CanWind

Status
Cancelledlifecycle stage
Ownership
Northland Power — 100% 
Location
Taiwan
Technology
Capacity 500 MW  Turbines 43 × 14 MW 
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Taiwan Round 3 Zonal Development — Block 3.1 (區塊開發 3-1) · 2022 ·
Revenue & grid
Offtake
Grid
Schedule
COD

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

0/6 fields verified · rests on 2 sources
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press2
[1]
offshoreWIND.biz2022
Press report — cited, not quoted; read it at the source link.
supportsownerTotal capacity
[2]
Power Technology2025
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacity