Eoliennes Flottantes d'Occitanie (EFLO - Narbonnaise)
AO6 Round 6 project. One of two Mediterranean floating wind sites awarded under AO6.
Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
Location
Mediterranean Sea
Technology
Capacity
250 MW ◇
Turbines
—
Foundation
Floating ◇
Site & conditions
Site rights
Seabed rights held ∴
Origination
France Offshore Wind AO6 (Mediterranean floating) · 2024 ·
Water depth
7–34 m ≈
Distance from shore
25 km ◇
Wind speed
9.9 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · €92.7/MWh ◇
Grid
No agreement · 2025-09 ◇
Connection
RTE grid connection. Eiffage (via Smulders) contracted by RTE … ◇
Schedule
FID
Not taken
COD · announced
2031 ◇
COD · Hafrok
2031 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2031
expected year of commercial operation
Chance of delivery
≈83%
estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2030 | 3.9% |
| 2031 (expected) | 50.2% |
| 2032 | 29.5% |
| 2033 | 10.6% |
| 2034 | 3.8% |
| 2035 | 1.4% |
| 2036 | 0.6% |
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in
2026. From there Hafrok adds how long similar projects (floating, in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2032; the faster quarter of similar projects would be done by 2030, the slower quarter not until 2032 Q3.3
Result
Expected commercial operation
2031, likely range 2030–2033 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈83%, which rates it
Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2024-12
France Offshore Wind AO6 (Mediterranean floating)
- Awarded to
- Ocean Winds + Eolien en Mer Participation
- Basis
- integrated tender
Founding JV · 2024-12
Ocean Winds · Banque des Territoires — The French government awarded the AO6 Mediterranean floating wind tender to a consortium of Ocean Winds (50-50 JV of EDP Renewables and ENGIE) and Banque des Territoires in December 2024. The project — Eoliennes Flottantes d'Occitanie (EFLO) — is located in the Narbonnaise zone in the Gulf of Lion, more than 25 km from the French coast between Agde (Hérault) and Port-la-Nouvelle (Aude). The benchmark tariff for AO6 was EUR 85.9/MWh. No equity M&A transactions have been publicly disclosed beyond the tender consortium formation. The project builds on experience from Ocean Winds' 30 MW EFGL pilot project in the same zone. Exact ownership split between Ocean Winds and Banque des Territoires is not publicly confirmed. Eiffage was awarded the offshore AC substation EPC contract (September 2025) covering all three AO5/AO6 French floating wind projects.
Evidence
- Ocean Winds — Ocean Winds and Banque des Territoires awarded new 250 MW floating offshore wind project in the French Mediterranean Sea ↗ 2024-12 ◆ held
- offshoreWIND.biz — Consortia Led by EDF, Ocean Winds Win French Floating Wind Tender ↗ 2024-12 ◆ held
From the auction results — the round that created the project; founding JV from Hafrok’s transactions record.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake contract duration and price levels · money of the day
250 MW contracted — tender award
● Tender award · France Offshore Wind AO6 (Mediterranean floating)
Price€92.7/MWh ·Capacity250 MWAwardedDec 2024Term20 yrs
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2031
Construction ports
PortPort-la-Nouvelle ◇·likely marshalling · quay 250 m · draft 11 m
Sources & verification
0/15 fields verified · rests on 11 sources (1 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[1]
Ocean Winds2024-12◆ Ocean Winds and Banque des Territoires a…
“Ocean Winds, in partnership with Banque des Territoires, has been awarded the Eoliennes Flottantes d'Occitanie project by the French Ministry in charge of Industry and Energy. The project has a total …”
supportsoperatorownerConsentCommercial operationTotal capacity+1 more
[6]
Ocean Winds2025◆ Éoliennes Flottantes d’Occitanie - Ocean…
“Eoliennes Flottantes d'Occitanie (EFLO) [...] around 250 MW [...] Gulf of Lion, Mediterranean Sea [...] one of the windiest areas in France, with average wind speeds close to 10 m/s [...] Port-La Nouv…”
supportsTotal capacitylikely marshalling
[10]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 805 (node--type-project) at /facades-maritimes-en-france/facade-mediterranee/projets-en-mediterranee/Narbonnaise/Narbonnaise-1 — title 'Narbonnaise Sud-Hérault 1'; page text 13832 chars,…”
supportsRegister entry
Auction results1
[11]
CRE (Commission de regulation de l'energie) / DGEC2024◆ fr-ao6-cahier-des-charges
AO6 cahier des charges ("FLOTTANTES DE MEDITERRANEE") - two floating farms in the Golfe du Lion.
supportsTender award · France Offshore Wind AO6 (Mediterranean floating)
Trade press7
[2]
French Ministry of Industry and Energy2024-12-27◆ Construction et l’exploitation de deux p…
“Les deux lauréats des deux zones [...] la zone « Narbonaise » [...] Ocean Winds et Eolien en Mer Participation [...] plus de 25 kilomètres des côtes françaises, entre Agde (Hérault) et Port-la-Nouvell…”
supportsDistance from shore
[3]
Offshore Wind Biz2024-12-27
Press report — cited, not quoted; read it at the source link.
supportsBackground
[4]
Energies de la Mer2024-12-30
“le projet « Éoliennes Flottantes d'Occitanie – EFLO » d'Ocean Winds (Engie et EDPR) et de la Banque des territoires (Eolien en Mer Participation) est au tarif de 92,70€/MWh”
supportsMechanismStrike / priceDetail
[5]
Eiffage2025-09-30
“Eiffage has been awarded the contract for three substations for the Bretagne Sud, Narbonnaise Sud-Hérault and Golfe de Fos French offshore wind farms, worth more than €1.5 billion.”
supportsStatusConnection point
[7]
[8]
[9]