Emerald

One of Ireland's largest proposed floating wind projects, located off the south coast of Cork near the decommissioned Kinsale gas field.

Technology
Capacity 1,300 MW 
Turbines
Foundation Floating 
Site & conditions
Site rights Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project 
Origination Simply Blue Group  Water depth 26–88 m  Wind speed 10.0 m/s @ 150 m 
Revenue & grid
Offtake Other 
Grid
Schedule
FID Not taken
COD · developer

Delivery outlook not forecast

We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.

Revenue & offtake route to market — open

No offtake secured — route to market open

Awaiting Irish ORESS auction allocation — project in early development.

The routes describe what exists in this market — not a prediction of which the project will take.
Next visible round · from the auction calendar
South Coast DMAP Area B (Lí Ban)
expected — · planned · the round’s published documents do not name this project
indicative

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

4/12 fields verified · rests on 5 sources (2 primary) · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator2
[1]
EDF Renewables Ireland2023-05-31◆ EDF Renewables Ireland and Simply Blue G…
“EDF Renewables Ireland and Simply Blue Group … sign partnership deal on Western Star and Emerald floating offshore wind projects in Ireland … 50:50 joint venture … Emerald: up to 1.3GW, off the south …”
supportsoperatordeveloperTotal capacityFoundation
[2]
Simply Blue Energy (formerly Simply Blue Group)2025
“The Emerald Project is a 1.3 GW floating offshore wind development located off the south coast of Cork, Ireland, in the vicinity of the decommissioned Kinsale gas field. The team are engaged with Gove…”
supportsConsentMechanismDetailCoordinatesOfftake history
Auction pipeline1
[7]
Government of Ireland (gov.ie)2024-05◆ govie-future-framework
Future Framework — plan-led DMAP auctions; South Coast DMAP sites beyond Tonn Nua to be brought to market.
supportsSouth Coast DMAP Area B (Lí Ban)
Trade press2
[5]
GEBCO Compilation Group2020
supportsWater depth
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed