Baltic Power

Located off Choczewo/Leba coast. Onshore substation at Choczewo municipality complete and ready for commissioning tests.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a market with a thinner delivery record, its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2026: 86.7% (conditional on completion) 2027: 13.3% (conditional on completion)2026now87%2027 Developer-announced COD: 2026 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2026developer cod guidance2021-06 → 2026-07: the developer guided 2026 in 5 statements — sources [5] [7] [17] [9] [16] — click for the sources2026-072026 · held since 2021-06 (×5) [5,7,17,9,16]
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-07-102026 (held since 2021-06-16, 5 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2023. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2026; the faster quarter of similar projects would be done by 2025, the slower quarter not until 2026 Q3.
3
Result
Expected commercial operation 2026, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26Developer-announced COD: 2026 announced COD 2026Poland offshore CfD Phase 1 (administrative) — awarded to Orlen / Northland PowerPoland offshore CfD Phase 1 (administrative) Jun 2021 · auction recordView the sources for Onshore constructionOnshore construction 2023 View the source for Final investment decisionFinal investment decision Oct 2023 View the sources for Offshore constructionOffshore construction Jan 2025 Commercial operation 2026 ·Hafrok expectedView the sources for First powerFirst power Jul 2026 Poland offshore CfD Phase 1 (administrative) — awarded to Orlen / Northland Power 2021-06 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDPKN Orlen → Northland Power — 49.0% · closed 2021-03 2021-01 JV ENTRYTODAYOrlen — 51% today · operator Orlen Orlen 51%Northland Power — 49% today Northland Power Northland Power 49%PKN Orlen PKN Orlen PKN Orlen exited 2021-01Poland offshore CfD Phase 1 (administrative) — awarded to Orlen / Northland Power Transfer(s) not in Hafrok's record — shown as a gap, never guessed. PKN Orlen → Northland Power — 49.0% · closed 2021-03 49%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2026, unchanged) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

1,197 MW contracted — tender award
Tender award · Poland offshore CfD Phase 1 (administrative)
Price319.6 PLN/MWh ·Capacity1,197 MWAwardedJun 2021
Term25 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations76 of 76100% · first seen 2025-01-28
Turbines76 of 76100% · first seen 2025-03-07
Latest count2026-08-31from 325 satellite passes · 2 substation platforms left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (76 turbines + 2 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
20406078 planned (turbines and platforms)latest count 2026-08-31foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedJan 2025 — 2 this month · 2 in totalFeb 2025 — 1 this month · 3 in totalMar 2025 — 5 this month · 8 in totalApr 2025 — 9 this month · 17 in totalMay 2025 — 8 this month · 25 in totalJun 2025 — 1 this month · 26 in totalJul 2025 — 7 this month · 33 in totalAug 2025 — 11 this month · 44 in totalSep 2025 — 3 this month · 47 in totalOct 2025 — 2 this month · 49 in totalNov 2025 — 3 this month · 52 in totalDec 2025 — 9 this month · 61 in totalJan 2026 — 8 this month · 69 in totalFeb 2026 — 3 this month · 72 in totalApr 2026 — 1 this month · 73 in totalMay 2026 — 2 this month · 75 in totalJun 2026 — 1 this month · 76 in totalJul 2026 — 0 this month · 76 in totalAug 2026 — 2 this month · 78 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedJan 2025 — 0 this month · 0 in totalFeb 2025 — 0 this month · 0 in totalMar 2025 — 3 this month · 3 in totalApr 2025 — 1 this month · 4 in totalMay 2025 — 0 this month · 4 in totalJun 2025 — 0 this month · 4 in totalJul 2025 — 5 this month · 9 in totalAug 2025 — 13 this month · 22 in totalSep 2025 — 4 this month · 26 in totalOct 2025 — 6 this month · 32 in totalNov 2025 — 5 this month · 37 in totalDec 2025 — 4 this month · 41 in totalJan 2026 — 7 this month · 48 in totalFeb 2026 — 4 this month · 52 in totalApr 2026 — 4 this month · 56 in totalMay 2026 — 8 this month · 64 in totalJun 2026 — 7 this month · 71 in totalJul 2026 — 1 this month · 72 in totalAug 2026 — 6 this month · 78 in total78 foundations78 turbines upJan 2025Mar 2025May 2025Jul 2025Sep 2025Nov 2025Jan 2026Apr 2026Jun 2026Aug 2026Svanen · FoundationsMV Lone · FoundationsWind Osprey · TurbinesWind Mover · Turbines
Satellite image
Image taken2026-09-06Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed78 confirmed · 0 not yet confirmedas counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Gdynia ·Component fabrication / marshalling (offshore substation structures) · quay 400 m · draft 15.5 m
PortLeba O&M / installation service base
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-06
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (78)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Baltic Power, 2026-09-06
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationBaltic Power offshore substation (1 of 2)·under construction · owner Baltic Power sp. z o.o. (ORLEN Group 51% / Northland Power 49%)
Offshore substationBaltic Power offshore substation (2 of 2)·under construction · owner Baltic Power sp. z o.o. (ORLEN Group 51% / Northland Power 49%)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20252026Hafrok expects the farm to start in 2026developer’s stated start 2026nowBaltic Power offshore substation (1 of 2)Baltic Power offshore substation …platform installed 2025platform installed 2025Baltic Power offshore substation (2 of 2)Baltic Power offshore substation …platform installed 2025platform installed 2025

Sources & verification

17/19 fields verified · rests on 22 sources (22 primary) · ◆ 11 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator12
[1]
Baltic Power (ORLEN Group / Northland Power)
“Baltic Power's offshore wind farm area of approximately 130 square kilometres will feature 76 wind turbines, each with a generating capacity of 15 MW. ... 23 km to the north of the Polish coastline, o…”
supportsCommercial operationTurbinesUnit capacityTotal capacityDistance from shore
[3]
Baltic Power (ORLEN Group / Northland Power)2024-10-18
“In the Baltic Power offshore wind farm area, the depth of the seabed reaches 30-45 metres ... monopiles ... driven more than 40 metres into the seabed.”
supportsFoundationWater depth
[7]
Northland Power2023-09-19◆ Northland Power Announces Signing of Cre…
“Northland Power Inc. ... 49% ... Orlen S.A. (51%). ... The project's 25-year Euro-pegged and inflation-indexed Contract for Difference ... Full commercial operations are expected in the latter half of…”
supportsCommercial operationMechanismStrike / priceDetail
[8]
ORLEN (Grupa ORLEN)2023-10-12
Press report — cited, not quoted; read it at the source link.
supportsConsentFinal investment decision
[9]
ORLEN (Grupa ORLEN)2026-02-18◆ All foundations installed as Baltic Powe…
“The installation of all 78 foundations, called monopiles, has been completed at Poland's first offshore wind farm. ... Transition pieces: 60/78 ... Wind turbines: 30/76 ... Baltic Power is scheduled t…”
supportsCommercial operation
[10]
Baltic Power (ORLEN Group / Northland Power)2025-11-01
“Baltic Power opened Poland's first dedicated offshore wind operations and maintenance service base ... in Łeba ... supporting installation work in a marine area covering over 130 km².”
supportsO&M / installation service base
[11]
Baltic Power (ORLEN Group)2025-02-05
“Manufactured at shipyards in Gdynia and Gdańsk, the steel structures of two offshore substations ... The completed structures were moved onto a barge ... and are now sailing to Aalborg for outfitting.”
supportsComponent fabrication / marshalling (offshore substation structures)
[12]
ORLEN2026-06
supportsoperatorowner
[14]
Baltic Power (ORLEN Group / Northland Power)2025-02-06
“As scheduled, the offshore construction of the first Polish offshore wind farm Baltic Power, a joint venture between Orlen Group and Northland Power, has commenced in January. The first monopiles, the…”
supportsOnshore constructionOffshore construction
[16]
Northland Power2026-07-10◆ Northland's Baltic Power Reaches First P…
“TORONTO, July 10, 2026 (GLOBE NEWSWIRE) — Northland Power Inc. (“Northland” or the “Company”) (TSX: NPI) today announced that Baltic Power – its 1.1-gigawatt offshore wind project, owned 49% by Northl…”
supportsFirst powerCOD history
[23]
Baltic Power2026-07-10◆ Morska farma wiatrowa baltic power po ra…
“na farmie Baltic Power – wspólnym projekcie ORLEN i Northland Power – pierwsze turbiny przeszły wymagane testy i dostarczyły energię z morskiego wiatru do krajowej sieci energetycznej. Odbiór energii …”
supportsFirst power
[25]
Baltic Power2026-06-22◆ Już 50 turbin zainstalowanych na morskie…
“Projekt znajduje się w końcowej fazie realizacji (postęp prac: ponad 80%). Aktualny status: Fundamenty i elementy przejściowe: 78/78 – prace zakończone Turbiny: 50/76 – w trakcie instalacji Morskie ka…”
supportsStatusConnection point
OEM1
[2]
Vestas / windfair2023-09-28
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacity
Auction results1
[28]
Norton Rose Fulbright2026-06-22◆ pl-phase1-admin-cfd-2021-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 1 (administrative)
Record source4
[29]
Van Oord2025-02◆ vanoord-svanen-first-monopile-2025-02
Heavy lift installation vessel Svanen installs first monopile at Baltic Power wind farm | Van Oord
supportsSvanen — foundation installation
[30]
offshore-energy.biz / offshoreWIND.biz2026-03-20◆ oe-baltic-power-all-tps-2026-03
Press report — cited, not quoted; read it at the source link.
supportsMV Lone — foundation installation
[31]
Cadeler A/S2025-07-07◆ cadeler-baltic-power-first-wtg-2025-07
This weekend, Cadeler successfully completed the installation of the very first Vestas 15MW turbine at the Baltic Power Offshore Wind Farm in the Baltic Sea... Over the coming months, Cadeler's Wind O…
supportsWind Osprey — turbine installation
[32]
Cadeler A/S2026-04-10◆ cadeler-wind-mover-first-project-2026-04
Cadeler's newbuild wind installation vessel Wind Mover is installing the very first turbine on her first transportation and installation campaign following her delivery last year. From Port of Ronne i…
supportsWind Mover — turbine installation
Trade press4
[4]
The Wind Power (industry database)
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[5]
Energy Regulatory Office (URE) / offshoreWIND.biz2021-06-16◆ 1.2 GW Baltic Power Offshore Wind Farm S…
Press report — cited, not quoted; read it at the source link.
supportsMechanismStrike / priceDetail
[13]
offshoreWIND.biz2023-05-23
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[15]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed