Vidar

Floating energy park in the northern Skagerrak, ~35 km from the mainland and ~25 km west of Väderöarna, within the Swedish EEZ (price area SE3); 201 km², water depths ~100–330 m so floating foundations throughout.

Status
Advanced Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
Vattenfall — 85% 
ZEZephyr — 15% 
Location
Sweden
Baltic Sea
Technology
Capacity 2,000 MW  Turbines 75  Foundation Floating 
Site & conditions
Site rights Seabed rights held 2026-07  Water depth 100–300 m  Wind speed 9.5 m/s @ 150 m 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · guidance 2035 
COD · Hafrok 2035 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2035
expected year of commercial operation
Chance of delivery
≈59% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. This one sits well below that: a market with a thinner delivery record, a very large build, technical complexity and no offtake contract yet.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2034: 3.9% (conditional on completion) 2035: 50.2% (conditional on completion) 2036: 29.5% (conditional on completion) 2037: 10.6% (conditional on completion) 2038: 3.8% (conditional on completion) 2039: 1.4% (conditional on completion) 2040: 0.6% (conditional on completion)2026now2028203020322034203550%203620382040 Developer-announced COD: 2035 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2035
COD probability by year, conditional on completion
YearProbability
20343.9%
2035 (expected)50.2%
203629.5%
203710.6%
20383.8%
20391.4%
20400.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (floating, in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2032; the faster quarter of similar projects would be done by 2030, the slower quarter not until 2032 Q3.
3
No route to market yet — counted from 2029
The project has no offtake contract yet. No contract, auction or tariff exists in Sweden today that a project without an offtake agreement could win, and none is scheduled. Hafrok believes a first support award there is unlikely before 2029 Q3, and counts from then. This is Hafrok's judgment, not a fact on the record — what it rests on: Sweden market page. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2031 Q3), then build time on top gives 2035 Q3. That is later than the milestone timing, so the auction sets the date.
4
Result
Expected commercial operation 2035, likely range 2034–2037 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈59%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33’34’35Developer-announced COD: 2035 announced COD 2035View the source for Consent grantedConsent granted 16 Jul 2026 Commercial operation 2035 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2035

Sources & verification

7/12 fields verified · rests on 7 sources (2 primary) · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[4]
Vattenfall2022-06-20
“The two wind projects, named Vidar and Poseidon, are located between 25 and 27 kilometers off the Swedish west coast, north of Gothenburg. After the acquisition, Vattenfall's ownership will amount to …”
supportsowner
[6]
Regeringskansliet (Klimat- och näringslivsdepartementet)2026-07-16◆ Nya beslut om havsbaserad vindkraft
"Två nya havsbaserade vindkraftsparker har beviljats tillstånd. Det handlar om Fyrskeppet Offshore i södra Bottenhavet och Vidar i norra Skagerrak. [...] Enligt tillståndet ska vindkraftparkerna vara …
supportsConsentSite rightsTurbinesConsent granted
[7]
Vattenfall2026-09-09◆ Energipark Vidar (project page)
“Regeringen har beslutat att ge tillstånd till den havsbaserade vindkraftsparken Vidar i norra Skagerrak. ... Antal vindkraftverk: Maximalt 75 verk. Totalhöjd: upp till 370 meter. Årlig produktion: Cir…”
supportsCommercial operationTurbinesTotal capacityFoundation
Trade press4
[1]
offshoreWIND.biz2024
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[2]
Global Energy Monitor2026
supportsFoundationCoordinates
[3]
offshoreWIND.biz2022
Press report — cited, not quoted; read it at the source link.
supportsWater depth
[5]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed