Greater Changhua 2

Greater Changhua 2 (632 MW) combines the former GC2a (295 MW, operational) and GC2b (337 MW, under construction, COD ~Q3 2026 after an export-cable delay) into a single unit under Ørsted's 2025 regrouping. Ørsted owns 100% today; a…

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈97% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. Its size, technical complexity and no offtake contract yet pull this one slightly below that.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2026: 86.7% (conditional on completion) 2027: 13.3% (conditional on completion)20252026now87%2027 Developer-announced COD: 2026 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2026developer cod guidance2025-08-11: the developer guided 2025 — source [9] — click for it2025-082025 [9]2025-11 → 2026-05: the developer guided 2026-Q3 in 2 statements — sources [13] [11] — click for the sources2026-052026-Q3 · held since 2025-11 (×2) [13,11]
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2025-08-112025
2026-05-072026-Q3 (held since 2025-11-05, 2 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2025. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2027; the faster quarter of similar projects would be done by 2026, the slower quarter not until 2028.
3
Result
Expected commercial operation 2026, likely range 2026–2028 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈97%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2018’19’20’21’22’23’24’25’26Developer-announced COD: 2026-Q3 announced COD 2026-Q3View the source for Consent grantedConsent granted Feb 2018 View the source for Final investment decisionFinal investment decision Mar 2023 View the source for Offshore constructionOffshore construction Feb 2025 View the sources for First powerFirst power Apr 2022 Commercial operation 2026 ·Hafrok expectedNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDØrsted → Cathay Life / Cathay Power — 55.0% · €670m 2025-12 FARMDOWNTODAYØrsted — 100% today · operator Ørsted Ørsted 100%Cathay Life Cathay Life Cathay Life exited 2025-12Cathay Power Cathay Power Cathay Power exited 2025-12Ørsted → Cathay Life / Cathay Power — 55.0% · €670m Ørsted → Cathay Life / Cathay Power — 55.0% · €670m 55% → consortium
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +1.1 yr (first announced 2025) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

632 MW contracted — feed-in tariff
Feed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Selection (遴選)
Priceprice undisclosed ·Capacity294.8 MWAwardedApr 2018
Term20 yrs
Feed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Competitive Auction (競標)
Price2.548 TWD/kWh ·Capacity337.1 MWAwardedJun 2018
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation under way
no satellite count yet: this farm is outside the tracker’s coverage so far
Installation · on record
StageUnder Construction
Offshore constructionstarted 2025-02
Expected start of operation2026-Q3

Sources & verification

3/13 fields verified · rests on 15 sources (5 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator5
[9]
Ørsted A/S2025-08-11◆ Orsted — interim financial report q2 202…
“Achieved first power at Greater Changhua 2b and 4 in July. ... Due to a delay in wind turbine blade delivery and a slow start to array cable installation, COD for Greater Changhua 2b is expected by th…”
supportsFirst power
[10]
Ørsted Taiwan2022-04-21◆ Ørsted achieves first power of Greater C…
“announced today (21) the successful delivery of first power of the Greater Changhua 2a Offshore Wind Farm”
supportsFirst power
[11]
Ørsted A/S2026-05-07◆ Ørsted IR presentation Q1 2026
“Capacity 920 MW Offtake contract Fully secured with TSMC through CPPA Commercial operation date Q3 2026”
supportsCommercial operationCOD history
[12]
Ørsted A/S2026-05-06◆ Ørsted Q1 2026 earnings call transcript
“Turning to slide 7 and an update on our Greater Changhua 2b and 4 project in Taiwan. With the progress achieved during the quarter, the degree of completion is now at 80 %, up from 75 % in Q4 '25. The…”
supportsStatus note
[14]
Ørsted2026-Q2◆ Orsted — orsted q2 2026 ir presentation
“3. The project finance proceeds related to Greater Changhua 2 will contribute to the overall proceeds target once the equity farm-down is completed. ... Borkum Riffgrund 3 Changhua 2b and 4 Revolution…”
supportsBackground
Auction results2
[15]
Conventus Law2026-06-22◆ tw-selection-2018-tw-2018-bond
Taiwan 2018 grid allocation: Stage-1 NT$4m/MW + Stage-2 NT$2m/MW performance bond; establishment permit before end-2019
supportsFeed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Selection (遴選)
[16]
Conventus Law2026-06-22◆ tw-auction-2018-tw-2018-bond
Taiwan 2018 grid allocation: Stage-1 NT$4m/MW + Stage-2 NT$2m/MW performance bond; establishment permit before end-2019
supportsFeed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Competitive Auction (競標)
Trade press8
[1]
offshoreWIND.biz2025-12-24
Press report — cited, not quoted; read it at the source link.
supportsoperatorTotal capacity
[2]
The Wind Power2025
Press report — cited, not quoted; read it at the source link.
supportsModelUnit capacityCoordinates
[3]
Offshore Wind2025
Press report — cited, not quoted; read it at the source link.
supportsFoundation
[4]
GEBCO Compilation Group2020
supportsWater depth
[5]
offshoreWIND.biz2018-02-09
Press report — cited, not quoted; read it at the source link.
supportsConsentConsent granted
[6]
Ocean Energy Resources2023-03-31
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[7]
GreentechLead2025-02-18
“Key milestones include the offshore construction launch in February 2025, expected first power in Q3 2025, and full grid connection in 2026.”
supportsOffshore constructionSite rights
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed