Barrow
Round 1 development in the East Irish Sea, approximately 7 km southwest of Walney Island near Barrow-in-Furness, Cumbria.
Technology
Capacity
90 MW ◆
Turbines
30 × 3 MW ◇
Model
Vestas V90 3-0 ◇
Foundation
Monopile ◇
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 1 · 2001 ·
Water depth
14–17 m ≈
Distance from shore
7 km ◇
Wind speed
9.4 m/s @ 100 m ≈
Revenue & grid
Offtake
Other ◇
Grid
Secured · 2006 ◆
Connection
Barrow 132/33kV Offshore Substation — holds TEC agreement … ◆
Schedule
FID
Taken · date not recorded ∴
COD
2006 ◇
Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2001-04
Crown Estate Round 1
- Awarded to
- Centrica / DONG (now Ørsted)
- Basis
- seabed award
From the auction results — the round that created the project.
Acquisition · 2014-12
Centrica → Ørsted 50%
- Stake
- 50%
- Consideration
- €62.0m
- Implied 100% value
- €124m
- Implied
- €1.38m / MW
- Announced
- 2014-12
- Project stage
- operational
DONG Energy (now Ørsted) acquired Centrica's 50% stake in Barrow Offshore Wind Farm for GBP 50m. Converted at GBP/EUR 1.24 (Dec 2014) = EUR 62m. Ørsted became 100% owner. Simultaneously, the existing PPA between Centrica and Barrow was terminated.
Evidence
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake the regime the project was built under
Offtake regime: ROC 1.0 ROCs/MWh
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from satellite counts and Hafrok’s registers
Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing31≈30 turbines + 1 platform expected · every expected structure seen
Surveyed2026-09-01≈from 120 satellite passes
Built2006offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07≈Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%≈the whole farm lies inside the image
Structures ringed31 confirmed · 0 not yet confirmed≈as counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortBelfast (Harland and Wolff shipyard) ◇fabrication assembly
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (31)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary

Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationBarrow Offshore Substation Platform (OSP)·owner TC Barrow OFTO Limited (Transmission Capital Partners) since the 2011 OFTO licence. BUILT for and originally owned by Barrow Offshore Wind Limited, a 50/50 joint venture between subsidiaries of DONG Energy A/S and Centrica plc; Ørsted took full ownership of BOW in 2014. The party named on the record today is not the builder.
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
4/18 fields verified · rests on 11 sources (7 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[3]
Ofgem2011-09-27◆ Ofgem E-Serve grants third offshore tran…
“Ofgem E-Serve has today confirmed that TC Barrow OFTO Limited (Transmission Capital Partners) has secured a licence to operate the high voltage link to the 90 MW Barrow offshore wind farm, near Barrow…”
supportsBackground
[9]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2546: Site Name "Barrow", Development Status "Operational", Installed Capacity 90 MWelec, Operator "Orsted (formerly Dong Energy)"”
supportsRegister entry
[11]
Operator3
[1]
Ørsted A/S2014-12-19◆ DONG Energy acquires full ownership of t…
“DONG Energy has acquired the remaining 50% ownership interest in the Barrow Offshore Wind Farm from its joint venture partner Centrica plc. The project has a total capacity of 90MW and has been in ful…”
supportsFinal investment decisionTotal capacity
[5]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Barrow Offshore Wind Farm,BARROW OFFSHORE WIND LIMITED,Barrow 132/33kV Offshore Substation,,90,0,90,,Built,Direct Connection,OFTO,Wind Offshore,a1f4L000000EHKVQA4,PRO-000022,”
supportsStatusConnection point
[10]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000022: "Barrow Offshore Wind Farm", Status "Built", MW Connected 90, Effective From n/a, Customer "BARROW OFFSHORE WIND LIMITED"”
supportsRegister entry
Financier1
[2]
European Investment Bank2005-12-20
“Signed €95,286,960.35 on 20 December 2005.”
supportsTotal capacity
Trade press3
[6]
offshoreWIND.biz2024-10
Press report — cited, not quoted; read it at the source link.
supportsoperator
[7]
[8]
Encyclopaedic1
[4]
Wikipedia2026-06-12
"Construction of the wind farm was completed in June 2006 with the first power generated in March 2006." ... planning consent given in March 2003 ... constructed by the consortium between July 2005 an…
supportsConsentOnshore constructionFirst powerCommercial operationTurbines+11 more