Sørlige Nordsjø II (Phase 1)

Norway's first commercial-scale offshore wind farm. Eastern part of Sorlige Nordsjo II area. Maximum 1500 MW, minimum 1400 MW.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
Parkwind — 51% 
Ingka Investments — 49% 
Location
Norway
North Sea
Technology
Capacity 1,500 MW 
Turbines
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Sørlige Nordsjø II (phase 1) · 2024 ·
Water depth 59–61 m  Distance from shore 140 km  Wind speed 10.7 m/s @ 150 m 
Revenue & grid
Offtake CfD · 115 NOK_ore_per_kWh  Grid Applied · 2024-10  Connection Statnett substation at Kvinesdal (~200 km HVDC) 
Schedule
FID Not taken
COD · Hafrok 2031 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2031
expected year of commercial operation
Chance of delivery
≈73% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. This one sits below that: a market with a thinner delivery record, a very large build and technical complexity. A secured offtake contract helps only slightly.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 14.1% (conditional on completion) 2031: 28.0% (conditional on completion) 2032: 22.7% (conditional on completion) 2033: 14.6% (conditional on completion) 2034: 8.7% (conditional on completion) 2035: 5.1% (conditional on completion) 2036: 3.1% (conditional on completion) 2037: 1.8% (conditional on completion) 2038: 1.1% (conditional on completion) 2039: 0.7% (conditional on completion)2026now20282030203128%EXPECTED2032203420362038
COD probability by year, conditional on completion
YearProbability
203014.1%
2031 (expected)28.0%
203222.7%
203314.6%
20348.7%
20355.1%
20363.1%
20371.8%
20381.1%
20390.7%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
Result
Expected commercial operation 2031, likely range 2029–2031 (the middle half of outcomes for similar projects). The typical time from consent is used.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈73%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2024’25’26’27’28’29’30’31Sørlige Nordsjø II (phase 1) — awarded to Ventyr SN II AS (Parkwind + Ingka Group)Sørlige Nordsjø II (phase 1) Mar 2024 · auction recordCommercial operation 2031 ·Hafrok expectedSørlige Nordsjø II (phase 1) — awarded to Ventyr SN II AS (Parkwind + Ingka Group) 2024-03 ORIGINATIONTODAYParkwind — 51% today Parkwind Parkwind 51%Ingka Investments — 49% today Ingka Investments Ingka Investments 49%Sørlige Nordsjø II (phase 1) — awarded to Ventyr SN II AS (Parkwind + Ingka Group)
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

1,500 MW contracted — tender award
Tender award · Sørlige Nordsjø II (phase 1)
Price115 NOK_ore/kWh ·Capacity1,500 MWAwardedMar 2024
Term15 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operationnot stated
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemSorlige Nordsjo II HVDC (Offshore)·1500 MW · ±320 kV · planned, expected 2030
HVDC systemSorlige Nordsjo II HVDC (Onshore — Kvinesdal)·1500 MW · ±320 kV · planned, expected 2030
Export & onshore
Export cableSorlige Nordsjo II Export Cable·HVDC subsea · 200 km · planned · to Kvinesdal, southern Norway
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
202620272028202920302031Hafrok expects the farm to start in 2031nowSorlige Nordsjo II HVDC (Offshore)Sorlige Nordsjo II HVDC (Offshore)expected 2030expected 2030Sorlige Nordsjo II HVDC (Onshore — Kvinesdal)Sorlige Nordsjo II HVDC (Onshore …expected 2030expected 2030Sorlige Nordsjo II Export CableSorlige Nordsjo II Export Cableexpected 2030expected 2030

Sources & verification

5/12 fields verified · rests on 12 sources (7 primary) · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[5]
NVE (Norges vassdrags- og energidirektorat)2024-10-15◆ Konsesjonssak - NVE
“VENTYR SN II AS — Utredningsprogram fastsatt [Assessment program established, 15.10.2024]. Capacity: 1,500 MW.”
supportsConsentTotal capacityStatusConnection point
[6]
GCE Ocean Technology2024-03-20
“The installed capacity in the project area is to be a minimum of 1,400 MW and a maximum of 1,500 MW.”
supportsTotal capacityMechanismStrike / priceDetail
[17]
Parkwind2024-03-20◆ Ventyr secures winning bid in norwegian …
“With the first turbines expected to be operational by 2030, this 1.5GW wind farm will play a crucial role in advancing the country's renewable energy transition.”
supportsFirst power
Auction results1
[18]
Norwegian Ministry of Energy (regjeringen.no)2026-06-22◆ no-sorlige-nordsjo-ii-2024-snii-cfd
Sorlige Nordsjo II CfD contract: NOK 2bn post-award guarantee, NOK 1m/day delay fine, NOK 2bn Fastholdelsesbot
supportsTender award · Sørlige Nordsjø II (phase 1)
Trade press7
[10]
Ventyr2024
“Ingka Investments, the investment arm of Ingka Group – the largest IKEA Retail operator – is to join the Ventyr consortium, taking a 49 percent stake in the consortium.”
supportsowner
[11]
4C Offshore2025
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[12]
NS Energy2025
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[13]
The Wind Power2025
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[14]
Offshore Wind Design AS2025
supportsDistance from shore
[15]
GEBCO Compilation Group2020
supportsWater depth
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown◆ Announcement of competition for a projec…
supportsTotal capacityWater depthDistance from shoreCoordinates