Greater Changhua 4

Located ~55 km off Changhua County, Taiwan Strait. Uses SG 14-236 DD turbines. Annual generation ~3.3 TWh.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2026: 86.7% (conditional on completion) 2027: 13.3% (conditional on completion)20252026now87%2027 Developer-announced COD: 2026 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2026developer cod guidance2025-Q1: the developer guided 2025-H2 — source [12] — click for it2025-Q12025-H2 [12]2025-11-05: the developer guided 2026-H1 — source [15] — click for it2025-112026-H1 [15]2026-01 → 2026-05: the developer guided 2026-Q3 in 2 statements — sources [11] [14] — click for the sources2026-052026-Q3 · held since 2026-01 (×2) [11,14]
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2025-Q12025-H2
2025-11-052026-H1
2026-05-072026-Q3 (held since 2026-01, 2 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2025. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2027; the faster quarter of similar projects would be done by 2026, the slower quarter not until 2028.
3
Result
Expected commercial operation 2026, likely range 2026–2028 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2023’24’25’26Developer-announced COD: 2026-Q3 announced COD 2026-Q3View the sources for Final investment decisionFinal investment decision 31 Mar 2023 View the source for Onshore constructionOnshore construction Apr 2023 View the source for Offshore constructionOffshore construction Feb 2025 View the source for First powerFirst power Jul 2025 Commercial operation 2026 ·Hafrok expectedNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDØrsted → Cathay Life Insurance — 50.0% · €1,554m · closed 2024-12 2023-10 FARMDOWNTODAYØrsted — 50% today · operator Ørsted Ørsted 50%Cathay Life Insurance — 50% today Cathay Life Insurance Cathay Life Insurance 50%Ørsted → Cathay Life Insurance — 50.0% · €1,554m · closed 2024-12 50%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2026-H1, unchanged) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

583 MW contracted — feed-in tariff
Feed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Competitive Auction (競標)
Price2.5481 TWD/kWh ·Capacity582.9 MWAwardedJun 2018
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation under way
no satellite count yet: this farm is outside the tracker’s coverage so far
Installation · on record
StageUnder Construction
Offshore constructionstarted 2025-02
Expected start of operation2026-Q3

Sources & verification

7/15 fields verified · rests on 16 sources (6 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator7
[2]
Ørsted2025-02-18◆ Ørsted starts offshore construction of 9…
“Since its final investment decision in March 2023, Ørsted has begun the manufacturing of the key components, completed civil work of the onshore substation, and started mobilising vessels to prepare t…”
supportsOnshore constructionOffshore constructionSite rights
[4]
Ørsted2026-01-20◆ All wind turbines installed at Ørsted’s …
“Since achieving first power in July 2025, the project has been delivering renewable energy to the national grid.”
supportsFirst powerModelUnit capacityStatusConnection point
[9]
Ørsted2023-03-31
“Ørsted has taken the final investment decision (FID) on its 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan with a timeline for completion by the end of 2025. ... Located approximately …”
supportsConsentFinal investment decision
[12]
Ørsted2025-Q1◆ Orsted — orsted investor presentation …
“Capacity 920 MW Offtake contract Fully secured with TSMC through CPPA Commercial operation date H2 2025”
supportsMechanismDetail
[14]
Ørsted A/S2026-05-07◆ Ørsted IR presentation Q1 2026
“Capacity 920 MW Offtake contract Fully secured with TSMC through CPPA Commercial operation date Q3 2026”
supportsCommercial operationCOD history
[16]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
“Borkum Riffgrund 3 Changhua 2b and 4 Revolution Wind Sunrise Wind Baltica 2 Hornsea 3 / BESS Capacity1 913 MW 920 MW 704 MW 924 MW 1,498 MW 2,852 MW / 300 MW COD Q3 2026 Q3 2026 H2 2026 H2 2027 H2 20…”
supportsCommercial operation
[18]
Ørsted Taiwan2026-08-21◆ Statement on a single turbine incident a…
“On 8 August, a wind turbine at the Greater Changhua 4 Wind Farm automatically tripped and ceased operation after its system detected an abnormal condition. Following this, the wind farm team observed …”
supportsStatus note
Auction results1
[19]
Conventus Law2026-06-22◆ tw-auction-2018-tw-2018-bond
Taiwan 2018 grid allocation: Stage-1 NT$4m/MW + Stage-2 NT$2m/MW performance bond; establishment permit before end-2019
supportsFeed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Competitive Auction (競標)
Trade press7
[5]
offshoreWIND.biz2025-12-24
Press report — cited, not quoted; read it at the source link.
supportsoperatorownerTotal capacity
[6]
GEM2026
supportsTotal capacityCoordinates
[7]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsConsentFinal investment decisionFoundation
[8]
GEBCO Compilation Group2020
supportsWater depth
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[11]
Ørsted2026-01◆ Orsted — q4 2025 pre close calls reminde…
“Greater Changhua 4 (583 MW gross, 50 % ownership) with expected commissioning in Q3 2026.”
supportsCommercial operation
[17]
reNEWS2026-08-21
Press report — cited, not quoted; read it at the source link.
supportsStatus note
Unverified import1
[1]
unknown
supportsCommercial operationTotal capacityFoundationWater depthCoordinates