Barrow

Round 1 development in the East Irish Sea, approximately 7 km southwest of Walney Island near Barrow-in-Furness, Cumbria.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2001’02’03’04’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 1 — awarded to Centrica / DONG (now Ørsted)Crown Estate Round 1 Apr 2001 · auction recordView the source for Consent grantedConsent granted Mar 2003 View the source for Onshore constructionOnshore construction 2005 View the source for First powerFirst power Mar 2006 View the source for Commercial operationCommercial operation 2006 Crown Estate Round 1 — awarded to Centrica / DONG (now Ørsted) 2001-04 ORIGINATIONCentrica → Ørsted — 50% · €62m 2014-12 ACQUISITIONTODAYCentrica Centrica Centrica exited 2014-12DONG (now Ørsted) DONG DONG exited 2001-04Ørsted — 100% today · operator Ørsted Ørsted 100%Crown Estate Round 1 — awarded to Centrica / DONG (now Ørsted) Centrica → Ørsted — 50% · €62m 50%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake the regime the project was built under

Offtake regime: ROC 1.0 ROCs/MWh
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing3130 turbines + 1 platform expected · every expected structure seen
Surveyed2026-09-01from 120 satellite passes
Built2006offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed31 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortBelfast (Harland and Wolff shipyard) fabrication assembly
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (31)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Barrow, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationBarrow Offshore Substation Platform (OSP)·owner TC Barrow OFTO Limited (Transmission Capital Partners) since the 2011 OFTO licence. BUILT for and originally owned by Barrow Offshore Wind Limited, a 50/50 joint venture between subsidiaries of DONG Energy A/S and Centrica plc; Ørsted took full ownership of BOW in 2014. The party named on the record today is not the builder.
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
200620072008200920102011201220132014201520162017201820192020202120222023202420252026developer’s stated start 2006nowBarrow Offshore Substation Platform (OSP)Barrow Offshore Substation Platfo…platform installed 2006-02platform installed 2006-02

Sources & verification

4/18 fields verified · rests on 11 sources (7 primary) · ◆ 6 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[3]
Ofgem2011-09-27◆ Ofgem E-Serve grants third offshore tran…
“Ofgem E-Serve has today confirmed that TC Barrow OFTO Limited (Transmission Capital Partners) has secured a licence to operate the high voltage link to the 90 MW Barrow offshore wind farm, near Barrow…”
supportsBackground
[9]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2546: Site Name "Barrow", Development Status "Operational", Installed Capacity 90 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
[11]
Ofgem2009-07◆ Barrow Offshore Transmission — Project-S…
supportsStatusConnection point
Operator3
[1]
Ørsted A/S2014-12-19◆ DONG Energy acquires full ownership of t…
“DONG Energy has acquired the remaining 50% ownership interest in the Barrow Offshore Wind Farm from its joint venture partner Centrica plc. The project has a total capacity of 90MW and has been in ful…”
supportsFinal investment decisionTotal capacity
[5]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Barrow Offshore Wind Farm,BARROW OFFSHORE WIND LIMITED,Barrow 132/33kV Offshore Substation,,90,0,90,,Built,Direct Connection,OFTO,Wind Offshore,a1f4L000000EHKVQA4,PRO-000022,”
supportsStatusConnection point
[10]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000022: "Barrow Offshore Wind Farm", Status "Built", MW Connected 90, Effective From n/a, Customer "BARROW OFFSHORE WIND LIMITED"”
supportsRegister entry
Financier1
[2]
European Investment Bank2005-12-20
“Signed €95,286,960.35 on 20 December 2005.”
supportsTotal capacity
Trade press3
[6]
offshoreWIND.biz2024-10
Press report — cited, not quoted; read it at the source link.
supportsoperator
[7]
GEBCO Compilation Group2020
supportsWater depth
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[4]
Wikipedia2026-06-12
"Construction of the wind farm was completed in June 2006 with the first power generated in March 2006." ... planning consent given in March 2003 ... constructed by the consortium between July 2005 an…
supportsConsentOnshore constructionFirst powerCommercial operationTurbines+11 more