 59 in totalApr 2026 — 4 this month · 63 in totalMay 2026 — 3 this month · 66 in totalJun 2026 — 5 this month · 71 in totalAug 2026 — 0 this month · 71 in total97 foundations71 turbines upSep 2023Jan 2024May 2024Aug 2024Mar 2025Jun 2025Sep 2025Mar 2026Jun 2026Voltaire · Turbines
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed97 confirmed · 0 not yet confirmedas counted on 2026-08-29 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (97)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Dogger Bank A, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemDogger Bank A HVDC·1200 MW · ±320 kV · in service 2023-10
Export & onshore
Export cableDogger Bank A Export Cable·HVDC subsea · 207 km · NKT · to Beverley, East Riding of Yorkshire
Converter supplierHitachi Energy·Dogger Bank A HVDC · Aibel (Haugesund, Norway) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2023202420252026Hafrok expects the farm to start in 2026developer’s stated start 2026nowDogger Bank A HVDCDogger Bank A HVDCin service 2023-10in service 2023-10Dogger Bank A Export CableDogger Bank A Export Cableexpected 2025expected 2025

Sources & verification

7/18 fields verified · rests on 16 sources (14 primary) · ◆ 9 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[6]
UK Department for Business, Energy & Industrial Strategy2019-10-11◆ CfD Allocation Round 3 results
“Creyke Beck A P1 (Dogger Bank A) — 1,200 MW at £39.650/MWh (2012 prices).”
supportsMechanismDetail
[7]
UK Statutory Instrument 2015/318 (Planning Inspectorate EN010021)2015-02-17◆ The Dogger Bank Creyke Beck Offshore Win…
“The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 You are here: UK Statutory Instruments 2015 No. 318 ... 3. Development consent, etc. granted by Order”
supportsConsentCoordinates
[19]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2541: Site Name "Dogger Bank A & B (was Creyke Beck A & B)", Development Status "Under Construction", Installed Capacity 2400 MWelec, Operator "SSE/Equinor (for…”
supportsRegister entry
Operator7
[2]
Dogger Bank Wind Farm
supportsStatusConnection pointDistance from shore
[3]
Equinor2023-10-10◆ World’s largest offshore wind farm Dogge…
“Dogger Bank started producing first power on 10 October 2023. ... 10 October 2023 06:00 ( UTC ) ... The first turbine at Dogger Bank A has started turning and producing electricity. Power from the off…”
supportsFirst powerVoltaire — turbine installation
[11]
Equinor2020-11-26◆ Equinor and partner reach financial clos…
“Dogger Bank wind farm owners, Equinor and SSE, have today announced financial close on the first two phases of the project, representing in aggregate the largest offshore wind project financing to dat…”
supportsFinal investment decision
[12]
SSE Renewables2020-01-17◆ Construction commences for Dogger Bank |…
“Construction on the world’s largest offshore wind farm has taken place this week near the coastal village of Ulrome, East Riding of Yorkshire, England. ... Jones Bros Civil Engineering ... has been aw…”
supportsOnshore constructionOffshore construction
[15]
SSE plc2026-05-28
“Following the completion of turbine installation at Dogger Bank A in February 2026, commissioning continues and is expected to be substantially complete by the end of calendar year 2026.”
supportsCommercial operationCOD history
[20]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000411: "Dogger Bank Project A", Status "Built", MW Connected 1200, Effective From n/a, Customer "DOGGERBANK OFFSHORE WIND FARM PROJECT 1 PROJCO LIMITED"”
supportsRegister entry
[21]
SSE plc2026-07-16◆ SSE Renewables — sse plc q1 fy27 trading…
“Commissioning work continues on Dogger Bank A in line with expectations.”
supportsCommercial operation
Auction results1
[23]
BEIS (gov.uk)2019-09◆ cfd-ar3-results-2019
Offshore Wind awards (2012 prices): Doggerbank Creyke Beck A P1 1,200.00 MW, GBP 39.650, 2023/24; Creyke Beck B P1 1,200.00 MW, GBP 41.611, 2024/25; Teeside A P1 1,200.00 MW, GBP 41.611, 2024/25; Sofi…
supportsCfD · AR3
Trade press5
[4]
offshoreWIND.biz2026-02-23
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[5]
offshoreWIND.biz2025-11-27
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacityFoundation
[13]
Dogger Bank Wind Farm2025
“It is a joint venture partnership between SSE Renewables (40%), Equinor (40%) and Vårgrønn (20%).”
supportsoperatorowner
[14]
GEBCO Compilation Group2020
supportsWater depth
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed