Gemini

Located ~85 km north of the Wadden Islands. Largest Dutch offshore wind farm by capacity at commissioning. Construction budget EUR 2.8bn.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2014’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted 2013 View the source for Final investment decisionFinal investment decision May 2014 View the source for Onshore constructionOnshore construction 2015 View the source for Offshore constructionOffshore construction Jul 2015 View the source for First powerFirst power Feb 2016 View the sources for Commercial operationCommercial operation 28 Apr 2017 — stake not disclosed · closed 2014-05 2013-04 JV FORMATIONNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDVan Oord → Alte Leipziger-Hallesche — 10% 2018-04 Transfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYVan Oord Van Oord Van Oord exited 2018-04Alte Leipziger-Hallesche — 10% today Alte Leipziger-Hallesche Alte Leipziger-Hallesche 10%Northland Power — 60% today · operator Northland Power Northland Power 60%Siemens Financial Services — 20% today Siemens Financial Servi… Siemens Financial Servi… 20%HVC Groep — 10% today HVC Groep HVC Groep 10%Van Oord → Alte Leipziger-Hallesche — 10% 10%
Dashed tick marks today (9 Sep 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2017-Q22017-04-28 · 2 recorded revisions · held (announced 2017-Q2, unchanged)

Revenue & offtake contract duration and price levels · money of the day

600 MW contracted — feed-in tariff
Feed-in tariff · Regeling windenergie op zee 2009 (SDE offshore subsidy tender)
Priceprice undisclosed ·Capacity600 MWAwardedMay 2010
Term15 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing151150 turbines + 2 platforms expected · 1 fewer than expected — a position the survey missed
Surveyed2026-08-31from 115 satellite passes
Built2015-07 → 2017-04-28offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-06Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed151 confirmed · 0 not yet confirmedas counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortEemshaven ~85km ·quay 5000 m · crane 50 t · draft 14 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-06
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (151)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Gemini, 2026-09-06
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationBuitengaats (Gemini OHVS)·in service 2017 · owner Gemini (the wind farm project company — NOT TenneT)
Offshore substationZeeEnergie (Gemini OHVS)·in service 2017 · owner Gemini (the wind farm project company — NOT TenneT)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2017201820192020202120222023202420252026developer’s stated start 2017-04nowBuitengaats (Gemini OHVS)Buitengaats (Gemini OHVS)in service 2017in service 2017ZeeEnergie (Gemini OHVS)ZeeEnergie (Gemini OHVS)in service 2017in service 2017

Sources & verification

15/18 fields verified · rests on 11 sources (6 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
RVO / Bureau Energieprojecten (Rijksdienst voor Ondernemend Nederland)2013◆ Aansluiting wind op zee - Gemini (RVO cl…
“Inpassingsplan onherroepelijk: 17 augustus 2013. Inpassingsplan inwerkingtreding: 17 augustus 2013. [...] Buitengaats CV en ZeeEnergie CV [...] bouwen twee naast elkaar gelegen offshore windparken in …”
supportsConsentStatusConnection pointportConsent granted
[3]
Noordzeeloket (Rijkswaterstaat / Ministry of Infrastructure and Water Management)◆ Windenergiegebied Ten noorden van de Wad…
“Gemini Buitengaats en ZeeEnergie / In gebruik vanaf / 2017 / In gebruik tot / 2036 / Aantal turbines / 150 / Vermogen turbine (MW) / 4 / Vermogen windpark (MW) / 600 / Oppervlakte (km2) / 70 / Exploit…”
supportsTurbinesUnit capacityTotal capacity
Operator3
[2]
Ministerie van Economische Zaken (Dutch Government)2009-11-24◆ Staatscourant 2009, 17851 - Procedure SD…
“Regeling van de Minister van Economische Zaken van 18 november 2009, nr. WJZ/9203919, tot aanwijzing van productie-installaties voor het opwekken van hernieuwbare elektriciteit met behulp van windener…”
supportsMechanismDetail
[4]
Northland Power Inc.
“Located 85 km off the Netherlands coast in the North Sea. Water depth: 28-36 meters. 150x Siemens 4 MW turbines. Financial close: May 2014. First turbine connected: February 2016. Full completion: Apr…”
supportsFirst powerCommercial operationModelUnit capacityWater depth+1 more
[5]
Northland Power Inc.2017-04-28◆ Northland Power's Gemini Offshore Wind F…
“Northland Power's Gemini Offshore Wind Farm Achieves Full Project Completion [...]. The project achieved full completion on April 28, 2017 [...] All turbines have been operating since October 2016. [.…”
supportsCommercial operationCOD history
Auction results1
[13]
Overheid.nl (Ministerie van Economische Zaken)2009-11-18◆ nl-regeling-wind-op-zee-2009
"Het subsidieplafond ... bedraagt EUR 5.384.817.810,00. De Minister verdeelt het bedrag ... op volgorde van rangschikking van de aanvragen." / "Aanvragen ... worden ontvangen in de periode van 4 janua…
supportsFeed-in tariff · Regeling windenergie op zee 2009 (SDE offshore subsidy tender)
Trade press4
[6]
Offshore Wind (offshorewind.biz)2014-05-15◆ Dutch Gemini Becomes Largest-Ever Projec…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[7]
Offshore Wind (offshorewind.biz)2015-07-02◆ Gemini: First Foundation Installed | Off…
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionSite rightsFoundation
[9]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Encyclopaedic1
[10]
Wikipedia2026-07-02
supportsCoordinates