F.E.W. Baltic II

Located approximately 50 km offshore in the Polish part of the Baltic Sea, north of the town of Ustka. Covers an area of approximately 41 km2.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
PGEPGE — 100% 
Location
Poland
Baltic Sea
Technology
Capacity 350 MW  Turbines 25 × 14 MW  Model Siemens Gamesa SG 14-236 DD  Foundation Monopile 
Site & conditions
Site rights Seabed rights held 
Origination Poland offshore CfD Phase 1 (administrative) · 2021 ·
Water depth 30–50 m  Distance from shore 50 km  Wind speed 10.0 m/s @ 150 m 
Revenue & grid
Offtake CfD  Grid Secured · 2021-01  Connection Grid connection agreement with PSE in place (signed January … 
Schedule
FID Not taken
COD · Hafrok 2029 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2029
expected year of commercial operation
Chance of delivery
≈82% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2028: 14.1% (conditional on completion) 2029: 28.0% (conditional on completion) 2030: 22.7% (conditional on completion) 2031: 14.6% (conditional on completion) 2032: 8.7% (conditional on completion) 2033: 5.1% (conditional on completion) 2034: 3.1% (conditional on completion) 2035: 1.8% (conditional on completion) 2036: 1.1% (conditional on completion) 2037: 0.7% (conditional on completion)2026now20272028202928%EXPECTED20302031203220332034203520362037
COD probability by year, conditional on completion
YearProbability
202814.1%
2029 (expected)28.0%
203022.7%
203114.6%
20328.7%
20335.1%
20343.1%
20351.8%
20361.1%
20370.7%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2024. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2029; the faster quarter of similar projects would be done by 2027, the slower quarter not until 2029.
3
Result
Expected commercial operation 2029, likely range 2027–2029 (the middle half of outcomes for similar projects). The typical time from consent is used.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈82%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27’28’29Poland offshore CfD Phase 1 (administrative) — awarded to RWEPoland offshore CfD Phase 1 (administrative) Jun 2021 · auction recordView the source for Consent grantedConsent granted Dec 2024 Commercial operation 2029 ·Hafrok expectedPoland offshore CfD Phase 1 (administrative) — awarded to RWE 2021-06 ORIGINATIONRWE → PGE — 100.0% 2025-11 DIVESTMENTTODAYRWE RWE RWE exited 2025-11PGE — 100% today PGE PGE 100%Poland offshore CfD Phase 1 (administrative) — awarded to RWE RWE → PGE — 100.0% 100%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

350 MW contracted — tender award
Tender award · Poland offshore CfD Phase 1 (administrative)
Price319.6 PLN/MWh ·Capacity350 MWAwardedJun 2021
Term25 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

11/19 fields verified · rests on 11 sources (6 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[7]
European Commission2021-05◆ State aid: Commission approves EUR 22.5 …
“The aid will be granted in the form of a two-way contract-for-difference premium, during 25 years ... The reference price for projects in the first phase will be administratively fixed based on their …”
supportsMechanismDetail
Operator3
[1]
RWE2024-12-03◆ RWE receives building permits for F.E.W.…
“The Voivode of West Pomerania issued two building permits to RWE for its 350 MW F.E.W. Baltic II offshore wind farm in Poland, covering the construction of offshore wind turbines along with inter-arra…”
supportsConsentTotal capacityDistance from shoreConsent granted
[2]
RWE2021-04-08◆ Poland awards Contract for Difference to…
“The Polish Energy Regulatory Office has awarded a Contract for Difference to RWE's 350 MW F.E.W. Baltic II offshore wind development project in the Polish Baltic Sea. The Contract for Difference provi…”
supportsTotal capacityMechanismDetail
[3]
RWE2026-03-10◆ RWE sold its Polish offshore wind develo…
“RWE and PGE have successfully closed the transaction they announced in December. As agreed, PGE has become the sole owner of the F.E.W. Baltic II offshore wind development project in the Polish Baltic…”
supportsowner
OEM1
[8]
Siemens Gamesa Renewable Energy2022-06-27◆ Powering up in Poland: RWE and Siemens G…
“The 350 MW wind farm is intended to utilize 25 of Siemens Gamesa's flagship SG 14-236 DD offshore wind turbines.”
supportsTurbinesModelUnit capacityTotal capacity
Auction results1
[13]
Norton Rose Fulbright2026-06-22◆ pl-phase1-admin-cfd-2021-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 1 (administrative)
Trade press5
[4]
Offshore Energy2021-01-07◆ RWE secures grid connection agreement fo…
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection point
[9]
Offshore Wind Biz2024-12-04◆ RWE Granted Building Permits for Its Fir…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityDistance from shore
[10]
Power Technology (GlobalData)2022-08-31
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelFoundationWater depth
[11]
Global Energy Monitor2026-07-02
supportsCoordinates
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed