Vesterhav Nord & Syd

Vesterhav Nord (176 MW, 21 turbines) off Harboore/Thyboron + Vesterhav Syd (168 MW, 20 turbines) off Ringkobing.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2017’18’19’20’21’22’23’24’25’26Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/SVesterhav Nord & Syd (Danish near-shore tender) Sep 2016 · auction recordView the source for Consent grantedConsent granted Dec 2020 View the source for Final investment decisionFinal investment decision Dec 2021 View the source for Offshore constructionOffshore construction Feb 2023 View the source for First powerFirst power Nov 2023 View the sources for Commercial operationCommercial operation Mar 2024 Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/S 2016-09 ORIGINATIONVattenfall → Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) — stake not disclosed · closed 2023-07 2023-Q2 FARMDOWNTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYVattenfall — 92% today · operator Vattenfall Vattenfall 92%Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) Local residents and hol… Local residents and hol… exited 2023-Q2Community shareholders — 8% today · community Community shareholders Community shareholders 8%Vesterhav Nord & Syd (Danish near-shore tender) — awarded to Vattenfall Vindkraft A/S Vattenfall → Local residents and holiday-home owners (Ringkøbing-Skjern Municipality) — stake not disclosed · closed 2023-07 Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 20202020202020232024-Q12024-03 · 6 recorded revisions · slipped +3.7 yr (first announced 2020)

Revenue & offtake contract duration and price levels · money of the day

350 MW contracted — tender award
Tender award · Vesterhav Nord & Syd (Danish near-shore tender)
Price47.5 DKK_ore/kWh ·Capacity350 MWAwardedSep 2016

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations41 of 41100% · first seen 2023-02-28
Turbines41 of 41100% · first seen 2023-06-09
Latest count2025-12-31from 429 satellite passes · 0 substation platforms left out so the counts compare with the turbine number · the count has ended: the build is complete
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (41 turbines + 0 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
1020304041 planned (turbines and platforms)latest count 2025-12-31foundations — running total, confirmedFeb 2023 — 4 this month · 4 in totalMar 2023 — 14 this month · 18 in totalApr 2023 — 23 this month · 41 in totalJun 2023 — 0 this month · 41 in totalJul 2023 — 0 this month · 41 in totalAug 2023 — 0 this month · 41 in totalSep 2023 — 0 this month · 41 in totalOct 2023 — 0 this month · 41 in totalNov 2023 — 0 this month · 41 in totalDec 2023 — 0 this month · 41 in totalApr 2024 — 0 this month · 41 in totalturbines up — running total, confirmedFeb 2023 — 0 this month · 0 in totalMar 2023 — 0 this month · 0 in totalApr 2023 — 0 this month · 0 in totalJun 2023 — 1 this month · 1 in totalJul 2023 — 4 this month · 5 in totalAug 2023 — 10 this month · 15 in totalSep 2023 — 10 this month · 25 in totalOct 2023 — 8 this month · 33 in totalNov 2023 — 5 this month · 38 in totalDec 2023 — 2 this month · 40 in totalApr 2024 — 1 this month · 41 in total41 foundations41 turbines upFeb 2023Apr 2023Jul 2023Sep 2023Nov 2023Apr 2024
Satellite image
Image taken2026-09-06Copernicus Sentinel-1 radar satellite, southbound pass · 3 newer passes skipped because the satellite’s track only caught part of the farm (the best of them 76%)
Farm covered100%the whole farm lies inside the image
Structures ringed41 confirmed · 0 not yet confirmedas counted on 2025-12-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Thyboron foundation marshalling
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-06
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (41)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Vesterhav Nord & Syd, 2026-09-06
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 0
Offshore substationNone by design·nearshore direct-to-shore design; turbine cables run to onshore coastal collection stations (Nord: Klinkby, then Idomlund; Syd: near the coast, then Stovstrup) — Energinet

Sources & verification

15/16 fields verified · rests on 13 sources (12 primary) · ◆ 9 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator7
[1]
Vattenfall2024-09-12◆ Danish offshore wind farms Vesterhav Nor…
“Danish offshore wind farms Vesterhav Nord and Vesterhav Syd inaugurated … combined installed capacity of 344 MW … 1.5 TWh fossil-free electricity … 5.5 to 10 kilometres … service facility at Hvide San…”
supportsCommercial operationTotal capacityDistance from shore
[2]
Vattenfall2021-12-15◆ Vattenfall gives go-ahead for Vesterhav …
“With the final investment decision at a value of 769 MEUR, Vattenfall and its suppliers initiated the last stage of the development of the two offshore wind farms ... combined installed capacity of 34…”
supportsFinal investment decisionTurbinesUnit capacity
[4]
Vattenfall2023-11-10◆ Vattenfall supplies first power from Den…
“On 10 November, the first power from Vattenfall's offshore wind farm Vesterhav Syd was supplied to the Danish power grid.”
supportsFirst power
[5]
Vattenfall2024-01-09◆ Vattenfall connects Danish offshore wind…
“Every single turbine at the offshore windfarm Vesterhav Syd has now supplied the first power and the offshore wind farm is now completely connected to the Danish power grid - initial power delivery oc…”
supportsCommercial operationStatusConnection point
[8]
Vattenfall2024◆ Power plants: Vesterhav Nord - Vattenfal…
“Vattenfall ownership share 92% … between 5.5 and 8.4 kilometres from Thyborøn and Ferring Sø on the Jutland coast … 21 units … 176 MWe.”
supportsoperatorcommunityTotal capacity
[11]
Vattenfall2016-09-12◆ Vattenfall wins Danish Near Shore Wind  …
“Vattenfall has won the Danish Near Shore Wind Tender (DNS) … the outcome of the tender is based on Vattenfall delivering the lowest bid of 0,475 kr/kWh … Vattenfall will now develop two wind farms wit…”
supportsMechanismStrike / priceDetail
[15]
Vattenfall2023-03-31
“Vattenfall afslutter fundamenter til Vesterhav Syd – nu begynder arbejdet i nord ... Siden den 20. februar har installationsskibet "DEME Innovation" nedrammet 20 monopæle i Vesterhav Syd havmøllepark …”
supportsOffshore construction
OEM1
[3]
Siemens Gamesa Renewable Energy2021-12-15◆ Delivering in Denmark: Siemens Gamesa re…
“41 SG 8.0-167 Direct Drive offshore wind turbines … Vesterhav Nord: 21 SG 8.0-167 DD offshore wind turbines … Vesterhav Syd: 20 SG 8.0-167 DD offshore wind turbines … A three-year Service agreement, w…”
supportsTurbinesModelUnit capacityFoundation
Auction results1
[20]
AURES II / DTU2026-06-22◆ dk-vesterhav-near-shore-aures
AURES II Denmark case study: two-sided sliding-premium CfD vs day-ahead spot, FLH cap, DKK 100m guarantee, support-volume clawback
supportsTender award · Vesterhav Nord & Syd (Danish near-shore tender)
Trade press4
[7]
Offshore Wind Biz2024-09-12
Press report — cited, not quoted; read it at the source link.
supportsConsentTurbinesUnit capacityTotal capacityStatus+2 more
[10]
Thyboron Port2023
“Thyboron Port was selected as the marshalling base for installing 41 foundations supporting 8.4 MW Siemens Gamesa offshore wind turbines … 41 monopiles (77 m long, ~622 tonnes each) … proximity to the…”
supportsFoundationWater depthfoundation marshalling
[14]
offshoreWIND.biz2024-03-12◆ Vattenfall Links Vesterhav Nord to Danis…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD history
[16]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed