Fyrskeppet

Located ~50 km off the Uppsala County coast in the southern Bothnian Sea (permit decision: ~54 km east of Söderhamn).

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2035
expected year of commercial operation
Chance of delivery
≈63% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. This one sits well below that: a market with a thinner delivery record, its size, technical complexity and no offtake contract yet.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2034: 14.1% (conditional on completion) 2035: 28.0% (conditional on completion) 2036: 22.7% (conditional on completion) 2037: 14.6% (conditional on completion) 2038: 8.7% (conditional on completion) 2039: 5.1% (conditional on completion) 2040: 3.1% (conditional on completion) 2041: 1.8% (conditional on completion) 2042: 1.1% (conditional on completion) 2043: 0.7% (conditional on completion)2026now2028203020322034203528%EXPECTED2036203820402042 developer cod guidance2026-04-15: the developer guided 20322026-042032 2026-06-16: the developer guided 2030 — source [2] — click for it2026-062030 [2]
COD probability by year, conditional on completion
YearProbability
203414.1%
2035 (expected)28.0%
203622.7%
203714.6%
20388.7%
20395.1%
20403.1%
20411.8%
20421.1%
20430.7%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-04-152032
2026-06-162030
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
No route to market yet — counted from 2029
The project has no offtake contract yet. No contract, auction or tariff exists in Sweden today that a project without an offtake agreement could win, and none is scheduled. Hafrok believes a first support award there is unlikely before 2029 Q3, and counts from then. This is Hafrok's judgment, not a fact on the record — what it rests on: Sweden market page. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2031 Q3), then build time on top gives 2034 Q3. That is later than the milestone timing, so the auction sets the date.
4
Result
Expected commercial operation 2035, likely range 2033–2035 (the middle half of outcomes for similar projects). The auction step above sets the date: the round has to be won before building can start.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈63%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33’34’35View the source for Consent grantedConsent granted 16 Jul 2026 Commercial operation 2035 ·Hafrok expected
Dashed tick marks today (9 Sep 2026).
Announced COD: pulled forward -2.0 yr (first announced 2032) · the full guidance history is in the delivery chart above

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operationnot stated
Construction ports
PortGävle assembly

Sources & verification

5/15 fields verified · rests on 6 sources (4 primary) · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator5
[1]
Skyborn Renewables2023-07-07◆ Skyborn Submits Permit Application For F…
“Skyborn Sweden has submitted a permit application to the Swedish government for the construction, operation and decommissioning of Fyrskeppet offshore wind farm. Fyrkeppet is located approximately 50 …”
supportsUnit capacityStatusConnection pointDistance from shoreassembly
[2]
Skyborn Renewables2026-06-16
“Fyrskeppet is situated in the Bothnian Sea, approximately 50 km off the coast in Uppsala county … capacity of 2,800 MW, utilizing a maximum of 215 wind turbines … anticipated commercial operation date…”
supportsCOD historyWater depthDistance from shoreCoordinates
[5]
Skyborn Renewables2023-07◆ Skyborn Submits Permit Application For F…
supportsoperator
[7]
Regeringskansliet (Klimat- och näringslivsdepartementet)2026-07-16◆ Nya beslut om havsbaserad vindkraft
"Två nya havsbaserade vindkraftsparker har beviljats tillstånd. Det handlar om Fyrskeppet Offshore i södra Bottenhavet och Vidar i norra Skagerrak. [...] Enligt tillståndet ska vindkraftparkerna vara …
supportsConsentSite rightsTurbinesConsent granted
[8]
Skyborn Renewables2026-07-16◆ Swedish Government Approves Fyrskeppet O…
“Under the conditions outlined in the Government's decision today, the fully developed wind farm is expected to have an installed capacity of approximately 1,400 MW and generate around 5 TWh of renewab…”
supportsTotal capacity
Trade press1
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed