Centre Manche 1

AO4 Round 4 project. France's first 1 GW offshore wind farm. Located off the coast of Manche and Calvados departments in Normandy, covering 183 km2.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
EDF Renewables — 50% 
MSMaple Power SAS — 50% 
Location
France
English Channel
Technology
Capacity 1,000 MW 
Turbines
Foundation
Site & conditions
Site rights Seabed rights held 
Origination France Offshore Wind AO4 (Centre Manche 1) · 2023 ·
Water depth 41–49 m  Distance from shore 32 km  Wind speed 9.4 m/s @ 150 m 
Revenue & grid
Offtake CfD · €44.9/MWh  Grid Applied · 2025-09  Connection HVDC grid connection planned. RTE ordered EUR 4.5B substations … 
Schedule
FID Not taken
COD · announced 2032 
COD · Hafrok 2032 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2032
expected year of commercial operation
Chance of delivery
≈81% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record, its size and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2031: 3.9% (conditional on completion) 2032: 50.2% (conditional on completion) 2033: 29.5% (conditional on completion) 2034: 10.6% (conditional on completion) 2035: 3.8% (conditional on completion) 2036: 1.4% (conditional on completion) 2037: 0.6% (conditional on completion)2026now20272028202920302031203250%20332034203520362037 Developer-announced COD: 2032 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2032
COD probability by year, conditional on completion
YearProbability
20313.9%
2032 (expected)50.2%
203329.5%
203410.6%
20353.8%
20361.4%
20370.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
Result
Expected commercial operation 2032, likely range 2029–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈81%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2023’24’25’26’27’28’29’30’31’32Developer-announced COD: 2032 announced COD 2032France Offshore Wind AO4 (Centre Manche 1) — awarded to Éoliennes en Mer Manche Normandie (EDF Renouvelables + Maple Power)France Offshore Wind AO4 (Centre Manche 1) Mar 2023 · auction recordView the source for Consent appliedConsent applied Mar 2025 Commercial operation 2032 ·Hafrok expectedFrance Offshore Wind AO4 (Centre Manche 1) — awarded to Éoliennes en Mer Manche Normandie (EDF Renouvelables + Maple Power) 2023-03 ORIGINATIONTODAYEDF Renewables — 50% today · operator EDF Renewables EDF Renewables 50%Maple Power SAS — 50% today · co-developer Maple Power Maple Power 50%France Offshore Wind AO4 (Centre Manche 1) — awarded to Éoliennes en Mer Manche Normandie (EDF Renouvelables + Maple Power)
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

1,000 MW contracted — tender award
Tender award · France Offshore Wind AO4 (Centre Manche 1)
Price€44.9/MWh ·Capacity1,000 MWAwardedMar 2023
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2032
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemCentre Manche 1 HVDC (Offshore)·1250 MW · ±320 kV · ordered, expected 2031
HVDC systemCentre Manche 1 HVDC (Onshore — Menuel)·1250 MW · ±320 kV · ordered, expected 2031
Export & onshore
Export cableCentre Manche 1 Export Cable·HVDC subsea · Nexans · planned · to Menuel (onshore converter)
Onshore connectionMenuel Converter Station (Centre Manche 1)·320 DC / 400 AC kV · planning
Converter supplierHitachi Energy·Centre Manche 1 HVDC (Offshore) · Chantiers de l'Atlantique (Saint-Nazaire) · for RTE
Converter supplierHitachi Energy·Centre Manche 1 HVDC (Onshore — Menuel) · Chantiers de l'Atlantique (Saint-Nazaire) · for RTE
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2026202720282029203020312032Hafrok expects the farm to start in 2032developer’s stated start 2032nowCentre Manche 1 HVDC (Offshore)Centre Manche 1 HVDC (Offshore)expected 2031expected 2031Centre Manche 1 HVDC (Onshore — Menuel)Centre Manche 1 HVDC (Onshore — M…expected 2031expected 2031Menuel Converter Station (Centre Manche 1)Menuel Converter Station (Centre …expected 2031expected 2031Centre Manche 1 Export CableCentre Manche 1 Export Cableexpected 2031expected 2031

Sources & verification

4/12 fields verified · rests on 15 sources (9 primary) · ◆ 6 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[7]
Prefecture de la Manche (France)2025-11-26
“Enquete publique unique — Raccordement parc eolien en mer Centre-Manche 1. Periode: du mardi 2 septembre 2025 au mardi 14 octobre 2025. Conclusions et Avis sur la demande de Declaration d'Utilite Publ…”
supportsStatusConnection point
Operator7
[3]
Ministere de la Transition Ecologique (France)2023-03-27◆ Eolien en mer : Agnès Pannier-Runacher p…
“Eoliennes en Mer Manche Normandie, laureat de l'appel d'offres Centre Manche 1 (AO4), pour une capacite de 1 000 MW. Le tarif propose est tres competitif et demontre une fois de plus la maturite de la…”
supportsTotal capacity
[5]
Energy Connects2025-10
“Guaranteed power price: 44.90 euros per megawatt-hour (with inflation adjustments). Capacity: 1 gigawatt. Construction scheduled to start in 2028. EDF has already committed nearly 100 million euros to…”
supportsMechanismStrike / priceDetail
[6]
Eoliennes en Mer Manche Normandie (EMMN) — project developer2026-06◆ Découvrir le projet - Parc éolien en mer…
“Horizon 2032 — date de mise en service prevue.”
supportsConsentCommercial operationConsent applied
[8]
Offshore Wind Biz2023-03-27
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[9]
Maple Power2026-06
“Centre Manche 1 — 1GW project, scheduled completion 2032. Owned by EDF Renewables and Maple Power SAS. Maple Power is a joint venture between Enbridge Inc. and Canada Pension Plan Investment Board (CP…”
supportsCommercial operation
[15]
Nexans2025-03-25◆ Nexans wins major frame agreement with r…
“Nexans has secured a major framework agreement with RTE for the design, manufacturing, and supply of HVDC cables, which will be used to connect the Centre Manche 1 & 2 and Oléron offshore wind farms t…”
supportsStatusConnection point
[16]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 803 (node--type-project) at /facades-maritimes-en-france/facade-manche-mer-du-nord/projet-centre-manche/centre-manche-1 — title 'Centre Manche 1'; page text 5640 chars, hash 190184929b88…”
supportsRegister entry
Auction results1
[17]
CRE (Commission de regulation de l'energie) / DGEC2023◆ fr-ao4-deliberation
AO4 Centre Manche 1 - CRE deliberation 2023-77 instructing the offers (dialogue concurrentiel n.1/2020, ~1,050 MW off Normandy). (The standalone AO4 cahier-des-charges URL redirected to AO2; deliberat…
supportsTender award · France Offshore Wind AO4 (Centre Manche 1)
Trade press5
[10]
Enbridge2023-03
supportsoperatorco-developer
[11]
offshoreWIND.biz2023-03
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityDistance from shore
[12]
Global Energy Monitor2026-07-02
supportsCoordinates
[13]
GEBCO Compilation Group2020
supportsWater depth
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown◆ France Selects EDF and Maple Power to Bu…
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityDistance from shoreCoordinates